WASHINGTON, DC —
OSHA Inspection: WR MASONRY LLC
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of WR MASONRY LLC in 5017 ESKRIDGE TERRACE, WASHINGTON, DC 20016 (NAICS 238140). OSHA activity number 346090822.
Where did this inspection happen?
- Establishment
- WR MASONRY LLC
- Site address
- 5017 ESKRIDGE TERRACE
- City
- WASHINGTON
- State
- DC
- ZIP
- 20016
- Mailing
- 2107 ORCHARD PLACE, HYATTSVILLE, MD 20785
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Complete (A)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238140
- Employees
- 3
- Ownership type
- A
Citations
6 citations on file for this inspection.
1926.100 A
- Issued
- Abate by
- Penalty
- Initial $4351.00 · Current $4351.00
General-duty citation text
29 CFR 1926.100(a): Employees working in areas where there was a possible danger of head injury from impact, or falling or flying objects, or from electrical shock and burns, were not protected by protective helmets: a) On or about July 20, 2022; Front area of the residential project (Eastside); employees working under the scaffold system were not wearing hard hats to protect them from falling objects including, but not limited to, trowels, knives and materials used by employees 18-feet overhead. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet), in addition, documentation demonstrating the abatement is complete must be included with your certification. This documentation may include, but is not limited to evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (1)
- — Z (S) $4351
1926.451 B01
- Issued
- Abate by
- Penalty
- Initial $4351.00 · Current $4351.00
General-duty citation text
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii): a) On or about July 20, 2022; Front area of the residential project (Eastside); the working platform of the scaffold system was not fully planked where up to 3 scaffold planks were missing exposing the employees to an 18-foot fall to ground level while prepping the exterior wall for stucco. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet), in addition, documentation demonstrating the abatement is complete must be included with your certification. This documentation may include, but is not limited to evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (1)
- — Z (S) $4351
1926.451 E01
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used. Crossbraces were used as a means of access. a) On or about July 20, 2022; Front area of the residential project (Eastside); the employees were accessing the work platform 18-feet above the ground level by climbing the cross braces and frame of the scaffold system. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet), in addition, documentation demonstrating the abatement is complete must be included with your certification. This documentation may include, but is not limited to evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (1)
- — Z (S) $0
1926.451 F07
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.451(f)(7): Scaffolds were not erected, moved, dismantled, or altered, by trained and experienced employees under the supervision and direction of a competent person qualified in scaffold erection, moving, dismantling or alteration:; Such activities were not performed only by experienced and trained employees selected for such work by the competent person. a) On or about July 20, 2022; Front area of the residential project (Eastside), the employer had not ensured that a competent person evaluated the scaffold system who understood the potential hazards including, but not limited to, fall hazards, and proper construction of the working platform, which exposed the employees to an estimated 18-foot fall hazard. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet), in addition, documentation demonstrating the abatement is complete must be included with your certification. This documentation may include, but is not limited to evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (1)
- — Z (S) $0
1926.451 G01 VII
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.451(g)(1)(vii): Each employee on a scaffold, not otherwise specified in paragraphs (g)(1)(i) through (g)(1)(vi) of this section, more than 10 feet (3.1 m) above lower level was not protected from falls by the use of personal fall arrest systems or guardrail systems meeting the requirements of paragraph (g)(4) of this section. a) On or about July 20, 2022; Front area of the residential project (Eastside); employees were exposed to an 18-foot fall while conducting masonry work on the upper, peak areas, of the wall when standing on insulation bundles which elevated the work platform above the protective guard rail system. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet), in addition, documentation demonstrating the abatement is complete must be included with your certification. This documentation may include, but is not limited to evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (1)
- — Z (S) $0
1926.451 H02 II
- Issued
- Abate by
- Penalty
- Initial $0.00 · Current $0.00
General-duty citation text
29 CFR 1926.451(h)(2)(ii): A toeboard was not erected along the edge of platforms more than 10 feet (3.1 m) above lower levels for a distance sufficient to protect employees below: a) On or about July 20, 2022; Front area of the residential project (Eastside); the working platforms of the scaffold system had no toe-boards to prevent masonry tools including, but not limited to, trowels and knives or materials from falling and striking the employee working on the ground. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet), in addition, documentation demonstrating the abatement is complete must be included with your certification. This documentation may include, but is not limited to evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (1)
- — Z (S) $0
More inspections in this industry (NAICS 238140)
RENO, NV—2026-07-16 00:00:00
DC MASONRY
WINNETKA, IL—2026-07-15 00:00:00
CHICAGO STUCCO CO.
LODI, NJ—2026-07-15 00:00:00
J & O MASONRY CONTRACTORS
DORAVILLE, GA—2026-07-14 00:00:00
SUDLOW CONCRETE, INC.
FLAGLER BEACH, FL—2026-07-14 00:00:00
PLANET DESIGN SERVICES, INC.
More inspections in DC
WASHINGTON, DC—2026-06-30 00:00:00
U.S. DEPARTMENT OF AGRICULTURE
WASHINGTON, DC—2026-06-16 00:00:00
MACY'S
WASHINGTON, DC—2026-06-02 00:00:00
RIGO MULTISERVICES
WASHINGTON, DC—2026-06-02 00:00:00
DDC CPL LLC
WASHINGTON, DC—2026-06-02 00:00:00
DDC CPL LLC
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 346090822.