OSHA Inspection: KEARNEY TRAILERS, LLC

Complaint inspection · Health discipline

On , OSHA opened a complaint health inspection of KEARNEY TRAILERS, LLC in 1035 SOUTH STATE HIGHWAY 19, EMORY, TX 75440 (NAICS 336212). OSHA activity number 340707991.

Watch Kearney Trailers, LLC — free Get an email when a new federal OSHA severe-injury report for Kearney Trailers, LLC is published. One employer, no account, unsubscribe in one click.
Site address
1035 SOUTH STATE HIGHWAY 19
City
EMORY
State
TX
ZIP
75440
Mailing
1035 SOUTH STATE HIGHWAY 19, EMORY, TX 75440
Inspection type
Complaint (B)
Scope
Partial (B)
Discipline
Health
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
336212
Employees
42
Ownership type
A

10 citations on file for this inspection.

1910.95 C01

Serious Gravity 5 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $3500.00 · Current $1750.00 Reduced
29 CFR 1910.95(c)(1): The employer did not administer a continuing, effective hearing conservation program as described in 29 CFR 1910.95(c) through (o) whenever employee noise exposures equal or exceed an 8-hour time-weighted average sound level of 85 decibels measured on the A scale, or equivalently a dose of fifty percent:    (a) The employer had not administered a hearing conservation program for at least one employee who was exposed to noise that exceeded an 8-hour TWA of 85 dBA.  In the finish out building, a prep bay worker was exposed to noise levels at 72.3% of the permissible 8-hour TWA (90 dBA).  The equivalent dBA level of 72.3% is approximately 87.6 dBA.  Sampling was performed for 480 minutes during one shift.
Recent events (2)
  • — I (S) $1750
  • — Z (S) $3500

1910.141 D02 III

Other-than-serious 1 instance 18 exposed
Issued
Abate by
Penalty
Initial $2100.00 · Current $0.00 Reduced
29 CFR 1910.141(d)(2)(iii): Lavatories were not provided with hand soap or similar cleansing agent:    (a) In the restroom for employees working in the finish out building, hand soap or similar cleansing agent was not provided.
Recent events (2)
  • — I (O) $0
  • — Z (S) $2100

1910.141 D02 IV

Serious Gravity 1 1 instance 18 exposed
Issued
Abate by
Penalty
Initial $0.00 · Current $0.00
29 CFR 1910.141(d)(2)(iv): Lavatories were not provided with individual hand towels or sections thereof, of cloth or paper, warm air blowers or clean individual sections of continuous cloth toweling:  (a) In the restroom for employees working in the finish out building, individual hand towels or sections thereof, of cloth or paper, warm air blowers or clean individual sections of continuous cloth toweling were not provided.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.178 L01 II

Serious Gravity 10 1 instance 7 exposed
Issued
Abate by
Penalty
Initial $4900.00 · Current $2450.00 Reduced
29 CFR 1910.178(l)(1)(ii): The employer did not ensure that each operator had successfully completed the training required by paragraph (l), except as permitted by paragraph (l)(5), prior to permitting an employee to operate a powered industrial truck:    (a) In the finish out building, employees operated forklifts without first having completed a training program consisting of formal instruction, practical training, and evaluation.
Recent events (2)
  • — I (S) $2450
  • — Z (S) $4900

1910.178 A04

Serious Gravity 5 1 instance 7 exposed
Issued
Abate by
Penalty
Initial $3500.00 · Current $1500.00 Reduced
29 CFR 1910.178(a)(4): Modifications and additions which affect capacity and safe operation of powered industrial truck were performed by the employer without the manufacturer's prior written approval:    (a) In the finish out building, at least three forklifts had holes cut out in the tynes so that the trucks could be used to move trailers.
Recent events (2)
  • — I (S) $1500
  • — Z (S) $3500

1910.184 C09

Serious Gravity 10 1 instance 4 exposed
Issued
Abate by
Penalty
Initial $4900.00 · Current $2450.00 Reduced
29 CFR 1910.184(c)(9): Employee(s) were not kept clear of load(s) suspended, or about to be lifted by sling(s):    (a) In the wiring department in the finish out building, employees worked under trailers suspended from a monorail system by alloy steel chain slings.
Recent events (2)
  • — I (S) $2450
  • — Z (S) $4900

1910.184 E01

Serious Gravity 10 1 instance 4 exposed
Issued
Abate by
Penalty
Initial $0.00 · Current $0.00
29 CFR 1910.184(e)(1): Alloy steel sling(s) did not have permanently affixed durable identification stating size, grade, rated capacity, and reach:    (a) In the prep bay and wiring department in the finish out building, trailers were suspended from a monorail system by alloy steel chain slings that did not have permanently affixed durable identification.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.212 A03 II

Serious Gravity 10 1 instance 2 exposed
Issued
Abate by
Penalty
Initial $4900.00 · Current $2450.00 Reduced
29 CFR 1910.212(a)(3)(ii): Point(s) of operation of machinery were not guarded to prevent employee(s) from having any part of their body in the danger zone(s) during operating cycle(s):    (a) In the piece work area, employees were exposed to point of operation hazards while using hydraulic and mechanical press brakes.
Recent events (2)
  • — I (S) $2450
  • — Z (S) $4900

1910.303 B02

Serious Gravity 5 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $2800.00 · Current $1400.00 Reduced
29 CFR 1910.303(b)(2): Listed or labeled electrical equipment was not used or installed in accordance with instructions included in the listing or labeling:    (a) In the piece work area near the plasma table, a power strip was series connected to an extension cord and another power strip, was permanently secured to the building, and was used as a substitute for fixed wiring.
Recent events (2)
  • — I (S) $1400
  • — Z (S) $2800

1910.305 G01 IV D

Serious Gravity 5 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $0.00 · Current $0.00
29 CFR 1910.305(g)(1)(iv)(D): Flexible cords and cables were used where attached to building surfaces:  (a) In the piece work area near the plasma table, flexible cords and/or cables were attached to the building.