O FALLON, IL —
OSHA Inspection: JEFF HALL DBA EJH CUSTOM HOMES & CONSTRUCTION
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of JEFF HALL DBA EJH CUSTOM HOMES & CONSTRUCTION in LOT NEXT TO 1559 N PARC GROVE CT, O FALLON, IL 62269 (NAICS 238130). OSHA activity number 341436095.
Where did this inspection happen?
- Establishment
- JEFF HALL DBA EJH CUSTOM HOMES & CONSTRUCTION
- Site address
- LOT NEXT TO 1559 N PARC GROVE CT
- City
- O FALLON
- State
- IL
- ZIP
- 62269
- Mailing
- 413 E. MAPLE ST., GILLESPIE, IL 62033
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238130
- Employees
- 4
- Ownership type
- A
Citations
5 citations on file for this inspection.
1903.19 C01
- Issued
- Abate by
- Penalty
- Initial $400.00 · Current $400.00
General-duty citation text
29 CFR 1903.19(c)(1): Within 10 calendar days after the abatement date, the employer must certify to OSHA (the Agency) that each cited violation has been abated, except as provided in paragraph (c)(2) of this section. a) For Citation 1, Item 1, issued on 5/11/2016 with an abatement date of 6/28/2016, the employer did not certify the complete abatement of the cited violation. b) For Citation 1, Item 3, issued on 5/11/2016 with an abatement date of 6/28/2016, the employer did not certify the complete abatement of the cited violation.
Recent events (1)
- — Z (O) $400
1903.19 D01
- Issued
- Abate by
- Penalty
- Initial $400.00 · Current $400.00
General-duty citation text
29 CFR 1903.19(d)(1): The employer must submit to the Agency, along with the information on abatement certification required by paragraph (c)(3) of this section, documents demonstrating that abatement is complete for each willful or repeat violation and for any serious violation for which the Agency indicates in the citation that such abatement documentation is required. For Citation 1, Item 2, issued on 5/11/2016 with an abatement date of 6/28/2016, the employer did not submit documents demonstrating complete abatement of the cited violation to OSHA.
Recent events (1)
- — Z (O) $400
1926.102 A01
- Issued
- Abate by
- Penalty
- Initial $1600.00 · Current $1600.00
General-duty citation text
29 CFR 1926.102(a)(1): Eye and face protective equipment were not used when machines or operations presented potential eye or face injury from physical, chemical, or radiation agents: Eye protective equipment was not used when employees were exposed to eye injury while using pneumatic nail guns.
Recent events (1)
- — Z (S) $1600
1926.501 B13
- Issued
- Abate by
- Penalty
- Initial $2800.00 · Current $2800.00
General-duty citation text
29 CFR 1926.501(b)(13): Each employee engaged in residential construction activities 6 feet (1.8 m) or more above lower levels was not protected by guardrail systems, safety net systems, personal fall arrest systems, or an alternative fall protection measure under another provision of paragraph 1926.501 (b), nor did the employer demonstrate that it is infeasible or creates a greater hazard to use these systems and develop and implement a fall protection plan which meets the requirements of paragraph (k) of section 1926.502: Employees were not protected from falling by guardrail systems, safety net systems, personal fall arrest systems, or any other approved mean. Employees were in the process of installing sheeting. While working on the roof employees was exposed to falls of approximately 19.9 feet to a lower level.
Recent events (1)
- — Z (S) $2800
1926.1053 B13
- Issued
- Abate by
- Penalty
- Initial $2400.00 · Current $2400.00
General-duty citation text
29 CFR 1926.1053(b)(13): The top or top step of a stepladder was used as a step: Employees using a 8 ft. step ladder were standing on the top cap to access the roof. Employees were exposed to the hazard of falling.
Recent events (1)
- — Z (S) $2400
More inspections in this industry (NAICS 238130)
FAIRHOPE, AL—2026-07-16
FRANCISCO ARES
WOODHAVEN, MI—2026-07-16
G.J. PERELLI CO., L.L.C.
PHILADELPHIA, PA—2026-07-16
URUS CONSTRUCTION CORPORATION
BERLIN, NJ—2026-07-16
URUS CONSTRUCTION CORPORATION
MERIDIAN, ID—2026-07-15
TRIPLE R CONSTRUCTION LLC
More inspections in IL
DEERFIELD, IL—2026-07-16
JOHN BURNS CONSTRUCTION COMPANY, LLC
BANNOCKBURN, IL—2026-07-16
BUILDER SERVICES GROUP, INC. DBA CJ INSULATION
BANNOCKBURN, IL—2026-07-16
ROOFING H.P. LLC
HIGHLAND PARK, IL—2026-07-16
UNITED PLUMBING AND DRAIN, INC.
FRANKLIN PARK, IL—2026-07-16
B & M PLASTIC INC.
Source