OSHA Inspection: TROIANIELLO MASONRY AND CONSTRUCTION SERVICES, INC.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of TROIANIELLO MASONRY AND CONSTRUCTION SERVICES, INC. in 2020 WILKES BARRE MARKETPLACE, WILKES BARRE, PA 18702 (NAICS 238140). OSHA activity number 341401792.

Watch Troianiello Masonry AND Construction Services, INC. — free Get an email when a new federal OSHA severe-injury report for Troianiello Masonry AND Construction Services, INC. is published. One employer, no account, unsubscribe in one click.
Site address
2020 WILKES BARRE MARKETPLACE
City
WILKES BARRE
State
PA
ZIP
18702
Mailing
PO BOX 4227, SCRANTON, PA 18505
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238140
Employees
3
Ownership type
A

4 citations on file for this inspection.

1926.501 B15

Serious Gravity 10 1 instance 3 exposed
Issued
Abate by
Penalty
Initial $2800.00 · Current $1820.00 Reduced
29 CFR 1926.501(b)(15): Each employee on a walking/working surface 6 feet (1.8 m) or more above lower levels was not protected from falling by a guardrail system, safety net system, or personal fall arrest system:    a) Red Robin, Wilkes-Barre, PA: Employees performing work while on the roof over the main entrance approximately 14 feet above the ground were not protected from falling by a guardrail system, safety net system or personal fall arrest system, on or about April 15, 2016.    ABATEMENT CERTIFICATION AND DOCUMENTATION REQUIRED
Recent events (2)
  • — I (S) $1820
  • — Z (S) $2800

1926.451 B01

Serious Gravity 5 1 instance 3 exposed
Issued
Abate by
Penalty
Initial $2000.00 · Current $1300.00 Reduced
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports:    a) Red Robin, Wilkes-Barre, PA: Employees were working from a tubular welded frame scaffold with two (2) working platforms constructed of only two (2) planks, exposing the employees to a potential fall, on or about April 15, 2016.    ABATEMENT CERTIFICATION REQUIRED
Recent events (2)
  • — I (S) $1300
  • — Z (S) $2000

1926.451 F07

Serious Gravity 5 1 instance 3 exposed
Issued
Abate by
Penalty
Initial $0.00 · Current $0.00
29 CFR 1926.451(f)(7): Scaffolds were not erected, moved, dismantled, or altered, by trained and experienced employees under the supervision and direction of a competent person qualified in scaffold erection, moving, dismantling or alteration:  a) Red Robin, Wilkes-Barre, PA: Tubular welded frame scaffolding with two working levels was not erected by a competent person qualified in scaffold erection. The scaffold did not have a fully decked platform and was missing cross-bracing, on or about April 15, 2016.  ABATEMENT CERTIFICATION REQUIRED
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.452 C02

Serious Gravity 5 1 instance 3 exposed
Issued
Abate by
Penalty
Initial $0.00 · Current $0.00
29 CFR 1926.452(c)(2): Tubular welded frames and panels were not braced by cross, horizontal, or diagonal braces, or combination thereof, which would have secured vertical members together laterally:  a) Red Robin, Wilkes Barre, PA: Tubular welded frame scaffolding erected on the roof over the main entrance was not properly braced with cross-bracing exposing employees to the potential for injury from scaffold collapse, on or about April 15, 2016.  ABATEMENT CERITIFICTION REQUIRED
Recent events (2)