OSHA Inspection: JSG GENERAL CONSTRUCTION, LLC

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of JSG GENERAL CONSTRUCTION, LLC in 1818 3RD STREET, NE, WASHINGTON, DC 20002 (NAICS 236118). OSHA activity number 339342800.

Watch JSG General Construction, LLC — free Get an email when a new federal OSHA severe-injury report for JSG General Construction, LLC is published. One employer, no account, unsubscribe in one click.
Site address
1818 3RD STREET, NE
City
WASHINGTON
State
DC
ZIP
20002
Mailing
105 WHEATLEY STREET, KENSINGTON, MD 20895
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
236118
Employees
2
Ownership type
A

3 citations on file for this inspection.

1926.501 B11

Deleted Serious Gravity 10 1 instance 2 exposed
Issued
Abate by
Penalty
Initial $2800.00 · Current $0.00 Reduced
29 CFR 1926.501(b)(11): Each employee on a steep roof with unprotected sides and edges 6 feet (1.8 m) or more above lower levels was not protected from falling by guardrail systems with toeboards, safety net systems, or personal fall arrest systems:  a) Roof - Employees were observed on a roof with a slope of 6/12 while tearing off existing fiberglass shingles and were exposed to a 17 feet, 6 inch fall hazard, on or about 08/21/13.  Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.   For the purposes of this inspection, this employer was determined to be the controlling and correcting employer of the jobsite. The employer is being cited under OSHA's Multi-Employer Workplace Policy.
Recent events (2)
  • — I (S) $0
  • — Z (S) $2800

1926.502 D17

Deleted Serious Gravity 10 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $0.00 · Current $0.00
29 CFR 1926.502(d)(17): The attachment point of the body harness was not located in the center of the wearer's back near shoulder level, or above the wearer's head:  a) Roof - An employee was observed on a steep sloped roof 6/12 while tearing off existing fiberglass shingles and the lanyard was attached to the front of the body harness, on or about 08/21/13.  Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.    For the purposes of this inspection, this employer was determined to be the controlling and correcting employer of the jobsite. The employer is being cited under OSHA's Multi-Employer Workplace Policy.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.1053 B01

Deleted Serious Gravity 5 1 instance 4 exposed
Issued
Penalty
Initial $2000.00 · Current $0.00 Reduced
29 CFR 1926.1053(b)(1): Portable ladders were used for access to an upper landing surface and the ladder side rails did not extend at least 3 feet (.9 m) above the upper landing surface to which the ladder was used to gain access:  (a) Exterior - Employees were observed using a portable extension ladder to gain access to the roof, 17 feet, 6 inches above the ground and the ladder extended 29 inches above the roof landing, on or about 08/21/13.  Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.   For the purposes of this inspection, this employer was determined to be the controlling and correcting employer of the jobsite. The employer is being cited under OSHA's Multi-Employer Workplace Policy.