BIRCH TREE, MO —
OSHA Inspection: JBSR LUMBER
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of JBSR LUMBER in RR 2, BOX 273, BIRCH TREE, MO 65438 (NAICS 321113). OSHA activity number 336665989.
Where did this inspection happen?
- Establishment
- JBSR LUMBER
- Site address
- RR 2, BOX 273
- City
- BIRCH TREE
- State
- MO
- ZIP
- 65438
- Mailing
- RR 2, BOX 273, BIRCH TREE, MO 65438
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Complete (A)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 321113
- Employees
- 15
- Ownership type
- A
Citations
7 citations on file for this inspection.
1910.147 D04 I
- Issued
- Abate by
- Penalty
- Initial $2000.00 · Current $1400.00 Reduced
General-duty citation text
29 CFR 1910.147(d)(4)(i): Lockout or tagout devices were not affixed to each energy isolating device by authorized employees: a. Where lockout work was done, such as, but not limited to, head saw sharpening and repair and band saw blade change, equipment was not locked out. Abatement certification and abatement documentation is required for this violation. The documentation should include written verification of abatement, applicable measurements or monitoring results, and photographs or videos which you believe will be helpful. The abatement certification sheet is enclosed with the citation(s).
Recent events (2)
- — I (S) $1400
- — Z (S) $2000
1910.147 C04 I
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section: a. Where lockout work was done, such as, but not limited to, blade sharpening and changing, a lockout program and procedures were not in writing, including the requirements for lockout procedures as stated at 1910.147(c)(4)(ii)(A) through (D). Abatement certification and abatement documentation is required for this violation. The documentation should include written verification of abatement, applicable measurements or monitoring results, and photographs or videos which you believe will be helpful. The abatement certification sheet is enclosed with the citation(s).
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.147 C07 I
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1910.147(c)(7)(i): The employer did not provide adequate training to ensure that the purpose and function of the energy control program was understood by employees: a. Where lockout work was done, such as, but not limited to, blade sharpening and changing, training, acccording to the requirements of the standard, was not provided to authorized employees (those performing work requiring lockout) and affected employees (those operating equipment and only requiring purpose and use lockout training). (Note: training must be documented.) Abatement certification and abatement documentation is required for this violation. The documentation should include written verification of abatement, applicable measurements or monitoring results, and photographs or videos which you believe will be helpful. The abatement certification sheet is enclosed with the citation(s).
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.219 F03
- Issued
- Abate by
- Penalty
- Initial $1200.00 · Current $840.00 Reduced
General-duty citation text
29 CFR 1910.219(f)(3): Sprocket wheels and chains which were seven 7 feet or less above floors or platforms were not enclosed: a. The head saw feed chain was operated with the guard off. Abatement certification and abatement documentation is required for this violation. The documentation should include written verification of abatement, applicable measurements or monitoring results, and photographs or videos which you believe will be helpful. The abatement certification sheet is enclosed with the citation(s).
Recent events (2)
- — I (S) $840
- — Z (S) $1200
1910.219 M01 I
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1910.219(m)(1)(i): Standard materials were not secured by the use of the following: expanded metal, perforated or solid sheet metal, wire mesh on a frame of angle iron, or iron pipe securely fastened to floor or to frame of machine: a. The ventilation blower belt and pulleys to the band saw were guarded with cardboard. Abatement certification and abatement documentation is required for this violation. The documentation should include written verification of abatement, applicable measurements or monitoring results, and photographs or videos which you believe will be helpful. The abatement certification sheet is enclosed with the citation(s).
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.95 D01
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1910.95(d)(1): When information indicated that any employee's exposure equaled or exceed the 8-hour time-weighted average of 85 decibels, the employer did not develop and implement a monitoring program: a. Where sound level meter readings resulted in exposure up to 99 dBA, noise monitoring was not conducted to determine the need for a hearing conservation program, incluidng initial and annual hearing tests and training. (Note: establishing a hearing conservation program, including annual hearing tests and training, can be provided as an abatement to this violation without conducting 8 hr. noise monitoring.) Abatement certification and abatement documentation is required for this violation. The documentation should include written verification of abatement, applicable measurements or monitoring results, and photographs or videos which you believe will be helpful. The abatement certification sheet is enclosed with the citation(s).
Recent events (2)
- — I (O) $0
- — Z (O) $0
1910.178 L06
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1910.178(l)(6): The employer did not certify that each operator had been trained and evaluated as required by this paragraph (l): a. Where a forklift and two loaders were operated, powered industrial truck training was not certified, indicating that training, according to the requirements of the standard ("classroom" instruction, demonstration, and evaluation) was provided to equipment operators. Abatement certification and abatement documentation is required for this violation. The documentation should include written verification of abatement, applicable measurements or monitoring results, and photographs or videos which you believe will be helpful. The abatement certification sheet is enclosed with the citation(s).
Recent events (2)
- — I (O) $0
- — Z (O) $0
More inspections in this industry (NAICS 321113)
COCHRANTON, PA—2026-07-15 00:00:00
CRAWFORD COUNTY HARDWOODS, LLC
COCHRANTON, PA—2026-07-15 00:00:00
CRAWFORD COUNTY HARDWOODS, LLC
LIVE OAK, FL—2026-07-09 00:00:00
BINDERHOLZ LIVE OAK LLC
LAFAYETTE, TN—2026-07-08 00:00:00
CLARK LUMBER COMPANY, LLC
GASTON, OR—2026-07-07 00:00:00
317744699 - STIMSON LUMBER COMPANY
More inspections in MO
CLINTON, MO—2026-07-14 00:00:00
TORCHYLO BUILDERS, LLC.
BLUE SPRINGS, MO—2026-07-13 00:00:00
JORGE MERIDA
KANSAS CITY, MO—2026-07-09 00:00:00
NIAGARA BOTTLING
MONETT, MO—2026-07-09 00:00:00
MONETT METALS INC.
KANSAS CITY, MO—2026-07-08 00:00:00
NGC CONSTRUCTION LLC
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 336665989.