OSHA Inspection: PAUL MORRIS CONSTRUCTION.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of PAUL MORRIS CONSTRUCTION. in 144 PARK SIDE DRIVE., BELGRADE, MT 59714 (NAICS 236115). OSHA activity number 308303361.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Paul Morris Construction. — free Get an email when a new federal OSHA severe-injury report for Paul Morris Construction. is published. One employer, no account, unsubscribe in one click.
Site address
144 PARK SIDE DRIVE.
City
BELGRADE
State
MT
ZIP
59714
Mailing
P.O BOX 16001, BIG SKY, MT 59716
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
N
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
236115
SIC code (legacy)
1521
Employees
2
Ownership type
A

3 citations on file for this inspection.

5(a)(1)

Serious Gravity 02 1 instance 1 exposed
Issued
Feb 15, 2006
Abate by
Feb 19, 2006
Penalty
Initial $600 · Current $300 Reduced
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The
employer did not
furnish employment and a place of employment which is free from recognized
hazards that
were causing or likely to cause death or serious physical harm to
employees in that
employees were exposed to:
(a) Residential construction site: The hazard of being exposed to a fall
of approximately 10
feet to the ground below while working from a plywood platform raised by a
Sky Trak, all
terrain forklift at the construction site located at 144 Park Side Drive.
Among other methods. One feasible and acceptable abatement method of
correct this hazard
while using an all terrain forklift for lifting personnel is to follow the
requirements set forth
in the ASME B56.6-2002.
Recent events (2)
  • — I (S) $300.00
  • — Z (S) $600.00

1926.501 B13

Serious Gravity 10 2 instances 4 exposed
Issued
Feb 15, 2006
Abate by
Feb 19, 2006
Penalty
Initial $1,500 · Current $750 Reduced
Recent events (2)
  • — I (S) $750.00
  • — Z (S) $1500.00

1926.1053 B13

Serious Gravity 04 1 instance 1 exposed
Issued
Feb 15, 2006
Abate by
Feb 19, 2006
Penalty
Initial $750 · Current $375 Reduced
Recent events (2)
  • — I (S) $375.00
  • — Z (S) $750.00

View Paul Morris Construction.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 308303361.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.