EASTHAM, MA —
OSHA Inspection: DUCTED AIR SYSTEMS
Complaint inspection · Safety discipline
At a glance
On , OSHA opened a complaint safety inspection of DUCTED AIR SYSTEMS in 100 CABLE ROAD NAUSET REGIONAL HIGH SCHOOL, EASTHAM, MA 02642 (NAICS 332322). OSHA activity number 347830820.
Where did this inspection happen?
- Establishment
- DUCTED AIR SYSTEMS
- Site address
- 100 CABLE ROAD NAUSET REGIONAL HIGH SCHOOL
- City
- EASTHAM
- State
- MA
- ZIP
- 02642
- Mailing
- PO BOX 8005, CRANSTON, RI 02920
What kind of inspection was it?
- Inspection type
- Complaint (B)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- A
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 332322
- Employees
- 5
- Ownership type
- A
Citations
4 citations on file for this inspection.
1926.451 B01 I
- Issued
- Abate by
- Penalty
- Initial $4839.00 · Current $4000.00 Reduced
General-duty citation text
29 CFR 1926.451(b)(1)(i):Each platform unit (e.g., scaffold plank, fabricated plank, fabricated deck, or fabricated platform) was not installed so that the space between adjacent units and the space between the platform and the uprights were no more than 1 inch (2.5 cm) wide, except where the employer can demonstrate that a wider space is necessary. LOCATION: Nauset Regional High School On or about May 20, 2024, employees were exposed to fall hazards on the scaffolding where the void between fabricated platforms was not installed so that the space between adjacent units and the space between the platform and the uprights were no more than 1 inch (2.5 cm) wide.
Recent events (2)
- — I (O) $4000
- — Z (S) $4839
1926.451 B02
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.451(b)(2):Except as provided in paragraphs (b)(2)(i) and (b)(2)(ii) of this section, each scaffold platform and/or walkway was not at least 18 inches (46 cm) wide. LOCATION: Nauset Regional High School On or about May 20, 2024, employees were exposed to fall hazards on the scaffolding where, except as provided in paragraphs (b)(2)(i) and (b)(2)(ii) of this section, each scaffold platform and/or walkway was not at least 18 inches (46 cm) wide.
Recent events (2)
- — I (O) $0
- — Z (S) $0
1926.451 E01
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.451(e)(1):When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used. Crossbraces were used as a means of access. LOCATION: Nauset Regional High School On or about May 20, 2024, employees were exposed to fall hazards where scaffold platforms that were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used. Crossbraces were used as a means of access.
Recent events (2)
- — I (O) $0
- — Z (S) $0
1926.451 F03
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.451(f)(3):Scaffolds and scaffold components were not inspected for visible defects by a competent person before each work shift, and after any occurrence which could affect a scaffold's structural integrity. LOCATION: Nauset Regional High School On or about May 20, 2024, employees were exposed to numerous fall and struck-by hazards, where the employer did not ensure that scaffolds and scaffold components were inspected for visible defects by a competent person before each work shift, and after any occurrence which could affect a scaffold's structural integrity.
Recent events (2)
- — I (O) $0
- — Z (S) $0
More inspections in this industry (NAICS 332322)
CASTLE ROCK, CO—2026-07-10
MASTER MAGNETICS, INC.
PITTSBURG, KS—2026-07-09
PROGRESSIVE PRODUCTS INC
NEW ROCHELLE, NY—2026-07-09
HEFTI HARBOR ELEC FAB & TOOLS
LAKEWOOD, WA—2026-07-08
WA317992020 - KRUEGER SHEET METAL CO
SOUTHAMPTON, MA—2026-07-07
LYMAN SHEET METAL CO., INC
More inspections in MA
WORCESTER, MA—2026-07-10
QUINSIGAMOND COMMUNITY COLLEGE
FITCHBURG, MA—2026-07-10
KELLEY WOOD PRODUCTS, INC.
EVERETT, MA—2026-07-10
HORIZON RETAIL CONSTRUCTION INC
NORTON, MA—2026-07-09
DYNAMIC RESIDENTIAL ROOF MARKETING, LLC
NORTON, MA—2026-07-09
LM GENERAL CONSTRUCTION INC.
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 347830820.