OSHA Inspection: GROW-PERINI

Accident-driven inspection · Safety discipline

On , OSHA opened an accident-driven safety inspection of GROW-PERINI in QUEENSBOROUGH BRIDGE, NEW YORK, NY 10017 (NAICS 000000). OSHA activity number 106871650.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Grow-Perini — free Get an email when a new federal OSHA severe-injury report for Grow-Perini is published. One employer, no account, unsubscribe in one click.
Establishment
GROW-PERINI
Site address
QUEENSBOROUGH BRIDGE
City
NEW YORK
State
NY
ZIP
10017
Mailing
41-10A 22ND ST., LONG ISLAND CITY, NY 11101
Inspection type
Accident-driven (A)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
Y
Opened
Closing conference
Case closed
Data loaded
NAICS code
000000
SIC code (legacy)
1622
Employees
70
Ownership type
A

4 citations on file for this inspection.

5(a)(1)

Deleted Serious Gravity 10 2 instances 25 exposed
Issued
Mar 25, 1998
Abate by
Apr 3, 1998
Penalty
Initial $5,000 · Current $5,000
Section 5(a)(1) of the Occupational Safety and Health Act of 1970:
The employer did not furnish employment and a place of employment
which were free from recognized hazards that were causing or likely
to cause death or serious physical harm to employees in that
employees were exposed to falls of up to 135 feet to the water
below caused by a structural collapse.
a)Job Site: Queensboro Bridge, New York, NY: The employer
failed to ensure that a work platform being installed to
the underside of the bridge was lifted without first
removing the  wood planking (weight: approximately 1,175
pounds).  Design drawing notes specify the removal of
the planking before lifting; The lift was made on
September 29, 1997.
b)Job Site: The employer failed to ensure that prior to
installing platforms to the underside of the bridge that
radio communicated signals were understood by all
participants.  The lift was performed on September 29,
1997.
ABATEMENT:
a)Among other methods, one feasible and acceptable method
to correct this hazard would be to review the platform
lifting procedures before every lift. This would ensure
compliance with the platform design installation
instructions; as per engineering drawings and plans.
b)Among other methods, one feasible and acceptable
abatement method to correct this hazard is to conduct a
pre-lift meeting before each lift.
ABATEMENT VERIFICATION IS REQUIRED THIS ITEM.
FAILURE TO COMPLY WILL RESULT IN AN ADDITIONAL PENALTY OF $1000.00,
AS PER 29 CFR 1903.19.,
Recent events (2)
  • — F (S) $5000.00
  • — Z (S) $5000.00

5(a)(1)

Deleted Serious Gravity 10 1 instance 6 exposed
Issued
Mar 25, 1998
Abate by
Apr 3, 1998
Penalty
Initial $5,000 · Current $5,000
Section 5(a)(1) of the Occupational Safety and Health Act of 1970:
The employer did not furnish employment and a place of employment
which were free from recognized hazards that were causing or likely
to cause death or serious physical harm to employees in that
employees were exposed to being struck by or struck against objects
under excessive wind conditions.
a)Job Site - Queensboro Bridge, New York, NY: The employer
failed  to heed platform design specification notes
prohibiting the lifting of platforms by crane(s) for
installation to the underside of the bridge in excessive
wind conditions.  The platform was lifted in winds that
peaked at 32 knots, or 36.864 miles per hour, The
engineering design drawing notes cautioned against
lifting the platforms in winds in excess of 20 miles per
hour.The lift occurred on  September 29, 1997.
ABATEMENT:
Among other methods, one feasible and acceptable abatement method
to correct this hazard would be to adhere to design specifications.
ABATEMENT VERIFICATION IS REQUIRED THIS ITEM.  FAILURE TO COMPLY
WILL RESULT IN AN ADDITIONAL PENALTY OF $1000.00, AS PER 29 CFR
1903.19.,
Recent events (2)
  • — F (S) $5000.00
  • — Z (S) $5000.00

1926.502 D10 I

Serious Gravity 10 1 instance 6 exposed
Issued
Mar 25, 1998
Abate by
Mar 30, 1998
Penalty
Initial $5,000 · Current $5,000
Recent events (2)
  • — F (S) $5000.00
  • — Z (S) $5000.00

1926.502 D23

Deleted Serious Gravity 10 1 instance 6 exposed
Issued
Mar 25, 1998
Abate by
Apr 3, 1998
Penalty
Initial $5,000 · Current $5,000
Recent events (2)
  • — F (S) $5000.00
  • — Z (S) $5000.00

View Grow-Perini's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 106871650.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.