OSHA Inspection: PRESTON INSULATION

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of PRESTON INSULATION in TABERNACULO EMANUEL CHURCH PROJECT 301 E. LOS REALES, TUCSON, AZ 85756 (NAICS 238310). OSHA activity number 340146414.

Watch Preston Insulation — free Get an email when a new federal OSHA severe-injury report for Preston Insulation is published. One employer, no account, unsubscribe in one click.
Establishment
PRESTON INSULATION
Site address
TABERNACULO EMANUEL CHURCH PROJECT 301 E. LOS REALES
City
TUCSON
State
AZ
ZIP
85756
Mailing
602 EAST 24TH STREET, TUCSON, AZ 85713
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238310
Employees
33
Ownership type
A

2 citations on file for this inspection.

1926.20 B03

Serious Gravity 5 1 instance 2 exposed
Issued
Abate by
Penalty
Initial $2380.00 · Current $1785.00 Reduced
29 CFR 1926.20(b)(3): The use of any machinery, tool, material, or equipment which was not in compliance with any applicable requirement of this part was not prohibited.  Such machine, tool, material, or equipment was not either identified as unsafe by tagging or locking the controls to render them inoperable or by physically removed from the project:    Inside the structure under construction: A JLG scissor lift, model number 2646E2, was not identified as unsafe by tagging or locking the controls, and it was not removed from the project.    Employees that used the ladder to access the lift were exposed to the hazard of slipping off the ladder and falling onto to the metal corners of the lift.  In the event of control failure, employees in the lift were exposed to the hazard of being caught between the lift and other objects, and employees around the lift were exposed to the hazard of being struck by the lift
Recent events (2)
  • — I (S) $1785
  • — Z (S) $2380

1926.451 E06 IV

Serious Gravity 1 1 instance 2 exposed
Issued
Abate by
Penalty
Initial $1785.00 · Current $1339.00 Reduced
29 CFR 1926.451(e)(6)(iv): Integral prefabricated scaffold access frame rungs were not uniformly spaced within each frame section:  Inside the structure under construction: The integrated ladder rungs on the JLG scissor lift, model number 2646E2, were not uniformly spaced as the second rung from the bottom was damaged and bent upward.  Employee's using the ladder to access the lift were exposed to slip and fall hazards.