COLORADO SPRINGS, CO —
OSHA Inspection: WHITE AUTOMOTIVE (WITCO)
Complaint inspection · Health discipline
At a glance
On , OSHA opened a complaint health inspection of WHITE AUTOMOTIVE (WITCO) in 4401 NO. MARK DABLIN BLVD., COLORADO SPRINGS, CO 80901 (NAICS 000000). OSHA activity number 100014745.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- WHITE AUTOMOTIVE (WITCO)
- Site address
- 4401 NO. MARK DABLIN BLVD.
- City
- COLORADO SPRINGS
- State
- CO
- ZIP
- 80901
- Mailing
- 891 GORDON LINE, BIRMINGHAM, MI 48009
What kind of inspection was it?
- Inspection type
- Complaint (B)
- Scope
- Partial (B)
- Discipline
- Health
- Advance notice
- No
- Union status
- A
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Data loaded
Establishment context
- NAICS code
- 000000
- SIC code (legacy)
- 3714
- Employees
- 200
- Ownership type
- A
Citations
5 citations on file for this inspection.
1910.36 B04
- Issued
- May 1, 1990
- Abate by
- Apr 22, 1991
- Penalty
- Initial $800 · Current $800
Recent events (3)
- — F (S) $800.00
- — I (S) $800.00
- — Z (S) $800.00
1910.212 A01
- Issued
- May 1, 1990
- Abate by
- Apr 22, 1991
- Penalty
- Initial $700 · Current $700
Recent events (3)
- — F (S) $700.00
- — I (S) $700.00
- — Z (S) $700.00
1910.252 E02 III
- Issued
- May 1, 1990
- Abate by
- Apr 22, 1991
- Penalty
- Initial $600 · Current $600
Recent events (3)
- — F (S) $600.00
- — I (S) $600.00
- — Z (S) $600.00
5(a)(1)
- Issued
- May 1, 1990
- Abate by
- Apr 22, 1991
- Penalty
- Initial $900 · Current $900
General-duty citation text
5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to excess-ive radio frequency and electrical burns: (a) In the radio frequency heat sealer area: Employees were tasked to operate the five (5) Thermatron heat sealers in the absence of a safety and health program which addresses the health and safety hazards created by exposure of operators and maintenance personnel to 27.12 MHZ nonionizing radiation. Exposures occurred on or about 10 January and 22 February 1990 during heat sealing, maintenance, sewing and as a result of employees' positions in energy fields during duty cycles of other adjacent Thermatron heat sealers. Excessive exposure to absorbed energy from radio frequencies can cause a variety of health effects including reproductive damage, immunosuppressive illnesses and cardiopulmonary dysfunction. (b) In the radio frequency heat sealer area: Maintenance employees conducted service and maintenance operations such as, but not limited to, set-up of dies, adjusting duty cycles, electrical repairs, repairs of arc-out and discharge rectifiers on the Thermatron 1,4,10,15 and 20 KW RF Heat Sealers and were exposed to the hazards of severe electrical burns/shocks and crushing. The Heat Sealers are serviced by 440 volts, producing 29,000 volts and 70 amps. The maintenance operations are performed in the absence of a lock-out/tag-out procedure which would physically prevent the re-energization of the equipment. Feasible methods of abatement include, but are not limited to, the implementation of a comprehensive radio frequency heat sealer health and safety program with the following elements: 1. Identification of employees at risk of exposure. 2. Training of employees at risk in all aspects of safety and health related to radio frequency nonionizing radiation. 3. Effective shielding of heat sealer radio frequency electrodes to eliminate leakage of nonionizing radiation. 4. Periodic measurement of field strenghts around electrodes to assure the integrity of the shielding. 5. Increasing the distance between operators, and maintenance personnel and the energized secondary sealers in the immediate area (e.g. increase timed surge delay to allow operator to step back across 4 feet demarcation around each source electrode). 6. Posting of the heat sealer area with the appropriate warning signs (e.g. Warning Radio Frequency Radiation Hazard). 7. Use of a chair constructed of nonconductive material for the operators of heat sealers (i.e. operator of heat sealer #5 needs a wooden chair). 8. Use of elevated operator platforms constructed of nonconductive material (i.e. operators of heat sealers #1 and #5 (e.g. wood). 9. Use of grounding connectors for conductive equipments located in the energy fields which become energized, to prevent a shock hazard (e.g. sewing machines, storage trays/racks on either end, in front of, and below, the heat sealers).
Recent events (3)
- — F (S) $900.00
- — I (S) $900.00
- — Z (S) $900.00
5(a)(1)
- Issued
- May 1, 1990
- Abate by
- Apr 22, 1991
- Penalty
- Initial $9,000 · Current $9,000
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to cumulative trauma disorders: (a) The employees performing sewing, cutting, snipping and trimming operations in the Accessories Area, CAMI Area, HUM-V Area, Recreational Vechicle Areas and other manu- vacturing areas were exposed to undue repetitive motion trauma. This trauma was due to repeated hand, wrist, shoulder and upper torso exertions causing, aggravating or precipitating Carpal Tunnel Syndrome, tendinitis, tenosynovitis, numbness of fingers and hands, strains of the fingers, thumbs, hands, wrists, forearms, upper arms, elbows and necks, epicondylites and ganglionic cysts. Feasible and useful remedies include, but are not limited to, the following: 1) Education of employees as to the causes, nature of, and the reduction and treatment of Repetitive Trauma Disorders such as, but are not limited to, Carpal Tunnel Syndrome; 2) Training of employees and supervisors in exercises and conduct of sewing duties to recognize and reduce the effects of repetive trauma; 3) Utilization of ergonomically designed scissors, snips, and powered cutting devices for multiple layer cutting operations; maintenance of a sharp cutting edge on tools; 4) Utilization of ergonomically designed chairs; 5) Reduction of employee standards for production quotas on numbers of items produced per unit time; 6) Engage the services of an ergonomics consultant to further analyse the operations; 7) Adjustment of employee work stations relevant to employees' height; 8) Adjustment of employee work stations to reduce handling distances, twisting and reaching; 9) Implementation of employee exercise program to strengthen affected portions of the torso; 10) Implementation of a medical surveillance program designed to identify, treat, prevent, and lessen the effects of cumulative trauma disorders. STEP 1: A comprehensive training program for employees, supervisors, and management personnel which emphasizes; recognition, prevention, management, exercises to reduce traumas, methods to reduce the number of motions, work station design, ergonomic tools and equipment, and medical treatments of repetitive trauma disorders. STEP 2: A written detailed plan of progressive abatement leading to complete abatement shall be submitted to the Area Director. This plan shall include, at a minimum, target dates for the following actions which must be consistent with the abatement dates required by this citation: 1) Evaluation of engineering/administrative control options; 2) Selection of optimum control methods and completion of design; 3) Procurement, installation and operation of selected control measures; 4) Testing and acceptance or modification or redesign of controls; STEP 3: Abatement shall be completed by the implementation of feasible engineering and/or administrative controls and verification of their effectiveness in achieving compliance.
Recent events (3)
- — F (W) $9000.00
- — I (W) $9000.00
- — Z (W) $9000.00
More inspections in this industry (NAICS 000000)
More inspections in CO
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 100014745.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.