HAMPTON, NH —
OSHA Inspection: ROBERT A. MURRIN CONSTRUCTION, INC.
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of ROBERT A. MURRIN CONSTRUCTION, INC. in 3 GREAT BOARS HEAD AVE, HAMPTON, NH 03842 (NAICS 238130). OSHA activity number 347871592.
Where did this inspection happen?
- Establishment
- ROBERT A. MURRIN CONSTRUCTION, INC.
- Site address
- 3 GREAT BOARS HEAD AVE
- City
- HAMPTON
- State
- NH
- ZIP
- 03842
- Mailing
- 59 KITTERY AVENUE, ROWLEY, MA 01969
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238130
- Employees
- 4
- Ownership type
- A
Citations
13 citations on file for this inspection.
1926.451 G01 I
- Issued
- Abate by
- Penalty
- Initial $3547.00 · Current $1200.00 Reduced
General-duty citation text
29 CFR 1926.451(g)(1)(i): Each employee on a boatswains' chair, catenary scaffold, float scaffold, needle beam scaffold, or ladder jack scaffold was not protected by a personal fall arrest system: Site- Employees working from an outrigger scaffold were not protected from a falls of approximately 19 feet while installing roofing materials.
Recent events (3)
- — F (S) $1200
- — C (S) $3547
- — Z (S) $3547
1926.501 B13
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.501(b)(13): Each employee(s) engaged in residential construction activities 6 feet (1.8 m) or more above lower levels were not protected by guardrail systems, safety net system, or personal fall arrest system: Site- Employees working from the roof were exposed to a fall of more than 20 feet where fall protection was not adequately utilized.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
1926.602 C01 VIII A
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.602(c)(1)(viii)(A): The safety platform was not firmly secured to the lifting carriage and/or forks: JLG Lift - Two employees were exposed to falls of approximately 20 feet while working on a platform which was not secured to the lift.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
1926.451 B01
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds shall be fully planked or decked between the front uprights and the guardrail supports as follows: a. Employees were working on an outrigger scaffold which was not fully planked or decked while they were working at the roof level. b. Employees were working on a pole / carpenter bracket scaffold which was not fully planked or decked while they were installing trim board between the first and second levels.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
1926.602 C01 II
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.602(c)(1)(ii): Modifications and / or additions which affected the capacity or safe operation of the equipment were not made without the manufacturer's written approval. Additionally, when such modifications or changes were made, the capacity, operation, and maintenance instruction plates, tags, or decals were not changed accordingly: a. A personnel lift was used on the JLG lift without the manufacturer's written approval which identified the new capacity, operation and instruction plates.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
1926.300 B01
- Issued
- Abate by
- Penalty
- Initial $2837.00 · Current $900.00 Reduced
General-duty citation text
29 CFR 1926.300(b)(1): When power operated tools were designed to accommodate guards, they were not equipped with such guards when in use: a. Employees were using a Hilti AG 500-11S angle grinder without the required guard.
Recent events (3)
- — F (S) $900
- — C (S) $2837
- — Z (S) $2837
1926.451 B07
- Issued
- Abate by
- Penalty
- Initial $3547.00 · Current $1200.00 Reduced
General-duty citation text
29 CFR 1926.451(b)(7): On scaffolds where platforms were overlapped to create a long platform, the overlap shall occur only over supports, and was less than 12 inches (30 cm) unless the platforms were nailed together or otherwise restrained to prevent movement: Outrigger Scaffold - Employees were exposed to an approximately 19 foot fall while working on an outrigger scaffold where the platforms were not overlapped over supports and were not either nailed together or otherwise restrained to prevent collapse.
Recent events (3)
- — F (S) $1200
- — C (S) $3547
- — Z (S) $3547
1926.452 I03
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.452(i)(3):The fulcrum point of outrigger beams did not rest on secure bearings at least 6 inches (15.2 cm) in each horizontal dimension: The multiple fulcrum points on the outrigger scaffold were not resting on bearings.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
1926.452 I06
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.452(i)(6): The entire supporting structure shall be securely braced to prevent any horizontal movement. The Outrigger scaffold was not braced to eliminate horizontal movement to prevent collapse.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
1926.452 I07
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.452(i)(7):To prevent their displacement, platform units were not nailed, bolted, or otherwise secured to outriggers: Outrigger Scaffold - Employees were exposed to falls and platform collapse where platforms such as the metal platform / pick was not secured to the outriggers.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
1926.452 I08
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.452(i)(8):Scaffolds and scaffold components were not designed by a registered professional engineer and be constructed and loaded in accordance with such design: The outrigger scaffold was not designed by a professional engineer.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
1926.1052 C01 I
- Issued
- Abate by
- Penalty
- Initial $2128.00 · Current $700.00 Reduced
General-duty citation text
29 CFR 1926.1052(c)(1)(i):At least one handrail: First Floor and Basement - The stairway was not equipped with at least one handrail to prevent falls.
Recent events (3)
- — F (S) $700
- — C (S) $2128
- — Z (S) $2128
1926.1052 C01 II
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.1052(c)(1)(ii):One stair rail system along each unprotected side or edge. First Floor and Basement - The stairs were not not equipped with a stair rail system along the unprotected side or edge.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
More inspections at ROBERT A. MURRIN CONSTRUCTION, INC.
HAMILTON, MA—2012-08-01 00:00:00
ROBERT A. MURRIN CONSTRUCTION, INC.
MARBLEHEAD, MA—2010-08-16 00:00:00
ROBERT A. MURRIN CONSTRUCTION INC.
View ROBERT A. MURRIN CONSTRUCTION, INC.'s full OSHA safety record →
More inspections in this industry (NAICS 238130)
ENCINITAS, CA—2026-07-13
LOU RIDDLE CONSTRUCTION
MERIDIAN, ID—2026-07-10
IDAHO HOMES CONSTRUCTION LLC
KIMBERLY, WI—2026-07-10
ENRIQUE RESENDIC
METTER, GA—2026-07-10
M.A.P.C CONSTRUCTION, LLC
SLINGER, WI—2026-07-10
RAMIREZ HOME BUILDERS LLC
More inspections in NH
CONCORD, NH—2026-07-10
C.C. TOMATOES
FRANCESTOWN, NH—2026-07-10
JM BUILDERS LLC
FRANCESTOWN, NH—2026-07-10
D&D INSULATION, LLC
NORTHFIELD, NH—2026-07-03
JP PEST SERVICES
CONCORD, NH—2026-07-01
REYES CARPENTRY, LLC
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 347871592.