CLEVELAND, WI —
OSHA Inspection: PHOENIX CONTRACTOR, INC.
Unprogrammed Other inspection · Safety discipline
At a glance
On , OSHA opened an unprogrammed Other safety inspection of PHOENIX CONTRACTOR, INC. in 1290 NORTH AVE, CLEVELAND, WI 53015 (NAICS 238160). OSHA activity number 339877698.
Where did this inspection happen?
- Establishment
- PHOENIX CONTRACTOR, INC.
- Site address
- 1290 NORTH AVE
- City
- CLEVELAND
- State
- WI
- ZIP
- 53015
- Mailing
- 111 WILMONT DR. #1, WAUKESHA, WI 53151
What kind of inspection was it?
- Inspection type
- Unprogrammed Other (I)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238160
- Employees
- 4
- Ownership type
- A
Citations
3 citations on file for this inspection.
1926.502 H02
- Issued
- Abate by
- Penalty
- Initial $1700.00 · Current $0.00 Reduced
General-duty citation text
29 CFR 1926.502(h)(2): Mechanical equipment was used and stored in an area where a safety monitoring system was used to protect employees were involved in roofing operations: On 7/29/14, employees had mechanical equipment on the roof while they were using a safety monitor for fall protection while performing repairs on a low slope roof.
Recent events (2)
- — I (S) $0
- — Z (S) $1700
1926.502 J07 I
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.502(j)(7)(i): Materials and/or equipment were stored within 6 feet of a roof edge not equipped with guard rails: On 7/29/14, employees performing roof repairs placed materials and tools at the upper edge of the roof where they could be knocked off the roof onto workers on the ground.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1926.150 C01 VI
- Issued
- Penalty
- Initial $340.00 · Current $0.00 Reduced
General-duty citation text
29 CFR 1926.150(c)(1)(vi): A fire extinguisher, rated not less than 10B, was not provided within 50 feet of wherever more than 5 gallons of flammable or combustible liquids or 5 pounds of flammable gas were being used on the jobsite: On 7/29/14, employees using a propane torch connected to a 20# tank on the roof of a building did not have a fire extinguisher on the roof.
Recent events (2)
- — I (O) $0
- — Z (O) $340
More inspections in this industry (NAICS 238160)
SIOUX FALLS, SD—2026-07-13
H & R ROOFING OF SOUTH DAKOTA, INC.
HENDERSON, NV—2026-07-13
INTEGRITY ROOFING LLC
CORTLANDT MANOR, NY—2026-07-13
LG BUILDERS INC.
CAMDEN, OH—2026-07-13
ALBERTO MORALES
BLOOMINGTON, IL—2026-07-13
UNKNOWN CONTRACTOR
More inspections in WI
MUSCODA, WI—2026-07-10
SCOT INDUSTRIES, INC
FRANKLIN, WI—2026-07-10
EDGE BROADBAND SOLUTIONS LLC
APPLETON, WI—2026-07-10
LAWRENCE UNIVERSITY OF WISCONSIN
KIMBERLY, WI—2026-07-10
ENRIQUE RESENDIC
SLINGER, WI—2026-07-10
DYLAN MATTHEW SHELLEY LLC
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 339877698.