REEDVILLE, VA —
OSHA Inspection: JENNINGS BOATYARD
Planned inspection · Health discipline
At a glance
On , OSHA opened a planned health inspection of JENNINGS BOATYARD in 169 BOATYARD RD, REEDVILLE, VA 22539 (NAICS 336612). OSHA activity number 343704896.
Where did this inspection happen?
- Establishment
- JENNINGS BOATYARD
- Site address
- 169 BOATYARD RD
- City
- REEDVILLE
- State
- VA
- ZIP
- 22539
- Mailing
- 169 BOATYARD RD, REEDVILLE, VA 22539
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Complete (A)
- Discipline
- Health
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 336612
- Employees
- 4
- Ownership type
- A
Citations
5 citations on file for this inspection.
1910.134 C
- Issued
- Abate by
- Penalty
- Initial $2273.00 · Current $1477.00 Reduced
General-duty citation text
29 CFR 1910.134(c): The employer did not develop and implement a written respiratory protection program with required worksite-specific procedures and elements for required respirator use: a) 169 Boatyard Rd, Reedville, VA 22539: On or about January 10, 2019, and times prior thereto, the employer did not develop and implement a written respiratory protection program to include medical evaluation, fit-testing and other elements, prior to required use of respirators, including 3M full-face elastomeric negative pressure respirators, exposing employees to respiratory hazards. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (2)
- — I (S) $1477.45
- — Z (S) $2273
1910.213 D01
- Issued
- Abate by
- Penalty
- Initial $2842.00 · Current $1847.00 Reduced
General-duty citation text
29 CFR 1910.213(d)(1): Circular handfed crosscut table saw(s) were not guarded by an automatically adjusting hood which completely enclosed that portion of the saw above the table and above the material being cut: a) 169 Boatyard Rd, Reedville, VA 22539: On or about January 10, 2019, and times prior thereto, the portion of the saw blade above the table on the Delta Unisaw table saw S/N#113-2362, used to cut wood for boat building and repair work, was not guarded, exposing employees to amputation hazards. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (2)
- — I (S) $1847.3
- — Z (S) $2842
1910.1200 E01
- Issued
- Abate by
- Penalty
- Initial $2273.00 · Current $1477.00 Reduced
General-duty citation text
29 CFR 1910.1200(e)(1): The employer did not develop, implement, and/or maintain at the workplace a written hazard communication program which describes how the criteria specified in 29 CFR 1910.1200(f), (g), and (h) will be met: a) 169 Boatyard Rd, Reedville, VA 22539: On or about January 10, 2019, and times prior thereto, the employer did not develop and implement a written hazard communication program where employees used hazardous chemicals such as but not limited to fiberglass resins and boat paints, containing toluene, xylene, acetone and other hazardous chemicals, exposing employees to potential eye, skin and respiratory irritation and distress and central nervous system effects. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (2)
- — I (S) $1477.45
- — Z (S) $2273
1926.451 B01 I
- Issued
- Abate by
- Penalty
- Initial $2842.00 · Current $0.00 Reduced
General-duty citation text
29 CFR 1926.451(b)(1)(i): Each platform unit (e.g., scaffold plank, fabricated plank, fabricated deck, or fabricated platform) was not installed so that the space between adjacent units and the space between the platform and the uprights were no more than 1 inch (2.5 cm) wide, except where the employer can demonstrate that a wider space is necessary. a) 169 Boatyard Rd, Reedville, VA 22539, M/V Mary Rebecca: On or about January 10, 2019, and times prior thereto, the employer provided a wheel-mounted mobile scaffold as a work platform at the bow of the boat, that was not fully planked between the uprights, exposing employees to fall hazards of up to approximately 5' to lower level. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (2)
- — I (S) $0
- — Z (S) $2842
1926.451 B02
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.451(b)(2): Scaffold platforms and walkways were not at least 18 inches wide: a) 169 Boatyard Rd, Reedville, VA 22539, M/V Mary Rebecca: On or about January 10, 2019, and times prior thereto, the employer provided walkways, to a mobile scaffold at the bow of the boat, that were up to approximately 8" in width where at least 18" was feasible, exposing employees to fall hazards of up to approximately 5' to the lower level. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (2)
- — I (S) $0
- — Z (S) $0
More inspections in this industry (NAICS 336612)
CLANTON, AL—2026-07-13
UBIQUE TECHNOLOGIES, INC.
POST FALLS, ID—2026-06-23
BURLY PRODUCTS
TACOMA, WA—2026-06-18
WA317991721 - SILVERBACK INDUSTRIES LLC
CATAUMET, MA—2026-06-16
BALLENTINE'S BOAT SHOP, INC.
PORT TOWNSEND, WA—2026-06-11
WA317991653 - ARMSTRONG CONSOLIDATED LLC
More inspections in VA
WARSAW, VA—2026-07-10
CARR'S TIRE SERVICE
CHESAPEAKE, VA—2026-07-10
A&W CONTRACTORS, INC.
ROANOKE, VA—2026-07-10
NORTHWEST ACE HARDWARE
LYNCHBURG, VA—2026-07-10
RIVERFRONT HOSPITALITY LLC
CLOVERDALE, VA—2026-07-10
CUMMINS SALES AND SERVICE
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 343704896.