OSHA Inspection: BAE SYSTEMS SAN FRANCISCO SHIP REPAIR

Referral inspection · Safety discipline

On , OSHA opened a referral safety inspection of BAE SYSTEMS SAN FRANCISCO SHIP REPAIR in FOOT OF 20TH ST, SAN FRANCISCO, CA 94107 (NAICS 336611). OSHA activity number 311409528.

Watch BAE Systems SAN Francisco Ship Repair — free Get an email when a new federal OSHA severe-injury report for BAE Systems SAN Francisco Ship Repair is published. One employer, no account, unsubscribe in one click.
Site address
FOOT OF 20TH ST
City
SAN FRANCISCO
State
CA
ZIP
94107
Inspection type
Referral (C)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
Y
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
336611
SIC code (legacy)
3731
Employees
2600
Ownership type
A
Industry flags
Maritime safety.

10 citations on file for this inspection.

5(a)(1)

Serious Gravity 10 2 instances 2 exposed
Issued
Abate by
Penalty
Initial $5000.00 · Current $5000.00
Section 5(a)(1) of the Occupational Safety and Health Act of 1970:  The
employer did not
furnish employment and a place of employment which were free from
recognized hazards that
were causing or likely to cause death or serious physical harm to
employees in that employees
were exposed to possible injury from accidents caused by equipment which
was not properly
maintained and inspected:
a)Dry-dock number two, wingwall cranes # 33 and # 34: As required by the
Portal, Tower
and Pedestal Cranes Standard ASME B30.4-2003, Chapter 4-2, Inspection,
Testing and
Maintenance, dated reports and records were not made as required by
section 4-2.1.3
(frequent inspections) and 4-2.1.4 (periodic inspections) and signed and
dated reports
were not available as required by section 4-2.2.3 (test records)
b)Dry-dock number two, wingwall cranes # 33 and # 34: As required by ASME
B30.4-
2003, Section 4-2.3.1, the employer failed to implement a preventative
maintenance
program based on the crane manufacturers recommendations.
A FEASIBLE AND ACCEPTABLE METHOD TO CORRECT THIS HAZARD IS TO
FOLLOW THE PROCEDURES OUTLINED IN ASME B30.4-2003 INSPECTION TESTING
AND MAINTENANCE SECTION 4-2.2.3. WHICH STATES DATED REPORTS AND
RECORDS SHALL BE MADE AND AVAILABLE FOR ALL TESTS OF REPAIRED,
ALTERED OR MODIFIED CRANES REQUIRED UNDER PARAS. 4-2.2.1 AND 4-2.2.2.
ANOTHER FEASIBLE AND ACCEPTABLE METHOD TO CORRECT THIS HAZARD
WOULD BE TO ESTABLISH A CRANE MAINTENANCE PROGRAM AS REQUIRED IN
ASME B30.4-2003 SECTION 4-2.3.1, WHICH STATES A PREVENTATIVE
MAINTENANCE PROGRAM BASED ON THE CRANE MANUFACTURER'S (HYDRALIFT
AMCLYDE) RECOMMENDATIONS SHOULD BE ESTABLISHED.

5(a)(1)

Serious Gravity 10 2 instances 2 exposed
Issued
Abate by
Penalty
Initial $5000.00 · Current $5000.00
Section 5(a)(1) of the Occupational Safety and Health Act of 1970:  The
employer did not
furnish employment and a place of employment which were free from
recognized hazards that
were causing or likely to cause death or serious physical harm to
employees in that crane
operators  were exposed to injury caused by an uncontrolled wingwall crane
crashing onto the
drydock floor:
a)Floating dry-dock number two, east wingwall: During a docking operation
the dry- dock
was in a nine foot trim to the north and an American Model 203 Revolver
Crane #34
with operator onboard was not secured by the pelican hook provided at the
south end of
the dry-dock or by rail clamps installed on the equipment. A travel brake
failure
along
with the trim on the dock resulted in the crane unintentionally traveling
the length of the
wingwall (850') eventually falling approximately 60' on to the drydock
floor .
b)Floating dry-dock number two, west wingwall: While the dock was in a
nine foot trim
to the north, an American Model 203 Revolver crane #33 was not secured by
the pelican
hook provided at the south end of the dry-dock or by the rail clamps
installed on the
equipment.
ONE FEASIBLE AND ACCEPTABLE METHOD OF ABATING THE HAZARD IS TO
FOLLOW THE PROCEDURES CONTAINED IN U.S. NAVY FLOATING DRY-DOCK
ARCO CHECKLIST FOR BALLASTING OR DEBALLASTING EVOLUTIONS FCR
ENCLOSURE (6) PAGE 6-13B-5 STEP R WHICH REQUIRES THAT PORT AND
STARBOARD CRANES BE CLAMPED DOWN FOR DOCKING.
ANOTHER FEASIBLE AND ACCEPTABLE METHOD WOULD BE TO FOLLOW THE
PROCEDURE OUTLINED IN SAN FRANCISCO DRYDOCK, INC. STANDARD
OPERATING PROCEDURE (SOP) FOR CONFIGURATION CONTROL OF FLOATING
DRYDOCK NUMBER 2 ENCLOSURE A, PARAGRAPH 3,B,5 VESSEL ON DRYDOCK
WHICH STATES BOTH WINGWALL CRANES WILL BE SECURED WHILE BALLASTING
OR DEBALLASTING WITH A NAVY VESSEL ON DOCK.

5(a)(1)

Serious Gravity 10 2 instances 2 exposed
Issued
Abate by
Penalty
Initial $5000.00 · Current $5000.00
Section 5(a)(1) of the Occupational Safety and Health Act of 1970:  The
employer did not
furnish employment and a place of employment which were free from
recognized hazards that
were causing or likely to cause death or serious physical harm to
employees in that employees
were exposed to possible injury while operating wingwall cranes without
automatic rail clamps.
a)Drydock number two, wingwall crane # 33:  The crane was originally
equipped with
Automatic Hydraulic rail clamps. In 1997 they were removed and manually
operated rail
clamps installed. The manual clamps were not at least equal to the original
manufacturer's specification in that they would not automatically engage
the rails when
the crane control was in the neutral position.
b)Drydock number two, wingwall crane # 34:  The crane was originally
equipped with
Automatic Hydraulic rail clamps. In 1997 they were removed and manually
operated
clamps installed.  The manual clamps were not at least equal to the
original specification
in that they would not automatically engage the rails when the crane
control was in the
neutral position.
A FEASIBLE AND ACCEPTABLE METHOD TO CORRECT THIS HAZARD IS TO
FOLLOW THE PROCEDURES OUTLINED IN THE PORTAL, TOWER, AND PEDESTAL
CRANES STANDARD ASME B30.4-2003,MAINTENANCE,  SECTION 4-2.3.1 (b) WHICH
STATES REPLACEMENT PARTS SHALL BE AT LEAST EQUAL TO THE
MANUFACTURER'S SPECIFICATION.

5(a)(1)

Deleted Serious Gravity 10 1 instance 2 exposed
Issued
Abate by
Penalty
Initial $5000.00 · Current $5000.00
Section 5(a)(1) of the Occupational Safety and Health Act of 1970:  The
employer did not
furnish employment and a place of employment which were free from
recognized hazards that
were causing or likely to cause death or serious physical harm to
employees in that employees
were exposed to possible injury while being hoisted by a wingwall crane:
a)Drydock number two, wingwall crane # 34: The crane was used to lift
employees
approximately sixty feet from the high water platform and wingwall on to
barges inside
the dry-dock to facilitate centering of the barges during docking, and
there were less
hazardous alternatives which could be used to place employees on the
barges.
b)Drydock number two, wingwall crane # 33: The crane was used to lift
employees
approximately sixty feet from the high water platform and wingwall on to
barges inside
the dock to facilitate centering of the barges during docking, and there
were
less
hazardous alternatives which could be used to place employees on the
barges.
A FEASIBLE AND ACCEPTABLE METHOD TO CORRECT THIS HAZARD IS
TOFOLLOW THE  PROCEDURES REQUIRED IN ASME  B30.23-2005, PERSONNEL
LIFTING SYSTEMS, SECTION 23-3.2.1(b) WHICH  REQUIRES THE PERSONNEL LIFT
AUTHORIZER TO VERIFY THAT THERE ARE NO LESS HAZARDOUS ALTERNATIVES
TO PERFORMING THE WORK, OR PROVIDING ACCESS TO THE AREA. THE
PERSONNEL LIFT SHALL NOT BE AUTHORIZED WHEN LESS HAZARDOUS MEANS
ARE FEASIBLE.
EXAMPLES OF LESS HAZARDOUS MEANS WHICH WERE AVAILABLE TO GAIN
ACCESS TO THE  BARGES WOULD BE TO BOARD THE EMPLOYEES PIERSIDE BY
USE OF GANGWAY OR BY TRANSFERRING FROM A SMALL BOAT INSIDE THE DRY-
DOCK.
Recent events (2)
  • — I (S) $5000.00
  • — Z (S) $5000.00

1915.74 A01

Deleted Serious Gravity 10 1 instance 2 exposed
Issued
Abate by
Penalty
Initial $5000.00
Recent events (2)
  • — I (S)
  • — Z (S) $5000.00

5(a)(1)

Deleted Serious Gravity 10 3 instances 2 exposed
Issued
Abate by
Penalty
Initial $5000.00 · Current $5000.00
Section 5(a)(1) of the Occupational Safety and Health Act of 1970:  The
employer did not
furnish employment and a place of employment which were free from
recognized hazards that
were causing or likely to cause death or serious physical harm to
employees in that employees
were exposed to possible injury from accidents caused by the crane
operator not being allowed
to conduct a trial personnel lift prior to the actual lift:
a)Drydock number two, east wingwall, crane # 34: Two employees were hoisted
approximately sixty feet high in a manbasket by crane number thirty four
from the  east
wingwall of dry-dock number two to Manson crane barge EINER, then from the
barge
to the highwater platform, and a trial lift was not performed to ascertain
that hoist
equipment setup and configuration were correct, load capacities were
accurate, and that
no hazardous interferences exist, and to further demonstrate the operators
operational
competence.
b)Drydock number two, west wingwall crane # 33: Two employees were hoisted
in a
manbasket approximately sixty feet high and moved by crane number thirty
three from
west wingwall to barge number forty seven, and a trial lift was not
performed to
ascertain that hoist equipment setup and configuration were correct, load
capacities were
accurate, and that no hazardous interferences exist, and to further
demonstrate operators
operational competence.
c)Drydock number two, west wingwall crane # 33: an employee was hoisted in
a
manbasket approximately sixty feet high and moved by crane number thirty
three from
barge number forty seven to the west wingwall, and a trial lift was not
performed to
ascertain that hoist equipment setup and configuration were correct, load
capacities were
accurate, and that no hazardous interferences exist, and to further
demonstrate operators
operational competence.
ONE FEASIBLE AND ACCEPTABLE METHOD TO CORRECT THIS HAZARD IS TO
FOLLOW THE PROCEDURES OUTLINED IN PERSONNEL LIFTING SYSTEMS
STANDARD ASME B23-2005, SECTION 23-3.2.2(a)(9), HOISTING OPERATOR, WHICH
STATES "PERFORM A TRIAL LIFT PRIOR TO LIFTING PERSONNEL WITH THE
PLATFORM ON EACH SHIFT AND AFTER ANY CHANGE OF SETUP, LOCATION,
HOIST EQUIPMENT CONFIGURATION OR OPERATORS."
ANOTHER FEASIBLE AND ACCEPTABLE METHOD TO CORRECT THE HAZARD IS
TO FOLLOW THE PROCEDURES OUTLINED IN UNITED STATES CRANES, INC.
SUPER CAGE USER/ OPERATOR GUIDELINES PAGE 16 ITEM (ii)(D), WHICH STATES
THAT A COMPLETE TRIAL RUN SHALL BE PERFORMED TO TEST THE ROUTE OF
TRAVEL BEFORE EMPLOYEES ARE ALLOWED TO OCCUPY THE PLATFORM.
Recent events (2)
  • — I (S) $5000.00
  • — Z (S) $5000.00

5(a)(1)

Deleted Serious Gravity 10 3 instances 2 exposed
Issued
Abate by
Penalty
Initial $5000.00 · Current $5000.00
Section 5(a)(1) of the Occupational Safety and Health Act of 1970:  The
employer did not
furnish employment and a place of employment which were free from
recognized hazards that
were causing or likely to cause death or serious physical harm to
employees in that employees
were exposed to possible injury from accidents caused by the employer not
conducting frequent
or periodic inspections and maintaining records of such inspections for
the super cage
manbasket:
a)Drydock number two, east wingwall, crane  # 34: Two employees were
hoisted
approximately sixty feet high in a manbasket by crane # 34 from the east
wingwall of
dry-dock number two to Manson crane barge EINER, then from the barge to the
highwater platform, and periodic and frequent inspections of the SuperCage
manbasket
used to make the lift were not conducted.
b)Drydock number two, west wingwall, crane # 33: Two employees were hoisted
approximately sixty feet high in a manbasket by crane # 33 from the west
wingwall
number two to Manson crane barge EINER, then from the barge to the
highwater
platform, and  periodic and frequent inspection records of Lifting
Technologies
manbasket used to make the lift were not kept by or with the platform,
available for
review.
ONE FEASIBLE AND ACCEPTABLE METHOD TO CORRECT THIS HAZARD IS TO
FOLLOW THE PROCEDURES REQUIRED IN PERSONNEL LIFTING SYSTEMS
STANDARD B30.23-2005, SECTION 23-2.1.1.(b)(2)(a) AND (b),INSPECTION,
TESTING
AND MAINTENANCE WHICH STATES FOR FREQUENT INSPECTIONS "DATED
RECORDS FOR THE HOISTING EQUIPMENT AND PERSONNEL PLATFORM  SHALL
BE MADE AND KEPT BY THE PLATFORM USER FOR THE DURATION OF THE
PERSONNEL LIFT OPERATION." FOR PERIODIC INSPECTIONS, DATED RECORDS
FOR THE PLATFORM SHALL BE MADE BY THE PLATFORM OWNER. THE LAST
PERIODIC INSPECTION SHALL BE KEPT WITH THE PLATFORM AND AVAILABLE
FOR REVIEW."
ANOTHER FEASIBLE AND ACCEPTABLE METHOD TO CORRECT THE HAZARD IS
TO FOLLOW THE PROCEDURES OF ASME B30.23-2005 SECTIONS 23-2.1.1.(c)(1) AND
(2) AS REQUIRED BY US CRANE, INC SUPERCAGE USER/ OPERATOR GUIDELINES.
Recent events (2)
  • — I (S) $5000.00
  • — Z (S) $5000.00

1915.111 A

Serious Gravity 10 2 instances 2 exposed
Issued
Abate by
Penalty
Initial $5000.00 · Current $5000.00

1915.117 B

Serious Gravity 10 1 instance 2 exposed
Issued
Abate by
Penalty
Initial $5000.00 · Current $2500.00 Reduced
Recent events (2)
  • — I (S) $2500.00
  • — Z (S) $5000.00

1915.73 D

Serious Gravity 10 1 instance 1 exposed
Issued
Abate by
Penalty
Initial $5000.00 · Current $2500.00 Reduced
Recent events (2)
  • — I (S) $2500.00
  • — Z (S) $5000.00

View BAE SYSTEMS SAN FRANCISCO SHIP REPAIR's full OSHA safety record →