Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: RAND-WHITNEY ROBERTSON CORPORATION

Complaint inspection · Health discipline

On , OSHA opened a complaint health inspection of RAND-WHITNEY ROBERTSON CORPORATION in ROUTE 163, MONTVILLE, CT 06352 (NAICS 000000). OSHA activity number 100774546.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Rand-Whitney Robertson Corporation — free Get an email when a new federal OSHA severe-injury report for Rand-Whitney Robertson Corporation is published. One employer, no account, unsubscribe in one click.
Site address
ROUTE 163
City
MONTVILLE
State
CT
ZIP
06352
Mailing
BOX 38, ROUTE 163, MONTVILLE, CT 06352
Inspection type
Complaint (B)
Scope
Partial (B)
Discipline
Health
Advance notice
No
Union status
Y
Opened
Closing conference
Case closed
Data loaded
NAICS code
000000
SIC code (legacy)
2621
Employees
200
Ownership type
A

14 citations on file for this inspection.

5(a)(1)

Serious Gravity 08 280 instances 560 exposed
Issued
Dec 12, 1990
Abate by
May 31, 1991
Penalty
Initial $800 · Current $525 Reduced
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The
employer did not furnish employment and a place of employment which were
free from recognized hazards that were causing or likely to cause death
or serious physical harm to employees in that employees were exposed to
repetitive upper extremity body motion resulting in stress likely to
cause cumulative trauma disorders:
GLUING DEPARTMENT: EMPLOYEES WHO WORKED IN THIS DEPARTMENT WERE
EXPOSED TO:
A) GRIP FORCES, REPETITIVE HAND AND WRIST MOTIONS AND AWKWARD BODY
POSTURES WHICH CAUSED UPPER EXTREMITY CUMULATIVE TRAUMA DISORDERS
INCLUDING CARPEL TUNNEL SYNDROME, TENDONITIS AND GANGLION.
B) FREQUENT REPETITION OF MANUAL MATERIAL HANDLING WITH TORSO TWISTING
DURING LIFTING BODY POSITIONS THAT RESULTED IN LOWER BACK INJURIES.
WHILE ULTIMATE RESPONSIBILITY FOR HAZARD CORRECTION RESTS ON THE
EMPLOYER, SOME FEASIBLE METHODS TO ADDRESS THE PROBLEMS OR REDUCE THE
HAZARDS INCLUDE, BUT ARE NOT LIMITED TO:
STACKERS:
1) TRAIN EMPLOYEES TO WAIT FOR MATERIALS TO COME TO THEM. REACHING TO
PULL MATERIALS SHOULD BE LIMITED TO 16-17 INCHES OR LESS.
2) TRAIN EMPLOYEES TO MOVE ALONG THE CONVEYOR. THIS WOULD ENABLE THEM
TO POSITION THEIR BODIES IN FRONT OF THE MATERIALS TO BE HANDLED,
THUS MINIMIZING BODY TWISTS.
3) SHORTEN THE CONVEYOR. THIS ALLOWS THE EMPLOYEE TO STAND AT THE END
WHERE THE PRODUCT CAN BE DELIVERED TO THE EMPLOYEE ELIMINATING THE
NEED TO REACH.
4) UTILIZE ADJUSTABLE PACKING STANDS SO EMPLOYEES DO NOT REACH UP AND
OVER THE EDGE OF THE BOX TO PLACE MATERIALS INTO PACKING BOXES. BOTH
HEIGHT AND ANGLE SHOULD BE ADJUSTABLE. IT IS ALSO ADVANTAGEOUS TO
HAVE THE STANDS MOVABLE, MINIMIZING THE DISTANCE BETWEEN PICKUP AND
DELIVERY POINTS.
5) DESIGN A CLAMPING DEVICE TO SECURE MATEIRALS WHILE THEY ARE BEING
PACKED INTO SHIPPING BOXES. THIS ELIMINATED THE PINCH GRIP WORK.
6) INCREASE THE AMOUNT OF ADJUSTABLITY OF THE PACK OFF STAND. THIS
ALLOWS GREATER ACCESS TO EMPLOYEES AND MINIMIZES THE AMOUNT OF
HAND MANIPULATION REQUIRED DURING PACKING.
7) EDUCATE EMPLOYEES ON THE IMPORTANCE OF MAINTAINING NEUTRAL WRIST
POSITIONS WHILE PERFORMING REPETITIVE MOTIONS.
8) MORE FREQUENT ROTATION OF EMPLOYEES TO ALTERNATE WORKSTATIONS.
FEEDERS:
1) INSTALL A LIFT DEVICE TO RAISE AND LOWER PALLETS CONTAINING RAW
MATERIALS. THIS ELIMINATES EXCESSIVE TORSO FLEXING. GENERALLY,
TORSO FLEXING SHOULD BE LIMITED TO 6-10 DEGREES FROM VERTICAL.
2) STACK LOADS ON PALLETS AT LEVELS WHERE THE EMPLOYEES AVOID REACHING
ABOVE STRESSFULL HEIGHTS. HEIGHTS SHOULD ALLOW ACCESS WITHOUT THE
HAND BEING RAISED ABOVE SHOULDER LEVEL OR THE ELBOW BEING RAISED
ABOVE MID TORSO.
3) REDESIGN THE FEED MACHINES TO PULL MATERIAL FROM THE BOTTOM OF THE
STACK. ADDITIONAL FEED STOCK SHOULD BE ADDED TO THE TOP OF THE STACK.
4) WAIT UNTIL ALL MATERIAL HAS FED THROUGH THE MACHINE BEFORE ADDING
MOVE STOCK. THIS ALSO ELIMINATES THE NEED TO LIFT THE MATERIAL
ALREADY ON THE MACHINE EACH TIME NEW STOCK HAS TO BE ADDED.
5) USE TWO EMPLOYEES TO FEED EACH MACHINE. ONE LIFTS THE STOCK WHILE
THE OTHER ADDS STOCK UNDERNEATH.
6) TRAIN EMPLOYEES TO MOVE AROUND PALLETS OR SLIDE THE PRODUCT TO GET
IT CLOSER TO HIS/HER BODY TO GAIN BETTER ACCESS AND MECHANICAL
ADVANTAGE DURING LIFTING.
7) EDUCATE THE EMPLOYEE ON THE BASICS OF BODY BIOMECHANICS AND THE
IMPORTANCE OF MAINTAINING THE WRIST IN AN ERGONOMICALLY NEUTRAL
POSITION.
ABATEMENT SCHEDULE
STEP 1 - SUBMIT TO THE AREA DIRECTOR A WRITTEN DETAILED PLAN OF
ABATEMENT OUTLINING A SCHEDULE FOR THE IMPLEMENTATION OF ENGINEERING
AND/OR ADMINISTRATIVE MEASURES TO CONTROL EMPLOYEE EXPOSURE TO THE
TRAUMA CUMULATIVE TRAUMA DISORDERS REFERENCED IN THIS CITATION. THE
PLAN SHALL INCLUDE, AT A MINIMUM, TARGET DATES FOR THE FOLLOWING
ACTIONS WHICH MUST BE CONSISTENT WITH THE ABATEMENT DATES REQUIRED
BY THIS CITATION.
A) EVALUATION OF THE EXTENT AND LOCATION OF THE HAZARD SOURCE.
B) EVALUATION OF CONTROL MEASURE OPTIONS.
C) SELECTION OF OPTIMUM CONTROL MEASURE(S).
D) DETERMINATION OF CONTROL MEASURE DESIGN.
E) ORDERING AND DELIVERY OF ANY EQUIPMENT AND MATERIALS.
F) INSTALLATION OF CONTROL MEASURES.
G) TRAINING OF EMPLOYEES IN:
1) JOB(S) WHERE THE POTENTIAL FOR REPETITIVE MOTION INJURIES EXIST
2) ERGONOMIC METHOD(S) OF HOLDING AND HANDLING MATERIALS AND
AND PERFORMING REQUIRED WORK; AND
3) PROPER OPERATION AND MAINTENANCE OF NEWLY IMPLEMENTED CONTROL
MEASURES.
H) ASSURANCE OF EFFECTIVE PERFORMANCE OF CONTROL MEASURES.
ALL PROPOSED CONTROL MEASURES SHALL BE EVALUATED BY A TECHNICALLY
QUALIFIED PERSON. PROGRESS REPORT(S) ARE REQUIRED DURING THE
ABATEMENT PERIOD.
STEP 2 - CORRECTION SHALL BE COMPLETED BY IMPLEMENTATION OF FEASIBLE
ENGINEERING AND/OR ADMINISTRATIVE CONTROLS AND THEIR EFFECTIVENESS
AT ACHIEVING COMPLIANCE VERIFIED.
Recent events (3)
  • — A (S) $525.00
  • — I (S) $560.00
  • — Z (S) $800.00

1910.36 B04

Serious Gravity 02 1 instance 15 exposed
Issued
Dec 12, 1990
Abate by
Dec 26, 1990
Penalty
Initial $200 · Current $105 Reduced
Recent events (3)
  • — A (S) $105.00
  • — I (S) $140.00
  • — Z (S) $200.00

1910.132 A

Serious Gravity 06 8 instances 8 exposed
Issued
Dec 12, 1990
Abate by
Dec 26, 1990
Penalty
Initial $600 · Current $385 Reduced
Recent events (3)
  • — A (S) $385.00
  • — I (S) $420.00
  • — Z (S) $600.00

1910.151 C

Serious Gravity 05 4 instances 8 exposed
Issued
Dec 12, 1990
Abate by
Jan 15, 1991
Penalty
Initial $500 · Current $315 Reduced
Recent events (3)
  • — A (S) $315.00
  • — I (S) $350.00
  • — Z (S) $500.00

1910.176 B

Serious Gravity 05 1 instance 3 exposed
Issued
Dec 12, 1990
Abate by
Dec 18, 1990
Penalty
Initial $500 · Current $315 Reduced
Recent events (3)
  • — A (S) $315.00
  • — I (S) $350.00
  • — Z (S) $500.00

1910.212 A03 II

Serious Gravity 09 2 instances 8 exposed
Issued
Dec 12, 1990
Abate by
Feb 15, 1991
Penalty
Initial $900 · Current $595 Reduced
Recent events (3)
  • — A (S) $595.00
  • — I (S) $630.00
  • — Z (S) $900.00

1910.1200 F05 I

Serious Gravity 05 3 instances 20 exposed
Issued
Dec 12, 1990
Abate by
Jan 15, 1991
Penalty
Initial $500 · Current $595
Recent events (3)
  • — A (S) $595.00
  • — I (S) $630.00
  • — Z (S) $500.00

1910.1200 F05 II

Serious Gravity 06 3 instances 20 exposed
Issued
Dec 12, 1990
Abate by
Dec 31, 1990

1910.1200 H01

Serious Gravity 07 180 instances 180 exposed
Issued
Dec 12, 1990
Abate by
Jan 15, 1991
Penalty
Initial $700 · Current $455 Reduced
Recent events (3)
  • — A (S) $455.00
  • — I (S) $490.00
  • — Z (S) $700.00

1904.2 A02

Other-than-serious Gravity 02 1 instance 180 exposed
Issued
Dec 12, 1990
Abate by
Dec 31, 1990
Penalty
Initial $100 · Current $50 Reduced
Recent events (2)
  • — I (O) $50.00
  • — Z (O) $100.00

1910.303 F

Other-than-serious Gravity 04 4 instances 25 exposed
Issued
Dec 12, 1990
Abate by
Dec 31, 1990

1910.1200 E01 I

Other-than-serious Gravity 03 1 instance 180 exposed
Issued
Dec 12, 1990
Abate by
Dec 31, 1990

1910.1200 G01

Other-than-serious Gravity 03 1 instance 56 exposed
Issued
Dec 12, 1990
Abate by
Dec 31, 1990

1910.22 A01

Repeat Gravity 07 1 instance 56 exposed
Issued
Dec 12, 1990
Abate by
Mar 18, 1991
Penalty
Initial $1,400 · Current $700 Reduced
Recent events (2)
  • — I (R) $700.00
  • — Z (R) $1400.00

View Rand-Whitney Robertson Corporation's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 100774546.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.