OSHA Inspection: PRECISION WELL SERVICE, INC.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of PRECISION WELL SERVICE, INC. in VAIRA B1 NE NE SEC 35 T25N R54E, LAMBERT, MT 59243 (NAICS 213112). OSHA activity number 339122897.

Watch Precision Well Service, INC. — free Get an email when a new federal OSHA severe-injury report for Precision Well Service, INC. is published. One employer, no account, unsubscribe in one click.
Site address
VAIRA B1 NE NE SEC 35 T25N R54E
City
LAMBERT
State
MT
ZIP
59243
Mailing
P.O. BOX 1140, WATFORD CITY, ND 58854
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
213112
Employees
5
Ownership type
A

2 citations on file for this inspection.

5(a)(1)

Serious Gravity 5 3 instances 1 exposed
Issued
Abate by
Penalty
Initial $3500.00 · Current $2625.00 Reduced
Section 5(a)(1): The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to fall hazards:    a) Vaira B1: On or about June 18, 2013 and at times prior, employees were exposed to an approximate 60 foot fall hazard while working from the derrickman's tubing platform where the employer had installed an emergency egress "Geronimo" safety unit that had the escape line rigged with one wire rope clip at the anchor point.     Among other methods, feasible and acceptable abatement methods to correct the hazard would be for the employer to correctly install and rig the "Geronimo" safety slide ground anchor cable to withstand a pull of at least 3,000 lb. Illustration 2 and 3, pages 10 and 11 of the Manufacturer's Operators Manual contains the statement to use at least three American Petroleum Institute approved cable clamps to secure it in place when a thimble is used to turn back the wire rope and then apply the wire rope clips. When using a sheave, follow the American Petroleum Institute Recommended Practice (API RP) 9B 11th Edition, 2002 Recommended Practice on Application, Care and Use of Wire Rope for Oilfield Service. Section 3.7.4 recommends four wire rope clips to achieve this rating when a sheave is used at the anchor point.        b) Vaira B1: On or about June 18, 2013 and at times prior, employees were exposed to a fall and rapid descent from an emergency escape line where the employer had the emergency escape (Geronimo) safety slide anchor approximately 57 feet from the well bore.     Among other methods, feasible and acceptable abatement methods to correct the hazard would be for the employer to follow the American Petroleum Institute Recommended Practice (API RP 54) Third Edition, August 1999,  Recommended Practice for Occupational Safety for Oil and Gas Well Drilling and Servicing Operations, section 6.10 AUXILIARY ESCAPE, subsection 6.10.1(a). ...it is recommended that the ground anchor point of the escape line should be located a minimum lateral distance from the derrick or mast equal to two times the height of the work platform. The horizontal distance of the anchor point would need to have been at least 208 feet and secured to the anchor point with at least four wire rope clips with a sheave in place.      c) Vaira B1: On or about June 18,, 2013 and at times prior, employees were exposed to an approximate 60 foot fall hazard while working from the derrickman's tubing platform where the employer had installed an emergency egress "Geronimo" safety unit that was installed with the brake handle on the wrong side.     Among other methods, feasible and acceptable abatement methods to correct the hazard would be for the employer to correctly install and rig the "Geronimo" safety slide cart according to Illustrations 9 and 10, pages 17 and 18 of the Manufacturer's Operators Manual.
Recent events (2)
  • — I (S) $2625
  • — Z (S) $3500

1910.151 C

Serious Gravity 5 1 instance 2 exposed
Issued
Abate by
Penalty
Initial $3500.00 · Current $2625.00 Reduced
29 CFR 1910.151(c): Where employees were exposed to injurious corrosive materials, suitable facilities for quick drenching or flushing of the eyes and body were not provided within the work area for immediate emergency use:    a) Well - Vaira B1 Spring lake Field: On June 18, 2013 and at times prior, employee(s) were using and exposed to a corrosive chemical with a pH of 2 (Baker Hughes SCW2600 scale inhibitor). The employer did not have an eyewash unit or other potable water available for employees to flush their eyes and/or skin for 20 to 60 minutes as directed in the material safety data sheet.
Recent events (2)
  • — I (S) $2625
  • — Z (S) $3500

View PRECISION WELL SERVICE, INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 339122897.