Safety Incidents OSHA Severe Injury Reports · 2015–2025
4,113,118Inspections Most recent open 2026-07-13 Last loaded 2026-07-17

OSHA Inspection: CHAPMAN CONSTRUCTION CO., L.P.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of CHAPMAN CONSTRUCTION CO., L.P. in 5601 DAVIS BLVD., NORTH RICHLAND HILLS, TX 76180 (NAICS 237130). OSHA activity number 343023123.

Watch Chapman Construction CO., L.P. — free Get an email when a new federal OSHA severe-injury report for Chapman Construction CO., L.P. is published. One employer, no account, unsubscribe in one click.
Site address
5601 DAVIS BLVD.
City
NORTH RICHLAND HILLS
State
TX
ZIP
76180
Mailing
1415 SKYLINE DR., HUTCHINS, TX 75141
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
237130
Employees
4
Ownership type
A

2 citations on file for this inspection.

1926.1431 K02 II

Other-than-serious 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $9054.00 · Current $4527.00 Reduced
29 CFR 1926.1431(k)(2)(ii): The employer did not ensure that each employee was not standing, sitting on or working from the top or intermediate rail or toe board, or use any others means/device to raise their working height.    At the job site, an employee working from a personnel platform attached to a crane was standing on the intermediate rail to raise his working height exposing the employee to fall and electrocution hazards.
Recent events (3)
  • — R (O) $4527
  • — C (S) $9054
  • — Z (S) $9054

1926.1431 N

Deleted Serious Gravity 10 1 instance 2 exposed
Issued
Abate by
Penalty
Initial $9054.00 · Current $0.00 Reduced
29 CFR 1926.1431(n): Hoisting personnel near power lines. Hoisting personnel within 20 feet of a power line that is up to 350 kV, and hoisting personnel within 50 feet of a power line that is over 350 kV, is prohibited, except for work covered by subpart V of this part (Power Transmission and Distribution).  At the job site, the employer failed to ensure that hoisted employees maintained 20 feet of clearance from energized power lines operating at 138kV exposing employees to electrocution hazards.
Recent events (3)
  • — R (S) $0
  • — C (S) $9054
  • — Z (S) $9054

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 343023123.