PROVIDENCE, RI —
OSHA Inspection: KC & SON UNLIMITED LLC
Complaint inspection · Safety discipline
At a glance
On , OSHA opened a complaint safety inspection of KC & SON UNLIMITED LLC in 63-65 WYNDHAM AVENUE, PROVIDENCE, RI 02908 (NAICS 238170). OSHA activity number 346822729.
Where did this inspection happen?
- Establishment
- KC & SON UNLIMITED LLC
- Site address
- 63-65 WYNDHAM AVENUE
- City
- PROVIDENCE
- State
- RI
- ZIP
- 02908
- Mailing
- 88 SENECA AVENUE, PAWTUCKET, RI 02860
What kind of inspection was it?
- Inspection type
- Complaint (B)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238170
- Employees
- 1
- Ownership type
- A
Citations
6 citations on file for this inspection.
1926.451 A01
- Issued
- Abate by
- Penalty
- Initial $4688.00 · Current $2813.00 Reduced
General-duty citation text
29 CFR 1926.451(a)(1): Each scaffold and/or scaffold component was not capable of supporting, without failure, its own weight and at least 4 times the maximum intended load applied or transmitted to it. (a) Worksite - Side of the building: On or about 07/11/2023, the employer allowed employees to utilize non-scaffold-grade planks as the walking/working surface of the scaffold.
Recent events (2)
- — I (S) $2812.8
- — Z (S) $4688
1926.451 C02
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.451(c)(2): Supported scaffold poles, legs, posts, frames, or uprights did not bear on base plates and mud sills or other adequate firm foundation. (a) Worksite - Side of the building: On or about 07/11/2023, the employer allowed employees to assemble and use a pump jack scaffold system with 4 of the uprights resting on the ground, not bearing on base plates and mud sills, or another adequate firm foundation.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1926.451 F07
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.451(f)(7): Scaffolds were not erected, moved, dismantled, or altered, by trained and experienced employees under the supervision and direction of a competent person qualified in scaffold erection, moving, dismantling or alteration:; Such activities were not performed only by experienced and trained employees selected for such work by the competent person. (a)Worksite - Side of the building: On or about 07/11/2023, the employer allowed employees to assemble and use a pump jack scaffold system without supervision by a competent person qualified in scaffold erection in that the scaffold was missing a mid-rail, base plates, mud sills, and fall protection.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1926.451 G01
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.451(g)(1): Employees on scaffolds more than 10 feet (3.1 m) above a lower level were not protected from falling to that lower level by fall protection established in paragraphs (g)(1)(i)-(vii) of this section. (a)Worksite - Side of the building: On or about 07/11/2023, the employer allowed employees to assemble and use a pump jack scaffold system, at a height of approximately 16 feet above the lower level, without any means of fall protection.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1926.452 J02
- Issued
- Abate by
- Penalty
- Initial $4688.00 · Current $2813.00 Reduced
General-duty citation text
29 CFR 1926.452(j)(2): Poles were not secured to the structure by rigid triangular bracing or equivalent at the bottom, top, and other points as necessary. (a) Worksite - Side of the building: On or about 07/11/2023, the employer allowed employees to assemble and use a pump jack scaffold system with 4 upright poles not secured to the bottom of the structure by rigid triangular bracing or equivalent, thus exposing employees to scaffold collapse and fall hazards.
Recent events (2)
- — I (S) $2812.8
- — Z (S) $4688
1926.452 J07
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.452(j)(7): When two by fours are spliced to make a pole, mending plates shall be installed at all splices to develop the full strength of the member. (a) Worksite - Side of the building: On or about 07/11/2023, the employer allowed employees to assemble and use a pump jack scaffold system with 4 upright poles constructed from two-by-four lumber that was spliced together without mending plates installed at all splices, thus exposing employees to scaffold collapse and fall hazards.
Recent events (2)
- — I (S) $0
- — Z (S) $0
More inspections in this industry (NAICS 238170)
CLINTON, MO—2026-07-14
TORCHYLO BUILDERS, LLC.
HIGH POINT, NC—2026-07-14
161545 - RHP SIDING LLC
HIGH POINT, NC—2026-07-14
161544 - TRIAD SIDING OF THOMASVILLE INCORPORATED
OXFORD, OH—2026-07-13
R&R SIDING LLC
WINSTON SALEM, NC—2026-07-10
161522 - MS SIDING LLC
More inspections in RI
PAWTUCKET, RI—2026-07-16
INTERNATIONAL PACKAGING CORPORATION
WARWICK, RI—2026-07-16
LYON PROPERTY MANAGEMENT, LLC
LINCOLN, RI—2026-07-14
TFORCE FREIGHT
JOHNSTON, RI—2026-07-14
WEST BAY RESIDENTIAL SERVICES INC.
NEWPORT, RI—2026-07-10
STEVEN POSTHUMA
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 346822729.