CLEARWATER, FL ·
OSHA Inspection: ENDEAVOUR CATAMARAN CORPORATION
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of ENDEAVOUR CATAMARAN CORPORATION in 3703 131ST AVE., N., CLEARWATER, FL 33762 (NAICS 336612). OSHA activity number 311177026.
OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- ENDEAVOUR CATAMARAN CORPORATION
- Site address
- 3703 131ST AVE., N.
- City
- CLEARWATER
- State
- FL
- ZIP
- 33762
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Complete (A)
- Discipline
- Safety
- Advance notice
- No
- Union status
- N
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 336612
- SIC code (legacy)
- 3732
- Employees
- 32
- Ownership type
- A
- Industry flags
- Manufacturing safety.
Citations
30 citations on file for this inspection.
5(a)(1)
- Issued
- Nov 20, 2007
- Abate by
- Jan 25, 2008
- Penalty
- Initial $2,500 · Current $2,463 Reduced
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to the hazard of being struck by fragments of plastic pipe used to transport compressed air for the operation of air operated tools and air used for cleaning, in the event the piping ruptures: a. Throughout both warehouses, polyvinyl chloride ( PVC ) plastic pipe was used to transport compressed air in exposed above ground locations, for the operation of air operated tools and air used for cleaning, a practice not recommended by the Plastics Pipe Institute and prohibited by ANSI/ASME B31.8-1986, Gas Transmission and Distribution Piping Systems standard. Among other methods one feasible and acceptable method to correct this hazard is to replace the PVC piping with a type that is approved for transporting compressed gases in exposed above ground locations, such as iron or steel piping.
Recent events (2)
- · I (S) $2462.50
- · Z (S) $2500.00
1910.23 A08
- Issued
- Nov 20, 2007
- Abate by
- Dec 23, 2007
- Penalty
- Initial $750 · Current $713 Reduced
Recent events (2)
- · I (S) $712.50
- · Z (S) $750.00
1910.23 C01
- Issued
- Nov 20, 2007
- Abate by
- Dec 23, 2007
- Penalty
- Initial $1,750 · Current $1,713 Reduced
Recent events (2)
- · I (S) $1712.50
- · Z (S) $1750.00
1910.24 H
- Issued
- Nov 20, 2007
- Abate by
- Dec 23, 2007
- Penalty
- Initial $750
Recent events (2)
- · I (O)
- · Z (S) $750.00
1910.36 B04
- Issued
- Nov 20, 2007
- Abate by
- Dec 23, 2007
- Penalty
- Initial $2,500
Recent events (2)
- · I (O)
- · Z (S) $2500.00
1910.101 B
- Issued
- Nov 20, 2007
- Abate by
- Dec 8, 2007
- Penalty
- Initial $1,250 · Current $1,250
Recent events (2)
- · I (S) $1250.00
- · Z (S) $1250.00
1910.106 E02 IVD
- Issued
- Nov 20, 2007
- Abate by
- Dec 23, 2007
- Penalty
- Initial $1,000 · Current $963 Reduced
2280
Recent events (2)
- · I (S) $962.50
- · Z (S) $1000.00
1910.106 E09 III
- Issued
- Nov 20, 2007
- Abate by
- Dec 8, 2007
- Penalty
- Initial $1,750 · Current $1,713 Reduced
Recent events (2)
- · I (S) $1712.50
- · Z (S) $1750.00
1910.107 C05
- Issued
- Nov 20, 2007
- Abate by
- Jan 25, 2008
- Penalty
- Initial $2,500 · Current $2,463 Reduced
Recent events (2)
- · I (S) $2462.50
- · Z (S) $2500.00
1910.107 C09 I
- Issued
- Nov 20, 2007
- Abate by
- Jan 25, 2008
- Penalty
- Initial $1,750 · Current $1,713 Reduced
E101
Recent events (2)
- · I (S) $1712.50
- · Z (S) $1750.00
1910.133 A01
- Issued
- Nov 20, 2007
- Abate by
- Jan 25, 2008
- Penalty
- Initial $750 · Current $713 Reduced
Recent events (2)
- · I (S) $712.50
- · Z (S) $750.00
1910.157 G02
- Issued
- Nov 20, 2007
- Abate by
- Jan 25, 2008
- Penalty
- Initial $750 · Current $713 Reduced
88802280
Recent events (2)
- · I (S) $712.50
- · Z (S) $750.00
1910.178 C02 III
- Issued
- Nov 20, 2007
- Abate by
- Dec 8, 2007
- Penalty
- Initial $2,500 · Current $2,463 Reduced
Recent events (2)
- · I (S) $2462.50
- · Z (S) $2500.00
1910.178 L01 I
- Issued
- Nov 20, 2007
- Abate by
- Dec 23, 2007
- Penalty
- Initial $750 · Current $713 Reduced
Recent events (2)
- · I (S) $712.50
- · Z (S) $750.00
1910.178 P01
- Issued
- Nov 20, 2007
- Abate by
- Dec 23, 2007
- Penalty
- Initial $1,750 · Current $1,713 Reduced
Recent events (2)
- · I (S) $1712.50
- · Z (S) $1750.00
1910.178 Q07
- Issued
- Nov 20, 2007
- Abate by
- Dec 23, 2007
Recent events (2)
- · I (S)
- · Z (S)
1910.212 A05
- Issued
- Nov 20, 2007
- Abate by
- Dec 23, 2007
- Penalty
- Initial $1,250 · Current $1,213 Reduced
Recent events (2)
- · I (S) $1212.50
- · Z (S) $1250.00
1910.213 A12
- Issued
- Nov 20, 2007
- Abate by
- Jan 25, 2008
- Penalty
- Initial $1,750 · Current $1,713 Reduced
Recent events (2)
- · I (S) $1712.50
- · Z (S) $1750.00
1910.213 L03
- Issued
- Nov 20, 2007
- Abate by
- Jan 25, 2008
- Penalty
- Initial $1,000 · Current $963 Reduced
Recent events (2)
- · I (S) $962.50
- · Z (S) $1000.00
1910.213 P04
- Issued
- Nov 20, 2007
- Abate by
- Dec 8, 2007
- Penalty
- Initial $750
Recent events (2)
- · I (O)
- · Z (S) $750.00
1910.215 A01
- Issued
- Nov 20, 2007
- Abate by
- Dec 8, 2007
- Penalty
- Initial $1,250 · Current $1,213 Reduced
Recent events (2)
- · I (S) $1212.50
- · Z (S) $1250.00
1910.215 B09
- Issued
- Nov 20, 2007
- Abate by
- Dec 8, 2007
Recent events (2)
- · I (S)
- · Z (S)
1910.253 B04 III
- Issued
- Nov 20, 2007
- Abate by
- Dec 8, 2007
- Penalty
- Initial $750 · Current $750
Recent events (2)
- · I (S) $750.00
- · Z (S) $750.00
1910.303 B01
- Issued
- Nov 20, 2007
- Abate by
- Dec 8, 2007
- Penalty
- Initial $1,250 · Current $1,213 Reduced
Recent events (2)
- · I (S) $1212.50
- · Z (S) $1250.00
1910.303 B02
- Issued
- Nov 20, 2007
- Abate by
- Dec 23, 2007
Recent events (2)
- · I (S)
- · Z (S)
1910.303 B07 I
- Issued
- Nov 20, 2007
- Abate by
- Dec 23, 2007
Recent events (2)
- · I (S)
- · Z (S)
1910.305 G02 II
- Issued
- Nov 20, 2007
- Abate by
- Dec 8, 2007
- Penalty
- Initial $2,500 · Current $2,463 Reduced
Recent events (2)
- · I (S) $2462.50
- · Z (S) $2500.00
1910.1200 F05 I
- Issued
- Nov 20, 2007
- Abate by
- Dec 8, 2007
- Penalty
- Initial $2,500 · Current $2,463 Reduced
Recent events (2)
- · I (S) $2462.50
- · Z (S) $2500.00
1910.101 B
- Issued
- Nov 20, 2007
- Abate by
- Dec 8, 2007
- Penalty
- Current $713
Recent events (2)
- · I (S) $712.50
- · Z (S)
1910.253 B04 III
- Issued
- Nov 20, 2007
- Abate by
- Dec 8, 2007
Recent events (2)
- · I (S)
- · Z (S)
More inspections at Endeavour Catamaran Corporation
View Endeavour Catamaran Corporation's full OSHA safety record →
More inspections in this industry (NAICS 336612)
More inspections in FL
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 311177026.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.