OSHA Inspection: WHALEY MACHINE PRODUCTS, INC.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of WHALEY MACHINE PRODUCTS, INC. in 5553 PEACHTREE RD., CHAMBLEE, GA 30341 (NAICS 332710). OSHA activity number 337705610.

Watch Whaley Machine Products, INC. — free Get an email when a new federal OSHA severe-injury report for Whaley Machine Products, INC. is published. One employer, no account, unsubscribe in one click.
Site address
5553 PEACHTREE RD.
City
CHAMBLEE
State
GA
ZIP
30341
Mailing
5553 PEACHTREE RD., CHAMBLEE, GA 30341
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
332710
Employees
11
Ownership type
A

12 citations on file for this inspection.

5(a)(1)

Serious Gravity 5 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $2000.00 · Current $2000.00
OSH ACT of 1970 Section (5)(a)(1):  The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees. Employees were exposed to crush and struck-by hazards:    a) Facility - The Allis-Chalmers LPG-powered forklift did not have a seatbelt installed to restrain workers inside the cabin in case of tip-over.    In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (1)
  • — Z (S) $2000

1910.147 C04 I

Serious Gravity 5 1 instance 4 exposed
Issued
Abate by
Penalty
Initial $2000.00 · Current $2000.00
29 CFR 1910.147(c)(4)(i):     Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section:    a) Plant - Employees performed cleaning, maintenance, and repairs of machinery including (but not limited to) the Federal punch machines, the DoAll band saw, the Komatsu shear, the cutting oil recovery machine, the Lincoln robotic welder, the New Britain bar machines, the Fadal CNC milling machines, and the Acme-Gridley revolver lathes. The employer did not develop, implement, and utilize individual written lockout tagout procedures.     In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (3)
  • — I $1000
  • — Z $5000
  • — Z (S) $2000

1910.147 C07 I

Serious Gravity 5 1 instance 7 exposed
Issued
Abate by
Penalty
Initial $2000.00 · Current $2000.00
29 CFR 1910.147(c)(7)(i):     The employer did not provide adequate training to ensure that the purpose and function of the energy control program was understood by employees:     a) Plant - On or about 11/28/12 employees required to operate and to perform cleaning, maintenance, and repairs of equipment with energy sources that include but are not limited to electrical energy, compressed hydraulic fluid and compressed air, had not been provided with training in reference to control of hazardous energy.      In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (3)
  • — I $1000
  • — Z $5000
  • — Z (S) $2000

1910.212 A03 II

Serious Gravity 5 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $2000.00 · Current $2000.00
29 CFR 1910.212(a)(3)(ii):     Point(s) of operation of machinery were not guarded to prevent employee(s) from having any part of their body in the danger zone(s) during the operating cycle(s):    a) Plant - The point of operation of the Komatsu shear was not guarded in the back of the machine.    In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
  • — Z (S) $2000

1910.303 B01

Serious Gravity 1 4 instances 4 exposed
Issued
Abate by
Penalty
Initial $1200.00 · Current $1200.00
29 CFR 1910.303(b)(1):     Electrical equipment was not free from recognized hazards that were likely to cause death or serious physical harm to employees:    a) Plant - On or about 11/28/12 the junction box in the loading area of the Acme-Gridley revolver lathe was broken. Part of the wall on the right side was missing and the internal conductors were exposed.      b) Plant - On or about 11/28/12 the metallic spiral conduit entering the junction box in the loading area of the Acme-Gridley revolver lathe was broken.  The internal conductors were exposed and subjected to strain.    c) Plant, Cutting oil recovery station - On or about 11/28/12 the flexible cord powering the Dayton 1/2 Ton electric crane was damaged. The outer jacket was broken and covered with electrical tape.    d) Plant, Welding Station #2 - On or about 11/28/12 the flexible power cord for the cooling fan (mounted on the steel column) was damaged.  The outer jacket was broken in proximity of the switch, and the internal conductors were exposed.     In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
  • — Z (S) $1200

1910.305 A02 X

Serious Gravity 1 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $1200.00 · Current $1200.00
29 CFR 1910.305(a)(2)(x):     Flexible cords and cables were not protected from accidental damage, as might be caused, for example, by sharp corners, projections, and doorways or other pinch points:    b) Plant, Welding station #2 - On or about 11/28/12 the blue air circulator mounted on top of the welding table was powered by a spliced flexible power cord which was not installed permanently inside conduits. The cable passed inside the cage and was not protected from the sharp metallic edges of the fan box.     In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
  • — Z (S) $1200

1910.305 B02 I

Serious Gravity 5 3 instances 3 exposed
Issued
Abate by
Penalty
Initial $2000.00 · Current $2000.00
29 CFR 1910.305(b)(2)(i):     Pull boxes, junction boxes, and fittings were not provided with covers approved for the purpose:    a) Plant, Welding station #1 - On or about 11/28/12 the 480V junction box mounted on the wall did not have a cover. Spliced cables and conductor copper parts were exposed.     b) Plant, Robotic welding area - On or about 11/28/12 the 480 V junction box mounted on the wall in proximity of the Lincoln robotic welding machine did not have a cover.  Spliced cables, plastic screw caps, and conductor copper parts were exposed.    c) Plant -  On or about 11/28/12 the junction box in the loading area of the Acme-Gridley revolver lathe #3 did not have a cover.  Cables were exposed.    In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
  • — Z (S) $2000

1910.305 G01 IV A

Serious Gravity 1 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $1200.00 · Current $1200.00
29 CFR 1910.305(g)(1)(iv)(A):     Flexible cords and/or cables were used as a substitute for the fixed wiring of a structure:    a) Plant, Welding station #1 -  On or about 11/28/12  the yellow air circulator mounted on top of the welding table was powered by two spliced flexible cables that were being used as permanent wiring.    b) Plant, Welding station #2 - On or about 11/28/12 the blue air circulator mounted on top of the welding table was powered by a spliced flexible cable that was being used as permanent wiring.     In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
  • — Z (S) $1200

1910.305 G02 II

Serious Gravity 1 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $1200.00 · Current $1200.00
29 CFR 1910.305(g)(2)(ii):     Flexible cords were not used only in continuous lengths without splice or tap:    a) Plant, Welding station #1 -  On or about 11/28/12  the yellow air circulator mounted on top of the welding table was powered by two flexible cords. Each cord was spliced and joined with plastic screw caps.    b) Plant, Welding station #2 - On or about 11/28/12 the blue air circulator mounted on top of the welding table was powerd by a flexible power cord which was spliced and joined with plastic screw caps.     c) Plant, Cutting oil recovery station - On or about 11/28/12 the flexible cord powering the 1/2 Ton electric crane was spliced and joined with plastic screw caps.    In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
  • — Z (S) $1200

1910.132 D02

Other-than-serious 1 instance 7 exposed
Issued
Abate by
Penalty
Initial $0.00 · Current $0.00
29 CFR 1910.132(d)(2):     The employer did not verify, through a written certification, that the required workplace hazard assessment had been performed:    a) Plant - On or about 11/28/12 employees operated, cleaned, and maintained equipment including (but not limited to) CNC milling machines, revolver lathes, shears, punch presses, and welding machines, and handled compressed gases and chemicals.  The employer did not verify through a written certification that the workplace hazards assessment had been performed and kept up to date.     In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
  • — Z (O) $0

1910.178 L06

Other-than-serious 1 instance 2 exposed
Issued
Abate by
Penalty
Initial $0.00 · Current $0.00
29 CFR 1910.178(l)(6):     The employer did not certify that each operator has been trained and evaluated as required by this paragraph (l):    a) Plant - Workers operated the Allis-Chalmers LPG-powered forklift and the employer did not certify that the drivers were trained and evaluated in relation to the safe operation of the vehicle.     In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (3)
  • — I $200
  • — Z $1000
  • — Z (O) $0

1910.1200 H01

Other-than-serious 1 instance 7 exposed
Issued
Abate by
Penalty
Initial $0.00 · Current $0.00
29 CFR 1910.1200(h)(1):     Employees were not provided effective information and training on hazardous chemicals in their work area at the time of their initial assignment and whenever a new hazard that the employees had not been previously trained about was introduced into their work area:    a) Plant - On or about 11/28/12 workers handled and applied chemicals including (but not limited to) compressed air,  compressed argon, liquefied petroleum gas (LPG), cutting oil, lubricant oils and greases. The employer failed to provide employees with Hazard Communication training.     In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (3)
  • — I $200
  • — Z $1000
  • — Z (O) $0

View WHALEY MACHINE PRODUCTS, INC.'s full OSHA safety record →