OSHA Inspection: SOUTHERN OHIO FABRICATORS,INC DBA SOFCO ERECTORS

Accident-driven inspection · Safety discipline

On , OSHA opened an accident-driven safety inspection of SOUTHERN OHIO FABRICATORS,INC DBA SOFCO ERECTORS in 1275 WEST LANE AVENUE, COLUMBUS, OH 43221 (NAICS 000000). OSHA activity number 103042701.

What this inspection record means

OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Southern Ohio Fabricators,Inc DBA Sofco Erectors for free Get an email when a new federal OSHA severe-injury report for Southern Ohio Fabricators,Inc DBA Sofco Erectors is published. One employer, no account, unsubscribe in one click.
Site address
1275 WEST LANE AVENUE
City
COLUMBUS
State
OH
ZIP
43221
Mailing
10333 WAYNE AVENUE, CINCINNATI, OH 45213
Inspection type
Accident-driven (A)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
Union (Y)
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
000000
SIC code (legacy)
1791
Employees
28
Ownership type
Private (A)
Industry flags
Construction safety.

9 citations on file for this inspection.

5(a)(1)

Willful Gravity 10 1 instance 10 exposed
Issued
Oct 31, 1990
Abate by
Nov 30, 1990
Penalty
Initial $10,000 · Current $10,000
SECTION 5(A)(1) OF THE OCCUPATIONAL SAFETY AND HEALTH ACT OF 1970: THE
EMPLOYER DID NOT FURNISH EMPLOYMENT AND A PLACE OF EMPLOYMENT WHICH WERE
FREE FROM RECOGNIZED HAZARDS THAT WERE CAUSING OR LIKELY TO CAUSE DEATH
OR SERIOUS PHYSICAL HARM TO EMPLOYEES IN THAT EMPLOYEES WERE EXPOSED TO:
A) WORKERS WERE EXPOSED TO THE HAZARDS OF FALLS, CRUSHING, AND DEATH
WHEN THE EMPLOYER DID NOT PREPARE AND IMPLEMENT A BUILDING ERECTION
PLAN. PROJECT NO 100-87-016, DRAWING-31 STRUCTURAL NOTES AND DETAILS,
ITEM A.1, READS AS FOLLOWS:
"THE STRUCTURE IS DESIGNED TO BE SELF-SUPPORTING AND STABLE AFTER
THE BUILDING IS FULLY COMPLETE. IT IS SOLELY THE CONTRACTOR'S
RESPONSIBILITY TO DETERMINE THE ERECTION PROCEDURES AND SEQUENCE
TO INSURE THE SAFETY OF THE BUILDING AND ITS COMPONENT PARTS DURING
SHORING, SHEETING, TEMPORARY BRACING, GUYS OR TIEDOWNS WHICH MIGHT
BE NECESSARY. SUCH MATERIAL SHALL REMAIN THE CONTRACTOR'S PROPERTY
AFTER COMPLETION OF THE PROJECT."
ITEM A.2 READS AS FOLLOWS:
"ITEM IS SOLELY THE CONTRACTOR'S RESPONSIBILITY TO FOLLOW ALL
APPLICABLE SAFETY CODES AND REGULATIONS DURING ALL PHASES OF
CONSTRUCTION."
IN ANSI A10.13-1989 AMERICAN NATIONAL STANDARD FOR CONSTRUCTION AND
DEMOLITION OPERATIONS STEEL ERECTION SAFETY REQUIREMENTS, UNDER 4.JOB
PLANNING 4.1 "SURVEY OF WORK TO BE PERFORMED", STATES:
"PRIOR TO THE START OF WORK, THE EMPLOYER SHALL MAKE A SURVEY OF THE
WORK TO BE DONE FROM THE CONSTRUCTION DRAWINGS; BY DISCUSSION WITH
THE OWNER, ARCHITECT, ENGINEER, GENERAL CONTRACTOR, AND CONSTRUCTION
MANAGER; AND BY A PHYSICAL SURVEY OF THE JOB SITE."
THE HAZARDS ASSOCIATED WITH THE ERECTION OF THE BUILDING STRUCTURE CAN
BE ABATED BY THE DEVELOPMENT OF A FORMAL REASONED SEQUENTIAL APPROACH TO
THE ERECTION PROCESS. ANSI A10.13 CONTAINS GUIDANCE CONCERNING SAFE
ERECTION PROCEDURES. THE MINIMUM CONTENT OF THE ERECTION PLAN CAN BE
EXPECTED TO INCLUDE, BUT NOT BE LIMITED TO, THE FOLLOWING:
1) COLLECT NEEDED INFORMATION-
IF NECESSARY, REVIEW THE PLANS AND SPECIFICATIONS WITH THE
ARCHITECT AND DESIGN ENGINEER FIRM. ESTABLISH AN UNDERSTANDING
CONCERNING THE UNIQUE FEATURES OF THE BUILDING, STRESSES, AND WEIGHT
ON THE COMPONENTS.
2) DEVELOPMENT AN ORDERED PLAN FOR THE ERECTION OF THE BUILDING.
3) INSTRUCT AND TRAIN SUPERVISORS, FOREMEN, AND WORKERS IN THE PLAN AND
PROCEDURES THAT WILL BE USED, AND WHAT TO DO IN CASE OF AN EMERGENCY.
4) PERFORM THE TASK(S) WHILE MONITORING FOR HAZARDS THAT MAY DEVELOP.
IT IS POSSIBLE THAT THE PLAN IS FLAWED AND THAT SITUATIONS WILL
DEVELOPMENT THAT WERE NOT ANTICIPATED. THE WORKERS AND MANAGERS NEED
TO BE GIVEN CLEAR INSTRUCTION TO GET KNOWLEDGEABLE ORDER BEFORE
PROCEEDING INTO A PLANNED ERECTION PROCEDURE.

5(a)(1)

Deleted Willful Gravity 10 1 instance 10 exposed
Issued
Oct 31, 1990
Abate by
Nov 30, 1990
Penalty
Initial $10,000 · Current $10,000
SECTION 5(A)(1) OF THE OCCUPATIONAL SAFETY AND HEALTH ACT OF 1970: THE
%%
EMPLOYER DID NOT FURNISH EMPLOYMENT AND A PLACE OF EMPLOYMENT WHICH WERE
FREE FROM RECOGNIZED HAZARDS THAT WERE CAUSING OR LIKELY TO CAUSEDEATH
OR SERIOUS PHYSICAL HARM TO EMPLOYEES IN THAT EMPLOYEES WERE EXPOSED TO:
A) WORKERS WERE EXPOSED TO THE HAZARDS OF BUILDING COLLAPSE. THE
EMPLOYER IS IN VIOLATION OF RECOGNIZED PRINCIPLES AND PRACTICES
OF STEEL ERECTION AND OF THE AMERICAN NATIONAL STANDARD FOR
CONSTRUCTION AND DEMOLITION OPERATIONS-STEEL ERECTION SAFETY
REQUIREMENTS, ANSI A10.13-1989, PARAGRAGH 11.1 (SECOND SENTENCE),
WHICH READS:
"THE SEQUENCE OF ERECTION BOLTING, TEMPORARY GUYING, RIVETING, AND
WELDING SHALL BE SUCH AS TO MAINTAIN THE STABILITY OF THE STRUCTURAL
FORM AT ALL TIMES DURING THE CONSTRUCTION. CONSIDERATION SHALL BE
GIVEN TO THE DEAD WEIGHT OF THE STRUCTURE, WEIGHT, AND WORKING
REACTIONS OF ALL CONSTRUCTION EQUIPMENT PLACED THEREON AND ALL
EXTERNAL FORCES THAT MAY BE APPLIED."
THE HAZARDS OF THE COLLAPSE CAN BE ABATED BY A PROGRAM INCLUDING, BUT
NOT LIMITED TO, THE FOLLOWING FACTORS:
1) PLUMB THE COLUMNS OF THE BUILDING.
2) CONNECT THE BEAMS TO THE COLUMNS.
3) USING DIAGONAL GUYING, WHICH IS ATTACHED BETWEEN THE COLUMN AND A
BEAM TO BE LEVELED, DO THE FOLLOWING:
A) LOOSEN THE CONNECTION BOLTS, IF NEEDED.
B) POSITION THE BEAM SO THAT IT IS ALIGNED WITH THE BOLT
HOLES IN A HORIZONTAL POSITION.
C) PLACE FULL-SIZED BOLTS THROUGH THE FLANGE ATTACHMENT HOLES.
D) TORQUE THE BOLTS TO SPECIFICATIONS.
4) CHECK THAT COLUMN/BEAM MEETS ERECTION SPECIFICATIONS.
5) REMOVE DIAGONAL BRACING.
Recent events (2)
  • · F (W) $10000.00
  • · Z (W) $10000.00

1926.20 B01

Deleted Willful Gravity 10 1 instance 10 exposed
Issued
Oct 31, 1990
Abate by
Nov 30, 1990
Penalty
Initial $10,000 · Current $10,000
Recent events (2)
  • · F (W) $10000.00
  • · Z (W) $10000.00

1926.20 B02

Serious Gravity 10 1 instance 10 exposed
Issued
Oct 31, 1990
Abate by
Nov 30, 1990
Penalty
Current $5,000
Recent events (2)
  • · F (S) $5000.00
  • · Z (W)

1926.21 B02

Deleted Willful Gravity 10 1 instance 10 exposed
Issued
Oct 31, 1990
Abate by
Nov 30, 1990
Recent events (2)
  • · F (W)
  • · Z (W)

1926.28 A

Deleted Willful Gravity 10 1 instance 10 exposed
Issued
Oct 31, 1990
Abate by
Nov 30, 1990
Penalty
Initial $10,000 · Current $10,000
Recent events (2)
  • · F (W) $10000.00
  • · Z (W) $10000.00

1926.750 B01 II

Serious Gravity 10 1 instance 10 exposed
Issued
Oct 31, 1990
Abate by
Nov 30, 1990
Penalty
Initial $10,000 · Current $5,000 Reduced
Recent events (2)
  • · F (S) $5000.00
  • · Z (W) $10000.00

1926.750 B02 I

Serious Gravity 10 1 instance 10 exposed
Issued
Oct 31, 1990
Abate by
Nov 30, 1990
Recent events (2)
  • · F (S)
  • · Z (W)

1926.105 A

Deleted Willful Gravity 10 1 instance 10 exposed
Issued
Oct 31, 1990
Abate by
Nov 30, 1990
Recent events (2)
  • · F (W)
  • · Z (W)

View Southern Ohio Fabricators,Inc DBA Sofco Erectors's full OSHA safety record →