OSHA Inspection: CB&I STONE WEBSTER, INC.

Unprogrammed Related inspection · Safety discipline

On , OSHA opened an unprogrammed Related safety inspection of CB&I STONE WEBSTER, INC. in 1019 HAVERHILL-OHIO FURNACE RD, HAVERHILL, OH 45636 (NAICS 237990). OSHA activity number 339949919.

Watch CB&I Stone Webster, INC. — free Get an email when a new federal OSHA severe-injury report for CB&I Stone Webster, INC. is published. One employer, no account, unsubscribe in one click.
Site address
1019 HAVERHILL-OHIO FURNACE RD
City
HAVERHILL
State
OH
ZIP
45636
Mailing
4171 ESSEN LANE, BATON ROUGE, LA 70809
Inspection type
Unprogrammed Related (G)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
A
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
237990
Employees
158
Ownership type
A

3 citations on file for this inspection.

1910.147 C01

Deleted Serious Gravity 10 1 instance 158 exposed
Issued
Abate by
Penalty
Initial $7000.00 · Current $0.00 Reduced
29 CFR 1910.147(c)(1): Energy control program. The employer did not establish a program consisting of energy control procedures, employee training and periodic inspections to ensure that before any employee performs any servicing or maintenance on a machine or equipment where the unexpected energizing, startup or release of stored energy could occur and cause injury, the machine or equipment shall be isolated from the energy source and rendered inoperative:  (a)    CB&I Stone & Webster, Inc., did not establish an energy control program consisting of energy control procedures, employee training, sharing their program with the host company Haverhill Chemicals, Inc., and periodic inspections for their nested employees such as but not limited to maintenance and capital employees who perform servicing and maintenance of equipment and piping systems with energy sources such as but not limited to; electric, hydraulics, thermal heat, and chemicals, within the process and the piping systems at Haverhill Chemicals, Inc., located at 1019 Haverhill-Ohio Furnace Rd, Haverhill, OH, 45636 on a daily basis.
Recent events (3)
  • — F (S) $0
  • — C (S) $7000
  • — Z (S) $7000

1910.147 C07 I A

Other-than-serious 1 instance 6 exposed
Issued
Abate by
Penalty
Initial $0.00 · Current $3000.00
29 CFR 1910.147(c)(7)(i)(A): Each authorized employee shall receive training in the recognition of applicable hazardous energy sources, the type and magnitude of the energy available in the workplace, and the methods and means necessary for energy isolation and control.    (a)    CB&I Stone Webster Inc., did not provide adequate training on an energy control program to its employees nested at Haverhill Chemicals, Inc., located at 1019 Haverhill-Ohio Furnace Rd., Haverhill, OH to ensure that each authorized employee received training in the recognition of applicable hazardous energy sources, the type and magnitude of the energy such as but not limited to; electric, hydraulics, thermal heat, and chemicals, within the process and the piping systems that is available in the workplace, and the methods and means necessary for energy isolation and control.  On and before August 27, 2014, employees working on the A1401 950 ton temporary chiller piping system were exposed to water leaking from a knife valve that was not properly locked out while performing servicing and maintenance.  When the water turned hot the employees continued to work on the piping system and attempted to divert the hot water away from them.
Recent events (3)
  • — F (O) $3000
  • — C (S) $0
  • — Z (S) $0

1910.147 D06

Deleted Serious Gravity 10 1 instance 4 exposed
Issued
Abate by
Penalty
Initial $7000.00 · Current $0.00 Reduced
29 CFR 1910.147(d)(6): Verification of isolation. Prior to starting work on machines or equipment that have been locked out or tagged out, the authorized employee did not verify that isolation and deenergization of the machine or equipment have been accomplished:  (a)    On August 27, 2014, prior to starting work on the A1401 950 ton temporary chiller piping system, CB&I employees did not adequately verify that isolation of the knife valve had been accomplished in that the knife valve was leaking cold then hot water while employees were replacing the 12" x 10" reducing flanges exposing employees to burns.
Recent events (3)
  • — F (S) $0
  • — C (S) $7000
  • — Z (S) $7000

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 339949919.