OSHA Inspection: JAVIER RUIZ HERNANDEZ

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of JAVIER RUIZ HERNANDEZ in 260 LEARWOOD LN LOT #25, LEGEND OAKS SUBDIVISION, ATLANTA, GA 30349 (NAICS 238140). OSHA activity number 339756405.

Watch Javier Ruiz Hernandez — free Get an email when a new federal OSHA severe-injury report for Javier Ruiz Hernandez is published. One employer, no account, unsubscribe in one click.
Site address
260 LEARWOOD LN LOT #25, LEGEND OAKS SUBDIVISION
City
ATLANTA
State
GA
ZIP
30349
Mailing
221 UPPER RIVERDALE ROAD APT 58 F, JONESBORO, GA 30236
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238140
Employees
5
Ownership type
A

7 citations on file for this inspection.

1926.300 B02

Serious Gravity 1 1 instance 1 exposed
Issued
Penalty
Initial $1200.00 · Current $1200.00
29 CFR 1926.300(b)(2): Moving part(s) of equipment exposed to contact by employees or which otherwise created a hazard, were not guarded:  a) At Lot # 25, 260 Learwood Lane, Atlanta, GA- Employees were using a stone cement mixer (Model: 655PM, Serial: 022002202) without a guard over the recoil starter, exposing the employees to laceration hazards.
Recent events (1)
  • — Z (S) $1200

1926.451 B01

Serious Gravity 10 1 instance 3 exposed
Issued
Penalty
Initial $2800.00 · Current $2800.00
29 CFR 1926.451(b)(1): Platform(s) on all working levels of scaffolds, were not fully planked or decked between the front uprights and guardrail supports such that the space between adjacent units, and the space between the platform and the uprights is no more than 1 inch (2.5 cm) wide, and the employer could not demonstrate that a wider space was necessary:   a) At Lot # 25, 260 Learwood Lane, Atlanta, GA- Employees were exposed to fall hazards of approximately 13 feet 9 inches above ground level while installing bricks from a fabricated frame scaffold platform that was not fully planked.
Recent events (1)
  • — Z (S) $2800

1926.451 E01

Serious Gravity 10 1 instance 3 exposed
Issued
Abate by
Penalty
Initial $2800.00 · Current $2800.00
29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used.  Cross braces and end frames not designed for access were used as a means of access.   a) At Lot # 25, 260 Learwood Lane, Atlanta, GA- Employees were utilizing the scaffold cross braces and end frames not designed for access; for access and egress from upper level working platforms exposing themselves to fall hazards of approximately 13 feet 9 inches.
Recent events (1)
  • — Z (S) $2800

1926.451 G01 VII

Serious Gravity 10 1 instance 3 exposed
Issued
Abate by
Penalty
Initial $2800.00 · Current $2800.00
29 CFR 1926.451(g)(1)(vii): Each employee on a scaffold, not otherwise specified in paragraphs (g)(1)(i) through (g)(1)(vi) of this section, more than 10 feet (3.1 m) above lower level was not protected from falls by the use of personal fall arrest systems or guardrail systems meeting the requirements of paragraph (g)(4) of this section.   a)  At Lot # 25, 260 Learwood Lane, Atlanta, GA- The employer did not protect employees from fall hazards while working from a fabricated frame scaffold that did not have guardrails installed on open sides and ends approximately 13 feet 9 inches above ground level.
Recent events (1)
  • — Z (S) $2800

1926.451 H02

Serious Gravity 5 1 instance 1 exposed
Issued
Penalty
Initial $2000.00 · Current $2000.00
29 CFR 1926.451(h)(2): Employees working below a scaffold were not protected from falling tools, materials or equipment in accordance with the provisions of paragraphs (h)(2)(i)-(v) of this section:   a)  At Lot # 25, 260 Learwood Lane, Atlanta, GA- The employer did not provide head protection for each employee working below a fabricated frame scaffold, exposing employees to struck by hazards.
Recent events (1)
  • — Z (S) $2000

1926.452 C02

Serious Gravity 10 1 instance 3 exposed
Issued
Abate by
Penalty
Initial $2800.00 · Current $2800.00
29 CFR 1926.452(c)(2): Frames and panels were not braced by cross, horizontal, or diagonal braces, or combination thereof, which would secure vertical members together laterally, and the cross braces were not of such length as would  automatically square:   a) At Lot # 25, 260 Learwood Lane, Atlanta, GA- The employer was using a fabricated frame scaffold not fully braced exposing employees to fall hazards of approximately 13 feet 9 inches above ground level.
Recent events (1)
  • — Z (S) $2800

1910.1200 E01

Serious Gravity 1 1 instance 4 exposed
Issued
Abate by
Penalty
Initial $1200.00 · Current $1200.00
29 CFR 1910.1200(e)(1): The employer did not develop, implement, and/or maintain at the workplace a written hazard communication program which describes how the criteria specified in 29 CFR 1910.1200(f), (g), and (h) will be met:   a) At Lot # 25, 260 Learwood Lane, Atlanta, GA-The employer did not develop and implement a written hazard communication program for employees working with Portland cement.
Recent events (1)
  • — Z (S) $1200

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 339756405.