OSHA Inspection: MITCHELL WELDING, INC.

Planned inspection · Health discipline

On , OSHA opened a planned health inspection of MITCHELL WELDING, INC. in 7080 HWY 19E, SPRUCE PINE, NC 28777 (NAICS 332312). OSHA activity number 310295696.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Mitchell Welding, INC. — free Get an email when a new federal OSHA severe-injury report for Mitchell Welding, INC. is published. One employer, no account, unsubscribe in one click.
Site address
7080 HWY 19E
City
SPRUCE PINE
State
NC
ZIP
28777
Mailing
PO BOX 838, SPRUCE PINE, NC 28777
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Health
Advance notice
No
Union status
N
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
332312
SIC code (legacy)
3441
Employees
20
Ownership type
A
Industry flags
Manufacturing health.

15 citations on file for this inspection.

95012901

Serious 3 instances 4 exposed
Issued
Aug 21, 2006
Abate by
Oct 6, 2006
Penalty
Initial $250 · Current $250
North Carolina General Statute 95-129(1) of the Occupational Safety and
Health Act of North Carolina:  The
employer did not furnish to each of his employees conditions of employment
and a place of employment which
were free from recognized hazards that were causing or likely to cause
death or serious physical harm to
employees in that employees were exposed to fall or struck by hazards:
(a)  Facility, lower shop - two 5 ton underhung Jib Cranes were not load
tested as required.
(b)  Facility, maintenance shop - Monorail crane system was not load
tested as required.
REF:  ANSI B30.16-2, Section 16-2.2, Paragraph 16-2.2.2
(b)  Electric Powered or Air Powered Hoists
(1)  Complete new hoists shall be dynamically load tested by the
manufacturer as specified
in paragraphs 16-2.2.1(b)(1) and (2) with a load test not less than 125
of the rated
load, except that if testing cannot be performed by the manufacturer, the
user shall be
notified and the load test shall be accomplished at another location or
job site, by or
under the direction of a designated person prior to the hoist being placed
into service.
(The user is testing the complete structure wether or not the hoist was
tested by the
manufacturer.)
(c)  The person conducting the load test shall prepare a written report of
the load sustained during the
test and the operations performed during the test.  Reports must be placed
on file.
NOTE:  Among other methods, one feasible and acceptable method to correct
this hazard is to load test the
underhung hoists as required and maintain records of the load tests.

1910.179 K01 I

Serious 1 instance 1 exposed
Issued
Aug 21, 2006
Abate by
Oct 6, 2006

95012901

Serious 3 instances 4 exposed
Issued
Aug 21, 2006
Abate by
Oct 6, 2006
Penalty
Initial $250 · Current $250
North Carolina General Statute 95-129(1) of the Occupational Safety and
Health Act of North Carolina:  The
employer did not furnish to each of his employees conditions of employment
and a place of employment which
were free from recognized hazards that were causing or likely to cause
death or serious physical harm to
employees:
(a)  Facility, lower shop - two 5 ton underhung Jib Cranes were inspected
annually.
(b)  Facility, maintenance shop - Monorail crane system was not inspected
annually.
REF:  ANSI B30.11-1998, Chapter 11-2, Paragraph 11-2.1.3
(a)Periodic inspections shall be performed at intervals defined in para.
11-2.1.1(b)(2):  Visual
inspection by an appointed person making records of apparent external
conditions to provide the
basis for a continuing evaluation, as follows:  normal service, equipment
in place ---  annually.
(c) A qualified person shall examine any deficiencies found during the
inspection to determine
whether conditions found constitute a hazard, require disassembly for
further inspection, or
require replacement.
NOTE:  Among other methods, one feasible acceptable abatement method to
correct this hazard is to conduct
annual, periodic inspections on the crane systems per the requirements of
section
11-2.1.3 of ANSI B30-11-1998.

1910.179 J03

Serious 1 instance 1 exposed
Issued
Aug 21, 2006
Abate by
Oct 6, 2006

95012901

Serious 1 instance 1 exposed
Issued
Aug 21, 2006
Abate by
Oct 6, 2006
Penalty
Initial $125 · Current $125
North Carolina General Statute 95-129(1) of the Occupational Safety and
Health Act of North Carolina:  The
employer did not furnish to each of his employees conditions of employment
and a place of employment which
were free from recognized hazards that were causing or likely to cause
death or serious physical harm to
employees:
(a)  Facility, lower shop- The rated load was not marked on the under the
hook lifting device which was
attached to one 5 ton hoist on the overhead bridge crane.
REF:  ANSI B30.20-1985, Chapter 20-1, Section 20-1.2 Markings, Paragraph
20-1.1.2
(a)Rated load marking.  The rated load of the lifting device shall be
marked on the structure
where it is visible.
(b)Identification.  A nameplate or other permanent marking shall be
affixed
displaying the
following information:
(1)Manufacture's name
(2)Serial number
(3)Lifter weight, if over 100 lbs.
(4)Rated load
NOTE:  Among other methods, one feasible and acceptable method to correct
this hazard is to properly mark
the rated load on the below the hook lifting device.

1910.95 B01

Serious 1 instance 1 exposed
Issued
Aug 21, 2006
Abate by
Oct 6, 2006
Penalty
Initial $350 · Current $350

1910.95 C01

Serious 1 instance 1 exposed
Issued
Aug 21, 2006
Abate by
Oct 6, 2006

1910.215 B09

Serious 1 instance 1 exposed
Issued
Aug 21, 2006
Abate by
Aug 31, 2006
Penalty
Initial $125 · Current $125

1910.212 B

Serious 1 instance 1 exposed
Issued
Aug 21, 2006
Abate by
Aug 31, 2006

1910.134 C01

Other-than-serious 1 instance 1 exposed
Issued
Aug 21, 2006
Abate by
Oct 6, 2006

1910.134 C02 I

Other-than-serious 1 instance 1 exposed
Issued
Aug 21, 2006
Abate by
Oct 6, 2006

1910.134 E01

Other-than-serious 1 instance 1 exposed
Issued
Aug 21, 2006
Abate by
Oct 6, 2006

1910.134 H03 IA

Other-than-serious 1 instance 1 exposed
Issued
Aug 21, 2006
Abate by
Oct 6, 2006

1910.134 K03

Other-than-serious 1 instance 1 exposed
Issued
Aug 21, 2006
Abate by
Oct 6, 2006

1910.305 B01

Other-than-serious 1 instance 4 exposed
Issued
Aug 21, 2006
Abate by
Aug 31, 2006

View Mitchell Welding, INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 310295696.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.