WINTHROP, MA —
OSHA Inspection: CASHMAN/INTERBETON, A JOINT VENTURE
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of CASHMAN/INTERBETON, A JOINT VENTURE in BOSTON OUTER HARBOR CP-283, WINTHROP, MA 02152 (NAICS 000000). OSHA activity number 107532731.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- CASHMAN/INTERBETON, A JOINT VENTURE
- Site address
- BOSTON OUTER HARBOR CP-283
- City
- WINTHROP
- State
- MA
- ZIP
- 02152
- Mailing
- 2 HANCOCK STREET, QUINCY, MA 02169
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Complete (A)
- Discipline
- Safety
- Advance notice
- No
- Union status
- Y
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Data loaded
Establishment context
- NAICS code
- 000000
- SIC code (legacy)
- 1629
- Employees
- 60
- Ownership type
- A
- Industry flags
- Construction safety.
Citations
37 citations on file for this inspection.
5(a)(1)
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $3,500 · Current $3,500
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees, in that, employees were exposed to serious injury from falls into the ocean or to the deck of the transport vessel from the IB 909 emergency chain ladder which did not meet minimum construction quality: (a) Location; IB 909, STBD Side: The emergency ladder rungs were not protected from corrosion, they were not secured in place, and had sharp edges. The rungs were not of consistant rise. The rungs were made of old re bar of unknown quality and strength exposing employees to possible rung failure. Among other methods, one feasible and acceptable abatement method to correct this hazard is to follow 46 CFR 160-017; chain ladder.
Recent events (2)
- — I (S) $3500.00
- — Z (S) $3500.00
1926.21 B02
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $825 · Current $300 Reduced
Recent events (2)
- — I (O) $300.00
- — Z (S) $825.00
1926.28 A
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $3,500 · Current $3,500
1926.50 E
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $3,500 · Current $3,500
Recent events (2)
- — I (S) $3500.00
- — Z (S) $3500.00
1926.105 A
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $3,500 · Current $3,500
1926.106 C
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $825 · Current $600 Reduced
Recent events (2)
- — I (S) $600.00
- — Z (S) $825.00
1926.150 C01 IX
- Issued
- Oct 11, 1991
- Abate by
- Oct 14, 1991
- Penalty
- Initial $1,100 · Current $400 Reduced
Recent events (2)
- — I (O) $400.00
- — Z (S) $1100.00
1926.300 B02
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $825 · Current $825
1926.302 B01
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $825 · Current $825
1926.303 B
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $825 · Current $825
1926.350 A08
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $825 · Current $400 Reduced
Recent events (2)
- — I (S) $400.00
- — Z (S) $825.00
1926.350 J
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $1,375 · Current $400 Reduced
Recent events (2)
- — I (S) $400.00
- — Z (S) $1375.00
1926.403 I02 I
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $1,925 · Current $1,925
1926.405 A02 IIJ
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $1,100 · Current $650 Reduced
Recent events (2)
- — I (S) $650.00
- — Z (S) $1100.00
1926.405 B01
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $825 · Current $400 Reduced
Recent events (2)
- — I (S) $400.00
- — Z (S) $825.00
1926.500 B01
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $1,925 · Current $1,925
1926.500 B03
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $1,375 · Current $1,375
1926.500 F01
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $3,500 · Current $2,500 Reduced
Recent events (2)
- — I (S) $2500.00
- — Z (S) $3500.00
1926.550 A01
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $825 · Current $825
Recent events (2)
- — I (S) $825.00
- — Z (S) $825.00
1926.550 A05
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $1,100 · Current $900 Reduced
Recent events (2)
- — I (S) $900.00
- — Z (S) $1100.00
1926.550 A08
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $1,375 · Current $475 Reduced
Recent events (2)
- — I (S) $475.00
- — Z (S) $1375.00
1926.550 A09
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $1,375 · Current $1,075 Reduced
Recent events (2)
- — I (S) $1075.00
- — Z (S) $1375.00
1926.550 B02
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $1,100 · Current $900 Reduced
Recent events (2)
- — I (S) $900.00
- — Z (S) $1100.00
1926.550 G04 IA
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $825 · Current $825
Recent events (2)
- — I (S) $825.00
- — Z (S) $825.00
1926.550 G04 IIA
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $1,375
Recent events (2)
- — I (O)
- — Z (S) $1375.00
1926.500 G04 IIB
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $825 · Current $825
1926.550 G04 III
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $825
Recent events (2)
- — I (O)
- — Z (S) $825.00
1926.550 G05 I
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $825 · Current $825
1926.550 G05 VI
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $825 · Current $825
1926.550 G06 VII
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $1,375 · Current $1,075 Reduced
Recent events (2)
- — I (S) $1075.00
- — Z (S) $1375.00
1926.550 G08 I
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $825 · Current $825
1926.553 A01
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $1,375 · Current $775 Reduced
Recent events (2)
- — I (S) $775.00
- — Z (S) $1375.00
1926.1051 A
- Issued
- Oct 11, 1991
- Abate by
- Nov 25, 1991
- Penalty
- Initial $1,925 · Current $1,925
Recent events (2)
- — I (S) $1925.00
- — Z (S) $1925.00
1926.1053 B01
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $1,925 · Current $1,525 Reduced
Recent events (2)
- — I (S) $1525.00
- — Z (S) $1925.00
1926.1053 B16
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $1,925 · Current $1,525 Reduced
Recent events (2)
- — I (S) $1525.00
- — Z (S) $1925.00
1926.550 G03 IIC
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
- Penalty
- Initial $12,250 · Current $7,000 Reduced
Recent events (2)
- — I (S) $7000.00
- — Z (W) $12250.00
1926.550 A05
- Issued
- Oct 11, 1991
- Abate by
- Oct 16, 1991
More inspections at Cashman/Interbeton, a Joint Venture
View Cashman/Interbeton, a Joint Venture's full OSHA safety record →
More inspections in this industry (NAICS 000000)
More inspections in MA
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 107532731.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.