OSHA Inspection: JBGC, INC.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of JBGC, INC. in 136 NORTH STREET, MEDFORD, MA 02155 (NAICS 238190). OSHA activity number 346277593.

Watch Jbgc, INC. — free Get an email when a new federal OSHA severe-injury report for Jbgc, INC. is published. One employer, no account, unsubscribe in one click.
Establishment
JBGC, INC.
Site address
136 NORTH STREET
City
MEDFORD
State
MA
ZIP
02155
Mailing
42 HARRIET AVE, BURLINGTON, MA 01803
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238190
Employees
8
Ownership type
A

4 citations on file for this inspection.

1926.451 B01

Serious Gravity 5 1 instance 2 exposed
Issued
Penalty
Initial $3729.00 · Current $2610.00 Reduced
29 CFR  1926.451(b)(1):  Each platform on all working levels of scaffolding was not fully planked or decked:  Location: 136 North Street Medford MA  On or about 10/13/2022, a sawhorse scaffold system platform was not fully planked.
Recent events (2)
  • — I (S) $2610.3
  • — Z (S) $3729

1926.451 B05 II

Serious Gravity 5 1 instance 2 exposed
Issued
Penalty
Initial $0.00 · Current $0.00
29 CFR  1926.451(b)(5)(ii): The end of a platform greater than 10 feet in length extended over its support more than 18 inches and the platform was not designed and installed so that the cantilevered portion of the platform is able to support employees without tipping, or has guardrails which block employee access to the cantilivered end.   Location: 136 North Street Medford MA  On or about 10/13/2022, one end of the sawhorse scaffold platform less than 10 feet in length extended over the scaffold support more than 12 inches.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.451 C02

Serious Gravity 5 1 instance 2 exposed
Issued
Penalty
Initial $0.00 · Current $0.00
29 CFR  1926.451(c)(2): Supported scaffold poles, legs, posts, frames,  or uprights did not bear on base plates and mud sills or other adequate firm foundation:  Location: 136 North Street Medford MA  On or about 10/13/2022, the legs and poles of the sawhorse scaffold system did not bear weight on base plates and mudsills.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.451 F07

Serious Gravity 5 1 instance 2 exposed
Issued
Penalty
Initial $0.00 · Current $0.00
29 CFR  1926.451(f)(7):Scaffolds were not erected, moved, dismantled, or altered, by trained and experienced employees under the supervision and direction of a competent person qualified in scaffold erection, moving, dismantling or alteration:; Such activities were not performed only by experienced and trained employees selected for such work by the competent person.  Location: 136 North Street Medford MA  On or about 10/13/2022, a job-made sawhorse scaffold was not erected by trained or experienced employees under the supervision and direction of a competent person qualified in scaffold erection.