BELLWOOD, IL —
OSHA Inspection: CATALYTIC PRODUCTS INTERNATIONAL, INC.
Programmed Related inspection · Safety discipline
At a glance
On , OSHA opened a programmed Related safety inspection of CATALYTIC PRODUCTS INTERNATIONAL, INC. in 700 25TH AVE., BELLWOOD, IL 60104 (NAICS 811310). OSHA activity number 343303152.
Where did this inspection happen?
- Establishment
- CATALYTIC PRODUCTS INTERNATIONAL, INC.
- Site address
- 700 25TH AVE.
- City
- BELLWOOD
- State
- IL
- ZIP
- 60104
- Mailing
- 980 ENSELL ROAD, LAKE ZURICH, IL 60047
What kind of inspection was it?
- Inspection type
- Programmed Related (J)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 811310
- Employees
- 1
- Ownership type
- A
Citations
3 citations on file for this inspection.
1910.147 D
- Issued
- Abate by
- Penalty
- Initial $5174.00 · Current $3800.00 Reduced
General-duty citation text
29 CFR 1910.147(d): The established procedure for the application of energy control (the lockout or tagout procedure) was not done in sequence as required by 29 CFR 1910.147(d)(1) through (d)(6): a) Courtyard Area- On or about July 5, 2018, an employee was exposed to machine hazards associated with moving parts and pinch point hazards during the maintenance and servicing of the Glue and Roll Coat Lines Oxidizer 1097. The employer failed to implement energy control application steps as lockout tagout (LOTO) devices were not applied to the electrical disconnect, gas supply valve, and three pneumatic valves [per the 1910.147(d)(4) requirements. As a result, the remaining applicable energy control elements, involving dissipation of residual energy [(d)(5)(i)], and verification of isolation [(d)(6)], were not implemented to protect employees from machine servicing hazards. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
- — I (S) $3800
- — Z (S) $5174
1910.147 F03 I
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1910.147(f)(3)(i): A procedure was not utilized to afford the employees a level of protection equivalent to that provided by the implementation of a personal lockout or tagout device when servicing and/or maintenance was performed by a crew: a) Courtyard Area- On or about July 5, 2018, the employer did not ensure that employees utilized a lockout procedure that provided employees a level of protection equivalent to that provided by the implementation of a personal lockout device to protect them from the unexpected energization of the equipment when work was performed by a group on the Glue and Roll Coat Lines Oxidizer 1097. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.147 F02 I
- Issued
- Abate by
- Penalty
- Initial $3696.00 · Current $0.00 Reduced
General-duty citation text
29 CFR 1910.147(f)(2)(i): When outside servicing personnel were engaged in activities in a facility, the onsite employer and the outside employer did not inform each other of their respective lockout or tagout procedures: a) Courtyard Area- On or about July 5, 2018, the employer and the outside servicing personnel of Advanced Technology Services, Inc. as well as BorgWarner Transmission Systems LLC, did not inform one another of their lockout tagout procedures. All three companies had procedures, but none of the three were utilized and it contributed to confusion among employees of the responsibilities with the application of lockout on the Glue and Roll Coat Lines Oxidizer 1097. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
- — I (S) $0
- — Z (S) $3696
More inspections in this industry (NAICS 811310)
CHRISTIANSBURG, VA—2026-07-09
BGIS GLOBAL INTEGRATED SOLUTION US, LLC
SEATTLE, WA—2026-07-09
WA317992010 - FLAGSHIP MANAGEMENT LLC
STATESBORO, GA—2026-07-08
TAYLOR BUILT PRODUCTS
, AK—2026-07-08
ANGUS ENTERPRISES
LOS ANGELES, CA—2026-07-08
CHILLEST INDUSTRIES LLC
More inspections in IL
DEERFIELD, IL—2026-07-16
JOHN BURNS CONSTRUCTION COMPANY, LLC
BANNOCKBURN, IL—2026-07-16
BUILDER SERVICES GROUP, INC. DBA CJ INSULATION
BANNOCKBURN, IL—2026-07-16
ROOFING H.P. LLC
HIGHLAND PARK, IL—2026-07-16
UNITED PLUMBING AND DRAIN, INC.
FRANKLIN PARK, IL—2026-07-16
B & M PLASTIC INC.
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 343303152.