OSHA Inspection: FAYO CONSTRUCTION, INC.

Accident-driven inspection · Safety discipline

On , OSHA opened an accident-driven safety inspection of FAYO CONSTRUCTION, INC. in 22 SCHIAVONE RD., NEW WINDSOR, NY 12553 (NAICS 238990). OSHA activity number 307541102.

What this inspection record means

OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Fayo Construction, INC. for free Get an email when a new federal OSHA severe-injury report for Fayo Construction, INC. is published. One employer, no account, unsubscribe in one click.
Site address
22 SCHIAVONE RD.
City
NEW WINDSOR
State
NY
ZIP
12553
Mailing
9 VIRGINIA AVE., CORNWALL, NY 12518
Inspection type
Accident-driven (A)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
Non-union (N)
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238990
SIC code (legacy)
1771
Employees
4
Ownership type
Private (A)

2 citations on file for this inspection.

5(a)(1)

Serious Gravity 03 1 instance 2 exposed
Issued
Dec 2, 2005
Abate by
Dec 7, 2005
Penalty
Initial $750 · Current $750
Section 5(a)(1) of the Occupational Safety and Health Act of 1970:  The
employer did not
furnish employment and a place of employment which were free from
recognized hazards that
were causing or likely to cause death or serious physical harm to
employees in that:
a)22 Schiavone Rd, New Windsor, NY - on or about June 7, 2005 - employees
were exposed to a struck by hazard while engaged in the placement of
concrete for a
basement slab through a concrete pump.  Employees were working adjacent to
the end
of the concrete pump hose while the pump was started and restarted.  This
is a violation
of the Concrete Pump Manufacturers Association procedures for safe
operation, Safety
Standard for Concrete Pumps, Placing Booms and Delivery Systems, Section
27-
1.18.2.2.
Methods to correct this hazard include, but are not limited to:  1)
Develop and implement

1926.100 A

Serious Gravity 03 1 instance 2 exposed
Issued
Dec 2, 2005
Abate by
Dec 7, 2005
Penalty
Initial $750 · Current $750

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). OSHA publishes its own view of this case as inspection number 307541102.