EL PASO, TX —
OSHA Inspection: WESTERN REFINING COMPANY, L.P.
Complaint inspection · Safety discipline
At a glance
On , OSHA opened a complaint safety inspection of WESTERN REFINING COMPANY, L.P. in 6501 TROWBRIDGE, EL PASO, TX 79905 (NAICS 324110). OSHA activity number 313498255.
Where did this inspection happen?
- Establishment
- WESTERN REFINING COMPANY, L.P.
- Site address
- 6501 TROWBRIDGE
- City
- EL PASO
- State
- TX
- ZIP
- 79905
What kind of inspection was it?
- Inspection type
- Complaint (B)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- Y
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 324110
- SIC code (legacy)
- 2911
- Employees
- 400
- Ownership type
- A
Citations
4 citations on file for this inspection.
5(a)(1)
- Issued
- Abate by
- Penalty
- Initial $6300.00 · Current $6300.00
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or were likely to cause death or serious physical harm to employees in that employees were exposed to the condition(s) listed below: On or about June 18, 2010, employees were exposed to flammable vapors due to a hazardous release of flammable materials from the Vapor Recovery Unit, while switching vapor recovery unit pumps. The Vapor Recovery Unit system interlock was reset and this caused an increase in vapor pressure and caused the pressure relief valve from the vapor line system to release flammable vapors into the atmosphere: 1) The employer did not follow their established Switch Vacuum Pump at Vapor Recovery Unit Procedure (MKT-NP-4822), while switching vapor recovery unit pumps. 2) The employer did not identify the Vapor Recovery Unit interlock system in their Switch Vacuum Pump at Vapor Recovery Unit Procedure (MKT-NP-4822). The procedure does not include any instructions for the interlock system and what is expected of employees to reset or not reset the interlock system. 3) The employer did not train all operators on the Switch Vacuum Pump at Vapor Recovery Unit Procedure (MKT-NP-4822). 4) The employer did not evaluate mechanical and system design features in the Vapor Recovery Unit, that are likely to produce significant human error. 5) The employer did not update the Vapor Recovery Unit - Piping & Instrument Diagram (PD-53-45304-001), when mechanical changes were performed in the Vapor Recovery Unit. AMONG OTHER METHODS, ONE FEASIBLE AND ACCEPTABLE METHOD TO CORRECT THIS HAZARD IS: 1) Ensure that operators and lead operators follow the established procedure Switch Vacuum Pump at Vapor Recovery Unit Procedure (MKT-NP-4822) when switching Vapor Recovery Unit pumps. 2) Include written procedures for the Vapor Recovery Unit interlock system in the Switch Vacuum Pump at Vapor Recovery Unit Procedure (MKT-NP-4822), for employees to follow when switching Vapor Recovery Unit pumps. 3) Ensure that all employees are properly and effectively trained on the Switch Vacuum Pump at Vapor Recovery Unit Procedure (MKT-NP-4822). 4) Conduct an evaluation of possible significant human errors that may occur when operators are switching pumps in the Vapor Recovery Unit and implement written procedures, training and system design to prevent human error from creating a possible catastrophic event. 5) Ensure that existing Piping & Instrument Diagrams are updated on a timely manner to ensure that P&ID's reflect the most current mechanical and system changes.
Recent events (2)
- — F (S) $6300.00
- — Z (S) $6300.00
1910.147 C06 IC
- Issued
- Abate by
- Penalty
- Initial $6300.00 · Current $6300.00
Recent events (2)
- — F (S) $6300.00
- — Z (S) $6300.00
1910.303 G01 I
- Issued
- Abate by
- Penalty
- Initial $3150.00 · Current $3150.00
Recent events (2)
- — F (S) $3150.00
- — Z (S) $3150.00
1910.305 B02
- Issued
- Abate by
- Penalty
- Initial $3150.00 · Current $3150.00
Recent events (2)
- — F (S) $3150.00
- — Z (S) $3150.00
More inspections at WESTERN REFINING COMPANY, L.P.
EL PASO, TX—2019-02-12 00:00:00
WESTERN REFINING COMPANY, L.P.
TUCSON, AZ—2009-09-23 00:00:00
WESTERN REFINING COMPANY, L.P.
View WESTERN REFINING COMPANY, L.P.'s full OSHA safety record →
More inspections in this industry (NAICS 324110)
TORRANCE, CA—2026-07-15
TORRANCE REFINING COMPANY LLC
EL SEGUNDO, CA—2026-06-30
CHEVRON U.S.A. INC.
EL SEGUNDO, CA—2026-06-30
CHEVRON U.S.A. INC.
TRAINER, PA—2026-06-26
MONROE ENERGY, LLC
RICHMOND, CA—2026-06-17
CHEVRON U.S.A. INC.
More inspections in TX
WICHITA FALLS, TX—2026-07-16
UNITED RENTALS, INC.
SAN MARCOS, TX—2026-07-16
CASA MECHANICAL SERVICES, LTD.
CLARKSVILLE, TX—2026-07-15
SEQUOIAS TREE EXPERT LLC
EL PASO, TX—2026-07-15
SURE STEEL
CORPUS CHRISTI, TX—2026-07-15
NORTH STAR ENERGY SOLUTIONS LLC
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 313498255.