Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: CENTRAL TOWER A DIELECTRIC COMPANY

Follow-up inspection · Safety discipline

On , OSHA opened a follow-up safety inspection of CENTRAL TOWER A DIELECTRIC COMPANY in WSTM TRANSMISSION FACILITY, SENTINEL HEIGHTS ROAD, ONONDAGA, NY 13215 (NAICS 237990). OSHA activity number 306309261.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Central Tower a Dielectric Company — free Get an email when a new federal OSHA severe-injury report for Central Tower a Dielectric Company is published. One employer, no account, unsubscribe in one click.
Site address
WSTM TRANSMISSION FACILITY, SENTINEL HEIGHTS ROAD
City
ONONDAGA
State
NY
ZIP
13215
Mailing
3266 TOWER DRIVE, NEWBURGH, IN 47630
Inspection type
Follow-up (F)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
N
Opened
Closing conference
Case closed
Data loaded
NAICS code
237990
SIC code (legacy)
1799
Employees
6
Ownership type
A

3 citations on file for this inspection.

1926.550 G04 III

Serious Gravity 03 1 instance 4 exposed
Issued
Aug 12, 2003
Abate by
Aug 15, 2003
Penalty
Initial $1,500 · Current $1,050 Reduced
Recent events (2)
  • — I (S) $1050.00
  • — Z (S) $1500.00

1926.550 G04 IIA

Serious Gravity 03 1 instance 4 exposed
Issued
Aug 12, 2003
Abate by
Aug 15, 2003
Recent events (2)
  • — I (S)
  • — Z (S)

5(a)(1)

Repeat Gravity 10 1 instance 4 exposed
Issued
Aug 12, 2003
Abate by
Aug 15, 2003
Penalty
Initial $6,000 · Current $4,200 Reduced
Section 5(a)(1) of the Occupational Safety and Health Act of 1970:  The
employer did not
furnish employment and a place of employment which were free from
recognized hazards that
were causing or likely to cause death or serious physical harm to
employees in that employees
were exposed to the hazard of falling:
a)Tower Site, On or about 6/6/03:  Employees were accessing the working
level
of a new Television Antenna by riding the ball of the load line to a
height of
approximately 860 feet above the ground, exposing employees to a fall
hazard.
Among other methods, feasible and acceptable abatement methods to correct
these
hazards are to:
1)Follow all of the requirements of CPL 2-1.36, Interim Inspection
Procedures During Communication Tower Construction.  Which
amongst other items, would require that the employer provide:
a) Proper training in regards to hoisting employees.
c) The personnel load capacity and material capacity of the
lifting system in use and ensure that it is posted near the lift
operator.
d) A trial lift of the maximum intended personnel load from the
ground to the location to which personnel are to be hoisted.
e) A visual inspection of the hoist, rigging, base support and
foundation by a competent person immediately after the trial
lift.
f) A proof test of the hoist in which 125 percent of the load is
suspended for 5 minutes.
g) Documentation of all trial lifts.
h) As-built drawings approved by a registered professional
engineer, available on the site.
i) The rated load capacities, recommended operating speeds,
and special hazard warnings or instructions for the hoist and
conspicuously post them on the hoist.
j) Personnel load capacity for the current configuration of the
gin pole that are posted within site of the operator.
k) An accessible fire extinguisher of 5B:C minimum rating for
the operators station.
l) An operators manual for the hoist in use, maintained on the
site.
m) A hoist log book that shall record all hoist inspections, tests,
maintenance, and repair.  The hoist log shall be updated daily
when the hoist is being used or serviced and shall be
maintained on site at all times.n) That the personnel hoist be anchored to
prevent movement.
o) An anti two block device on the hoist and gin pole.
p) That no more than two employees ride the hoist ball at one
time.
Central Tower A Dielectric Company was previously cited for a violation of
this Occupational Safety and Health Standard or its equivalent standard,
Section 5(1)(1) pertaining to communication tower work, which was contained
in OSHA Inspection number 304592520, Citation 1, Item 1, issued on
01/24/03, with respect to a workplace located at the WSTM Transmission
Facility, Sentinel Heights Road, Onondaga, New York.
Recent events (2)
  • — I (R) $4200.00
  • — Z (R) $6000.00

View Central Tower a Dielectric Company's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 306309261.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.