WASHINGTON, DC —
OSHA Inspection: DAVE KELLY
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of DAVE KELLY in 5060 MACARTHUR BLVD NW, WASHINGTON, DC 20006 (NAICS 238130). OSHA activity number 340978741.
Where did this inspection happen?
- Establishment
- DAVE KELLY
- Site address
- 5060 MACARTHUR BLVD NW
- City
- WASHINGTON
- State
- DC
- ZIP
- 20006
- Mailing
- 5207 NORWAY DR, CHEVY CHASE, MD 20815
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238130
- Employees
- 4
- Ownership type
- A
Citations
4 citations on file for this inspection.
1926.100 A
- Issued
- Abate by
- Penalty
- Initial $1600.00 · Current $1000.00 Reduced
General-duty citation text
29 CFR 1926.100(a): Employees working in areas where there was a possible danger of head injury from impact, or falling or flying objects, or from electrical shock and burns, were not protected by protective helmets: a) On or October 8, 2015; front of building; Employee working on the ground level providing supplies to the employees on the second floor was not wearing any head protection exposing him to a struck by hazard. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $1000
- — Z (S) $1600
1926.102 A01
- Issued
- Abate by
- Penalty
- Initial $2800.00 · Current $1680.00 Reduced
General-duty citation text
29 CFR 1926.102(a)(1): Eye and face protective equipment were not used when machines or operations presented potential eye or face injury from physical, chemical, or radiation agents: a) On or about October 8, 2015; second floor platform; employees using equipment such as but not limited to nail guns were not wearing eye protection exposing them to a struck by hazard. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (2)
- — I (S) $1680
- — Z (S) $2800
1926.501 B13
- Issued
- Penalty
- Initial $4900.00 · Current $2940.00 Reduced
General-duty citation text
29 CFR 1926.501(b)(13): Each employee(s) engaged in residential construction activities 6 feet (1.8 m) or more above lower levels were not protected by guardrail systems, safety net system, or personal fall arrest system, nor were employee(s) provided with an alternative fall protection measure under another provision of paragraph 1926.501 (b): a) On or about October 8, 2015; second level; employees were exposed to a 15 foot fall while laying the floor for the second floor of the new residential floor. b) On or about October 8, 2015; second floor access area west-side and east-side; employees were exposed to a 10 foot fall while working near floor openings.
Recent events (2)
- — I (S) $2940
- — Z (S) $4900
1926.1053 B01
- Issued
- Abate by
- Penalty
- Initial $2800.00 · Current $1680.00 Reduced
General-duty citation text
29 CFR 1926.1053(b)(1): Where portable ladders were used for access to an upper landing surface and the ladder's length allows, the ladder side rails did not extend at least 3 feet (.9 m) above the upper landing surface being accessed: a) On or about October 8, 2015; front of building; the extension ladder used to access the working platform placed 8 inches above the platform exposing the employees to a 10 foot fall while accessing the ladder or platform. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (2)
- — I (S) $1680
- — Z (S) $2800
More inspections in this industry (NAICS 238130)
FAIRHOPE, AL—2026-07-16
FRANCISCO ARES
WOODHAVEN, MI—2026-07-16
G.J. PERELLI CO., L.L.C.
PHILADELPHIA, PA—2026-07-16
URUS CONSTRUCTION CORPORATION
BERLIN, NJ—2026-07-16
URUS CONSTRUCTION CORPORATION
MERIDIAN, ID—2026-07-15
TRIPLE R CONSTRUCTION LLC
More inspections in DC
WASHINGTON, DC—2026-06-30
U.S. DEPARTMENT OF AGRICULTURE
WASHINGTON, DC—2026-06-16
MACY'S
WASHINGTON, DC—2026-06-02
RIGO MULTISERVICES
WASHINGTON, DC—2026-06-02
DDC CPL LLC
WASHINGTON, DC—2026-06-02
DDC CPL LLC
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 340978741.