VALDOSTA, GA —
OSHA Inspection: JAMES SMITH
Unprogrammed Other inspection · Safety discipline
At a glance
On , OSHA opened an unprogrammed Other safety inspection of JAMES SMITH in 3295 INNER PERIMETER RD, VALDOSTA, GA 31601 (NAICS 238140). OSHA activity number 336117783.
Where did this inspection happen?
- Establishment
- JAMES SMITH
- Site address
- 3295 INNER PERIMETER RD
- City
- VALDOSTA
- State
- GA
- ZIP
- 31601
- Mailing
- 540 SAND RIDGE LANE, NASHVILLE, GA 31639
What kind of inspection was it?
- Inspection type
- Unprogrammed Other (I)
- Scope
- Complete (A)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238140
- Employees
- 6
- Ownership type
- A
Citations
9 citations on file for this inspection.
1926.451 B01
- Issued
- Abate by
- Penalty
- Initial $2800.00 · Current $667.00 Reduced
General-duty citation text
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds shall be fully planked or decked between the front uprights and the guardrail supports as follows: a) North side of the building - on or about August 30, 2012, several employees were exposed to fall hazard while performing work from the 3rd level of a tubular welded frame scaffold. This section of the scaffold was not fully planked, exposing the employee up to an 18-foot fall hazard. ABATEMENT CERTIFICATION AND DOCUMENTATION ARE REQUIRED
Recent events (2)
- — I (S) $667
- — Z (S) $2800
1926.451 E01
- Issued
- Abate by
- Penalty
- Initial $2800.00 · Current $667.00 Reduced
General-duty citation text
29 CFR 1926.451(e)(1): When scaffold platforms are more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from another scaffold, structure, personnel hoist, or similar surface shall be used. Crossbraces shall not be used as a means of access. a) North side of the building - on or about August 30, 2012, several employees were observed working from a tubular welded frame scaffold without a ladder or any other means of safe access/egress, exposing them up to a 18-foot fall hazard. b) South side of the building - on or about August 30, 2012, two employees were observed working from a tubular welded frame scaffold without a ladder or any other means of safe access/egress, exposing them up to a 14-foot fall hazard. ABATEMENT CERTIFICATION AND DOCUMENTATION ARE REQUIRED
Recent events (2)
- — I (S) $667
- — Z (S) $2800
1926.451 F07
- Issued
- Abate by
- Penalty
- Initial $2800.00 · Current $667.00 Reduced
General-duty citation text
29 CFR 1926.451(f)(7): Scaffolds shall be erected, moved, dismantled, or altered only under the supervision and direction of a competent person qualified in scaffold erection, moving, dismantling or alteration. Such activities shall be performed only by experienced and trained employees selected for such work by the competent person. a) At the construction site - on or about August 30, 2012, the tubular welded frame scaffolding that employees work from did not have guardrails, ladder, no uplift pins, not fully planked and employees were not trained, which indicated the competent person was not adequately qualified in the erection, moving, and altering of the scaffold. ABATEMENT CERTIFICATION AND DOCUMENTATION ARE REQUIRED
Recent events (2)
- — I (S) $667
- — Z (S) $2800
1926.451 G01
- Issued
- Abate by
- Penalty
- Initial $2800.00 · Current $667.00 Reduced
General-duty citation text
29 CFR 1926.451(g)(1): Each employee on a scaffold more than 10 feet (3.1 m) above a lower level shall be protected from falling to that lower level. Paragraphs (g)(1)(i) through (vii) of this section establish the types of fall protection to be provided to the employees on each type of scaffold. Paragraph (g)(2) of this section addresses fall protection for scaffold erectors and dismantlers. Note to paragraph (g)(1): The fall protection requirements for employees installing suspension scaffold support systems on floors, roofs, and other elevated surfaces are set forth in subpart M of this part. a) North side of the building - on or about August 30, 2012, several employees were observed working from a tubular welded frame scaffold without guardrails and no other means of fall protection, exposing them up to a 18-foot fall hazard. b) South side of the building - on or about August 30, 2012, two employees were observed working from a tubular welded frame scaffold without guardrails and no other means of fall protection, exposing them up to a 14-foot fall hazard. ABATEMENT CERTIFICATION AND DOCUMENTATION ARE REQUIRED
Recent events (2)
- — I (S) $667
- — Z (S) $2800
1926.452 C04
- Issued
- Abate by
- Penalty
- Initial $2800.00 · Current $667.00 Reduced
General-duty citation text
29 CFR 1926.452(c)(4): Where uplift can occur which would displace scaffold end frames or panels, the frames or panels shall be locked together vertically by pins or equivalent means. a) North side of the building - on or about August 30, 2012, a tubular welded frame scaffold, 3 sections high, was missing pins that secure each section together, exposing employees up to an 18-foot fall hazard. ABATEMENT CERTIFICATION AND DOCUMENTATION ARE REQUIRED
Recent events (2)
- — I (S) $667
- — Z (S) $2800
1926.454 A
- Issued
- Abate by
- Penalty
- Initial $2800.00 · Current $665.00 Reduced
General-duty citation text
29 CFR 1926.454(a): The employer shall have each employee who performs work while on a scaffold trained by a person qualified in the subject matter to recognize the hazards associated with the type of scaffold being used and to understand the procedures to control or minimize those hazards. The training shall include the following areas, as applicable: a) North side of the building - on or about August 30, 2012, several employees were observed working from a tubular welded frame scaffold without being trained, exposing them up to an 18-foot fall hazard. ABATEMENT CERTIFICATION AND DOCUMENTATION ARE REQUIRED
Recent events (2)
- — I (S) $665
- — Z (S) $2800
1910.1200 E01
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1910.1200(e)(1): Employers shall develop, implement, and maintain at each workplace, a written hazard communication program which at least describes how the criteria specified in paragraphs (f), (g), and (h) of this section for labels and other forms of warning, safety data sheets, and employee information and training will be met, and which also includes the following: a) At the construction site- on or about August 30, 2012, the employer did not develop a written hazard communication program for chemicals used by employees at the job site. ABATEMENT CERTIFICATION IS REQUIRED
Recent events (2)
- — I (O) $0
- — Z (O) $0
1910.1200 G01
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1910.1200(g)(1): Chemical manufacturers and importers shall obtain or develop a safety data sheet for each hazardous chemical they produce or import. Employers shall have a safety data sheet in the workplace for each hazardous chemical which they use. a) At the construction site- on or about August 30, 2012, the employer did not have material safety data sheet (MSDS) for hazardous chemicals such as, Scruggs Type S mortar cement mix. ABATEMENT CERTIFICATION IS REQUIRED
Recent events (2)
- — I (O) $0
- — Z (O) $0
1910.1200 H01
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1910.1200(h)(1): Employers shall provide employees with effective information and training on hazardous chemicals in their work area at the time of their initial assignment, and whenever a new chemical hazard the employees have not previously been trained about is introduced into their work area. Information and training may be designed to cover categories of hazards (e.g., flammability, carcinogenicity) or specific chemicals. Chemical-specific information must always be available through labels and safety data sheets. a) At the construction site - on or about August 30, 2012, the employer did not provide information and training to employees who work with hazardous chemicals such as, Scruggs Type S mortar cement mix. ABATEMENT CERTIFICATION IS REQUIRED
Recent events (2)
- — I (O) $0
- — Z (O) $0
More inspections at JAMES SMITH
BILOXI, MS—2021-06-24 00:00:00
JAMES SMITH
View JAMES SMITH's full OSHA safety record →
More inspections in this industry (NAICS 238140)
RENO, NV—2026-07-16
DC MASONRY
WINNETKA, IL—2026-07-15
CHICAGO STUCCO CO.
LODI, NJ—2026-07-15
J & O MASONRY CONTRACTORS
DORAVILLE, GA—2026-07-14
SUDLOW CONCRETE, INC.
FLAGLER BEACH, FL—2026-07-14
PLANET DESIGN SERVICES, INC.
More inspections in GA
GREENSBORO, GA—2026-07-16
PURE BEAUTY FARMS, INC.
FOREST PARK, GA—2026-07-16
POLYNT COMPOSITES USA INC.
AUGUSTA, GA—2026-07-16
GF CASTING SOLUTIONS AUGUSTA, LLC
CHAMBLEE, GA—2026-07-16
U.S. DEPARTMENT OF TREASURY
DECATUR, GA—2026-07-15
PALLETS ACQUISITION LLC
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 336117783.