Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,214Inspections Most recent open 2026-07-16 Last loaded 2026-07-20

OSHA Inspection: HIGH COUNTRY LINE CONSTRUCTION INC

Referral inspection · Safety discipline

On , OSHA opened a referral safety inspection of HIGH COUNTRY LINE CONSTRUCTION INC in 30.99456? N,101.81164? W, OZONA, TX 76943 (NAICS 221122). OSHA activity number 346889322.

Watch High Country Line Construction INC — free Get an email when a new federal OSHA severe-injury report for High Country Line Construction INC is published. One employer, no account, unsubscribe in one click.
Site address
30.99456? N,101.81164? W
City
OZONA
State
TX
ZIP
76943
Mailing
2452 E 6700 S, UNIT A, UINTAH, UT 84405
Inspection type
Referral (C)
Scope
Partial (B)
Discipline
Safety
Advance notice
Yes
Union status
A
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
221122
Employees
68
Ownership type
A

4 citations on file for this inspection.

1926.551 J

Other-than-serious Gravity 5 1 instance 2 exposed
Issued
Abate by
Penalty
Initial $9376.00 · Current $8000.00 Reduced
29 CFR  1926.551(j):Static charge. Static charge on the suspended load shall be dissipated with a grounding device before ground personnel touch the suspended load, or protective rubber gloves shall be worn by all ground personnel touching the suspended load:  30�59'40.4"N 101�48'41.9"W, Crockett County, TX: On or about August 02, 2023, and times prior thereto, employees were exposed to electrical hazards due to the employer not ensuring that employees utilized rubber gloves before touching suspended loads from the helicopter.
Recent events (3)
  • — J (O) $8000
  • — C (S) $9376
  • — Z (S) $9376

1926.551 N

Deleted Serious Gravity 5 1 instance 2 exposed
Issued
Abate by
Penalty
Initial $9376.00 · Current $0.00 Reduced
29 CFR  1926.551(n):Signal systems. Signal systems between aircrew and ground personnel shall be understood and checked in advance of hoisting the load. This applies to either radio or hand signal systems. Hand signals shall be as shown in Figure N-1.:  30�59'40.4"N 101�48'41.9"W, Crockett County, TX: On or about August 02, 2023, and times prior thereto, employees were exposed to electrical hazards due to not ensuring that a signaling system was established by aircrew and ground personnel prior to hoisting loads.
Recent events (3)
  • — J (S) $0
  • — C (S) $9376
  • — Z (S) $9376

1926.962 F01

Deleted Serious Gravity 10 1 instance 2 exposed
Issued
Abate by
Penalty
Initial $10938.00 · Current $0.00 Reduced
29 CFR  1926.962(f)(1):Order of connection. The employer shall ensure that, when an employee attaches a ground to a line or to equipment, the employee attaches the ground-end connection first and then attaches the other end by means of a live-line tool. For lines or equipment operating at 600 volts or less, the employer may permit the employee to use insulating equipment other than a live-line tool if the employer ensures that the line or equipment is not energized at the time the ground is connected or if the employer can demonstrate that each employee is protected from hazards that may develop if the line or equipment is energized:    30�59'40.4"N 101�48'41.9"W, Crockett County, TX: On or about August 02, 2023, and times prior thereto, employees were exposed to electrical hazards due to not ensuring that grounding procedures were being implemented before working with lines that run parallel to energized lines.
Recent events (3)
  • — J (S) $0
  • — C (S) $10938
  • — Z (S) $10938

1926.964 B04 I

Other-than-serious Gravity 10 1 instance 2 exposed
Issued
Abate by
Penalty
Initial $10938.00 · Current $5000.00 Reduced
29 CFR  1926.964(b)(4)(i): Before employees install lines parallel to existing energized lines, the employer shall make a determination of the approximate voltage to be induced in the new lines, or work shall proceed on the assumption that the induced voltage is hazardous:    30�59'40.4"N 101�48'41.9"W, Crockett County, TX: On or about August 02, 2023, and times prior thereto, employees were exposed to electrical hazards due to not determining the appropriate voltage induced by installing new lines next to parallel energized lines.
Recent events (3)
  • — J (O) $5000
  • — C (S) $10938
  • — Z (S) $10938

PSE&G

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 346889322.