OSHA Inspection: PIOTR HAJDAS DBA J.P. ROOFING & REMODELING INCORPORATED

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of PIOTR HAJDAS DBA J.P. ROOFING & REMODELING INCORPORATED in 119 PALATINE ROAD, PALATINE, IL 60074 (NAICS 238160). OSHA activity number 337926414.

Watch Piotr Hajdas DBA J.P. Roofing & Remodeling Incorporated — free Get an email when a new federal OSHA severe-injury report for Piotr Hajdas DBA J.P. Roofing & Remodeling Incorporated is published. One employer, no account, unsubscribe in one click.
Site address
119 PALATINE ROAD
City
PALATINE
State
IL
ZIP
60074
Mailing
18W226 16TH STREET, VILLA PARK, IL 60181
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238160
Employees
3
Ownership type
A

4 citations on file for this inspection.

1903.19 C01

Other-than-serious 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $400.00 · Current $400.00
29 CFR 1903.19(c)(1):  The employer did not certify to OSHA, within 10 calendar days after the abatement date, that the cited violation had been abated:    Lugo's Construction, Inc. failed to certify to OSHA within 10 calendar days after the abatement date that each of the following cited violations had been corrected:     Citation Number                     Item Number                           Abatement Date  02                                            01                                            01/17/2013     In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
  • — Z (O) $400

1926.501 B10

Serious Gravity 10 3 instances 1 exposed
Issued
Abate by
Penalty
Initial $2800.00 · Current $1260.00 Reduced
29 CFR 1926.501(b)(10): Each employee engaged in roofing activities on low-slope roofs with unprotected sides and edges 6 feet or more above lower levels, was not protected from falling by guardrail systems, safety net systems, personal fall arrest systems, or a combination of warning line system and guardrail system, warning line system and safety net system, or warning line system and personal fall arrest system, or warning line system and safety monitoring system.  Or, on roofs 50-feet (15.25 m) or less in width, each employee was not protected by use of a monitoring system:    a) Employees were not protected from the hazard of falling approximately 21 feet from the edge of the roof deck while engaged in roofing activities without the use of fall protection or safety monitoring.    In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification.  This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $1260
  • — Z (S) $2800

1926.552 A01

Serious Gravity 5 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $2000.00 · Current $900.00 Reduced
29 CFR 1926.552(a)(1):  The employer did not comply with the manufacturer's specifications and limitations applicable to the operation of all hoists and elevators:    a) A manually operated material handling hoist at the roof edge was counterweighted with rolled roofing materials and not with approved counterweights.    In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (2)
  • — I (S) $900
  • — Z (S) $2000

1926.503 B01

Other-than-serious 3 instances 1 exposed
Issued
Abate by
Penalty
Initial $0.00 · Current $0.00
29 CFR 1926.503(b)(1): The employer did not verify compliance with paragraph (a) of this section by preparing a written (training) certification record including the name or other identity of the employee trained, the date(s) of the training, and the signature of the person who conducted the training or the signature of the employer:    a) The employer did not prepare written certification records related to employee fall protection training.    In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 337926414.