GREENFIELD, MA —
OSHA Inspection: GREENFIELD PAPER BOX CO., INC
Complaint inspection · Safety discipline
At a glance
On , OSHA opened a complaint safety inspection of GREENFIELD PAPER BOX CO., INC in 55 PIERCE ST, GREENFIELD, MA 01301 (NAICS 322212). OSHA activity number 336593983.
Where did this inspection happen?
- Establishment
- GREENFIELD PAPER BOX CO., INC
- Site address
- 55 PIERCE ST
- City
- GREENFIELD
- State
- MA
- ZIP
- 01301
- Mailing
- 55 PIERCE ST, GREENFIELD, MA 01301
What kind of inspection was it?
- Inspection type
- Complaint (B)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 322212
- Employees
- 30
- Ownership type
- A
Citations
11 citations on file for this inspection.
1910.23 D01
- Issued
- Abate by
- Penalty
- Initial $2100.00 · Current $1050.00 Reduced
General-duty citation text
29 CFR 1910.23(d)(1):Every flight of stairs having four or more risers was not equipped with standard stair railings or standard handrails: (a) 55 Pierce St Greenfield, MA: On or about May 16, 2012, a wooden stairway with 4 risers that is used to clean and service the box folder machine was not equipped with railings or handrails.
Recent events (2)
- — I (S) $1050
- — Z (S) $2100
1910.157 C01
- Issued
- Abate by
- Penalty
- Initial $2100.00 · Current $1050.00 Reduced
General-duty citation text
29 CFR 1910.157(c)(1):The employer did not provide portable fire extinguishers and shall mount, locate and identify them so that they are readily accessible to employees without subjecting the employees to possible injury: (a) 55 Pierce St Greenfield, MA: On or about May 16, 2012, wall/post mounted fire extinguishers in 3 separate locations on the facilty floor were observed to not be readily accessible to employees due to materials blocking their access.
Recent events (2)
- — I (S) $1050
- — Z (S) $2100
1910.147 C04 II
- Issued
- Abate by
- Penalty
- Initial $4900.00 · Current $2450.00 Reduced
General-duty citation text
29 CFR 1910.147(c)(4)(ii):The procedures did not clearly and specifically outline the scope, purpose, authorization, rules, and techniques to be utilized for the control of hazardous energy, and the means to enforce compliance: (a)MEQ Quad machine at 55 Pierce St Greenfield, MA: On or about May 16, 2012, the procedures for hazardous energy control at this facility, and specifically for this machine were deficient in that it did not address: (a) a specific statement of the intended use of the procedure, (b) specific procedural steps for blocking to control hazardous energy,(c) specific procedural steps for the placement, removal and transfer of lockout devices, and (d) specific requirements for testing and verifying the effectiveness of the energy control measures: Specific abatement documentation that this violation has been corrected must be provided within 10 days of the abatement in accordance with 29 CFR 1903.19(d)(1).
Recent events (2)
- — I (S) $2450
- — Z (S) $4900
1910.147 C05 I
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1910.147(c)(5)(i):Locks, tags, chains, wedges, key blocks, adapter pins, self-locking fasteners, or other hardware were not provided by the employer for isolating, securing or blocking of machines or equipment from energy sources: (a)55 Pierce St Greenfield ,MA: On or about May 2, 2012, an employee suffered serious injuries to her right arm while cleaning glue build up from the on Stokesfeed BF (aka Quad Wrapper) serial #726 when the machine unexpectedly cycled during a maintence procedure and blocking or other means was not provided or used to prevent that energy from creating a hazard to the employee. Specific abatement documentation that this violation has been corrected must be provided within 10 days of the abatement in accordance with 29 CFR 1903.19(d)(1).
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.147 C06 II
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1910.147(c)(6)(ii):The employer did not certify that the periodic inspections have been performed. The certification shall identify the machine or equipment on which the energy control procedure was being utilized, the date of the inspection, the employees included in the inspection, and the person performing the inspection: (a) 55 Pierce St Greenfield, MA: On or about May 16, 2012, the employer had not certified that the periodic inspections regarding hazardous energy control had been been performed: Specific abatement documentation that this violation has been corrected must be provided within 10 days of the abatement in accordance with 29 CFR 1903.19(d)(1).
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.147 C07 I A
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1910.147(c)(7)(i)(A):Each authorized employee did not receive training in the recognition of applicable hazardous energy sources, the type and magnitude of the energy available in the workplace, and the methods and means necessary for energy isolation and control: (a) 55 Pierce St Greenfield, MA: On or about May 16, 2012, employees engaged in activities covered by this subpart had not received training on the appropriate hazardous energy control procedures to prevent the release of hazardous energy during maintenance and repair work on machinery and equipment.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.147 C07 IV
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1910.147(c)(7)(iv):The employer did not certify that employee training has been accomplished and is being kept up to date. The certification shall contain each employee's name and dates of training: (a) 55 Pierce St Greenfield, MA: On or about May 16, 2012, the employer did not have documentation in accordance with this subpart to certify that Hazardous Energy Control Training had been provided to employees: Specific abatement documentation that this violation has been corrected must be provided within 10 days of the abatement in accordance with 29 CFR 1903.19(d)(1).
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.212 A01
- Issued
- Abate by
- Penalty
- Initial $2800.00 · Current $1400.00 Reduced
General-duty citation text
29 CFR 1910.212(a)(1):One or more methods of machine guarding was not provided to protect the operator and other employees in the machine area from hazards such as those created by point of operation, ingoing nip points, rotating parts, flying chips and sparks: (a) Basement maintenance shop at 55 Pierce St Greenfield, MA: On or about May 16, 2012, a Craftsman brand stand mounted drill press was observed to be operated without any guarding on the rotating drill bit.
Recent events (2)
- — I (S) $1400
- — Z (S) $2800
1910.303 B02
- Issued
- Abate by
- Penalty
- Initial $2100.00 · Current $1050.00 Reduced
General-duty citation text
29 CFR 1910.303(b)(2):Listed or labeled equipment was not installed and used in accordance with any instructions included in the listing or labeling: (a) 55 Pierce St Greenfield, MA: On or about May 16, 2012, a relocatable power tap (RPT) was used to power an extension cord that was ran through a partition to power overhead lighting for a loading dock at the facility not in accordance with its intended use.
Recent events (2)
- — I (S) $1050
- — Z (S) $2100
1910.305 A02 I
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1910.305(a)(2)(i):Temporary electrical power and lighting installation(s) 600 volts, nominal, or less were used in prohibited manners: (a) 55 Pierce St Greenfield, MA: On or about May 16, 2012, household type extension cords were used to make permanent electrical connections for the overhead lighting above the Quad Wrapper and for a glue warmer in the rear of the facility.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1904.29 B02
- Issued
- Abate by
- Penalty
- Initial $700.00 · Current $350.00 Reduced
General-duty citation text
29 CFR 1904.29(b)(2):An OSHA 301 Incident Report form, or an equivalent form, for each recordable injury or illness entered on the OSHA 300 Log was not entered within 7 days of the illness or injury: (a) 55 Pierce St Greenfield, MA: On or about May 16, 2012, an employee's injury on May 2, 2012, which required medical treatment and resulted in lost days at work, was not recorded at the time of this inspection.
Recent events (2)
- — I (O) $350
- — Z (O) $700
More inspections at GREENFIELD PAPER BOX CO., INC
GREENFIELD, MA—2019-03-15 00:00:00
GREENFIELD PAPER BOX CO., INC
GREENFIELD, MA—1984-07-24
GREENFIELD PAPER BOX CO INC
Greenfield, MA—1980-06-03
GREENFIELD PAPER BOX CO INC
Greenfield, MA—1975-10-24
GREENFIELD PAPER BOX CO INC
View GREENFIELD PAPER BOX CO., INC's full OSHA safety record →
More inspections in this industry (NAICS 322212)
MINNEAPOLIS, MN—2026-07-08
111554 - GREAT NORTHERN CORPORATION
WOOSTER, OH—2026-07-07
WELCH PACKAGING
BUFFALO, NY—2026-06-30
ENTERPRISE FOLDING BOX COMPANY, INC.
DAYTON, OH—2026-06-10
DAYTON CORRUGATED PACKAGING CORP.
DALLAS, TX—2026-05-20
CORRCHOICE/PCA LLC
More inspections in MA
WORCESTER, MA—2026-07-10
QUINSIGAMOND COMMUNITY COLLEGE
FITCHBURG, MA—2026-07-10
KELLEY WOOD PRODUCTS, INC.
EVERETT, MA—2026-07-10
HORIZON RETAIL CONSTRUCTION INC
NORTON, MA—2026-07-09
DYNAMIC RESIDENTIAL ROOF MARKETING, LLC
NORTON, MA—2026-07-09
LM GENERAL CONSTRUCTION INC.
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 336593983.