HYANNIS, MA ·
OSHA Inspection: ABBEY ROAD CONSTRUCTION CORPORATION
Complaint inspection · Safety discipline
At a glance
On , OSHA opened a complaint safety inspection of ABBEY ROAD CONSTRUCTION CORPORATION in 787 IYANOUGH ROAD, HYANNIS, MA 02601 (NAICS 000000). OSHA activity number 109171181.
OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- ABBEY ROAD CONSTRUCTION CORPORATION
- Site address
- 787 IYANOUGH ROAD
- City
- HYANNIS
- State
- MA
- ZIP
- 02601
- Mailing
- 297 NORTH STREET, HYANNIS, MA 02601
What kind of inspection was it?
- Inspection type
- Complaint (B)
- Scope
- Complete (A)
- Discipline
- Safety
- Advance notice
- No
- Union status
- Non-union (N)
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Data loaded
Establishment context
- NAICS code
- 000000
- SIC code (legacy)
- 1542
- Employees
- 50
- Ownership type
- Private (A)
Citations
12 citations on file for this inspection.
1926.25 A
- Issued
- Jun 6, 1995
- Abate by
- Jun 12, 1995
- Penalty
- Initial $900 · Current $500 Reduced
Recent events (2)
- · I (S) $500.00
- · Z (S) $900.00
1926.150 C01 I
- Issued
- Jun 6, 1995
- Abate by
- Jun 12, 1995
- Penalty
- Initial $900 · Current $500 Reduced
Recent events (2)
- · I (S) $500.00
- · Z (S) $900.00
1926.153 J
- Issued
- Jun 6, 1995
- Abate by
- Jun 9, 1995
- Penalty
- Initial $900 · Current $500 Reduced
Recent events (2)
- · I (S) $500.00
- · Z (S) $900.00
1926.304 F
- Issued
- Jun 6, 1995
- Abate by
- Jun 12, 1995
- Penalty
- Initial $900 · Current $800 Reduced
Recent events (2)
- · I (S) $800.00
- · Z (S) $900.00
1926.404 B01 I
- Issued
- Jun 6, 1995
- Abate by
- Jun 12, 1995
- Penalty
- Initial $900 · Current $500 Reduced
Recent events (2)
- · I (S) $500.00
- · Z (S) $900.00
1926.405 A02 IIJ
- Issued
- Jun 6, 1995
- Abate by
- Jun 12, 1995
- Penalty
- Initial $900 · Current $500 Reduced
Recent events (2)
- · I (S) $500.00
- · Z (S) $900.00
1926.403 I02 I
- Issued
- Jun 6, 1995
- Abate by
- Jun 12, 1995
- Penalty
- Initial $1,200 · Current $250 Reduced
Recent events (2)
- · I (R) $250.00
- · Z (R) $1200.00
1926.152 A01
- Issued
- Jun 6, 1995
- Abate by
- Jun 12, 1995
Recent events (2)
- · I (O)
- · Z (O)
1926.405 G01 III
- Issued
- Jun 6, 1995
- Abate by
- Jun 12, 1995
1926.416 E01
- Issued
- Jun 6, 1995
- Abate by
- Jun 9, 1995
1926.405 G02 IV
- Issued
- Jun 6, 1995
- Abate by
- Jun 12, 1995
1926.1053 B16
- Issued
- Jun 6, 1995
- Abate by
- Jun 9, 1995
More inspections at Abbey Road Construction Corporation
View Abbey Road Construction Corporation's full OSHA safety record →
More inspections in this industry (NAICS 000000)
More inspections in MA
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). OSHA publishes its own view of this case as inspection number 109171181.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.