On , OSHA opened a planned safety inspection of FORTNEY & WEYGANDT in 725 COLUMBUS AVE., FOSTORIA, OH 44830 (NAICS 000000). OSHA activity number 122087190.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- FORTNEY & WEYGANDT
- Site address
- 725 COLUMBUS AVE.
- City
- FOSTORIA
- State
- OH
- ZIP
- 44830
- Mailing
- 31269 BRADLEY ROAD, OLMSTED, OH 44070
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- N
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Data loaded
Establishment context
- NAICS code
- 000000
- SIC code (legacy)
- 1542
- Employees
- 200
- Ownership type
- A
- Industry flags
- Construction safety.
Citations
1 citation on file for this inspection.
5(a)(1)
- Issued
- Jul 28, 1998
- Abate by
- Aug 1, 1998
- Penalty
- Initial $4,000 · Current $2,000 Reduced
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to: Fortney & Weygandt, Inc. did not ensure the sub-contractor was following the HIB-91 Summary Sheet which includes commentary and recommendations for handling, installing and bracing metal plate connected wood trusses provided by the Truss Plate Institute. Fortney & Weygandt did not ensure the sub-contractor was following the steel manufacturers recommendations for Ultra-Span bracing. Fortney & Weygandt did not thoroughly inspect the trusses and temporary bracing after a large storm passed over this job site the night before this collapse occurred. One feasible abatement method would be to ensure sub-contractors follow the HIB-91 Summary Sheet which includes recommendations for bracing trusses and to inspect the temporary bracing before employees are allowed to install parts of the roof or to work on the trusses. Trusses should also be thoroughly inspected after high wind storms have passed over the project. Additional abatement information is required for this item.
Recent events (2)
- — I (S) $2000.00
- — Z (S) $4000.00
More inspections at Fortney & Weygandt
View Fortney & Weygandt's full OSHA safety record →
More inspections in this industry (NAICS 000000)
More inspections in OH
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 122087190.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.