OSHA Inspection: MOSEBACH MANUFACTURING COMPANY

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of MOSEBACH MANUFACTURING COMPANY in 1417 MCLAUGHLIN RUN ROAD, PITTSBURGH, PA 15241 (NAICS 335314). OSHA activity number 312629702.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Mosebach Manufacturing Company — free Get an email when a new federal OSHA severe-injury report for Mosebach Manufacturing Company is published. One employer, no account, unsubscribe in one click.
Site address
1417 MCLAUGHLIN RUN ROAD
City
PITTSBURGH
State
PA
ZIP
15241
Mailing
6417 MCLAUGHLIN RUN ROAD, PITTSBURGH, PA 15241
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
Y
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
335314
SIC code (legacy)
3625
Employees
70
Ownership type
A
Industry flags
Manufacturing safety.

23 citations on file for this inspection.

1910.147 C01

Serious Gravity 03 1 instance 60 exposed
Issued
Apr 29, 2009
Abate by
Sep 1, 2009
Penalty
Initial $1,250 · Current $1,000 Reduced
Recent events (3)
  • — P (S) $1000.00
  • — I (S) $1000.00
  • — Z (S) $1250.00

1910.147 C04 I

Serious Gravity 03 1 instance 60 exposed
Issued
Apr 29, 2009
Abate by
Sep 1, 2009
Recent events (3)
  • — P (S)
  • — I (S)
  • — Z (S)

1910.147 C07 I

Serious Gravity 03 1 instance 60 exposed
Issued
Apr 29, 2009
Abate by
Sep 1, 2009
Recent events (3)
  • — P (S)
  • — I (S)
  • — Z (S)

1910.147 D03

Serious Gravity 03 1 instance 60 exposed
Issued
Apr 29, 2009
Abate by
Sep 1, 2009
Penalty
Initial $1,250 · Current $1,000 Reduced
Recent events (3)
  • — P (S) $1000.00
  • — I (S) $1000.00
  • — Z (S) $1250.00

1910.132 D02

Serious Gravity 05 1 instance 70 exposed
Issued
Apr 29, 2009
Abate by
Sep 1, 2009
Penalty
Initial $1,750 · Current $1,000 Reduced
Recent events (3)
  • — P (S) $1000.00
  • — I (S) $1000.00
  • — Z (S) $1750.00

1910.133 A01

Serious Gravity 01 1 instance 70 exposed
Issued
Apr 29, 2009
Abate by
Jun 1, 2009
Recent events (2)
  • — I (S)
  • — Z (S)

1910.37 A03

Serious Gravity 01 2 instances 20 exposed
Issued
Apr 29, 2009
Abate by
May 4, 2009
Penalty
Initial $750 · Current $500 Reduced
Recent events (2)
  • — I (S) $500.00
  • — Z (S) $750.00

1910.157 G01

Serious Gravity 01 2 instances 20 exposed
Issued
Apr 29, 2009
Abate by
May 4, 2009
Penalty
Initial $750 · Current $500 Reduced
Recent events (2)
  • — I (S) $500.00
  • — Z (S) $750.00

1910.305 B01

Serious Gravity 03 2 instances 20 exposed
Issued
Apr 29, 2009
Abate by
May 7, 2009
Penalty
Initial $1,250 · Current $1,000 Reduced
Recent events (2)
  • — I (S) $1000.00
  • — Z (S) $1250.00

1910.303 F

Serious Gravity 03 2 instances 20 exposed
Issued
Apr 29, 2009
Abate by
May 7, 2009
Recent events (2)
  • — I (S)
  • — Z (S)

1910.305 A02 IIIF

Serious Gravity 01 1 instance 20 exposed
Issued
Apr 29, 2009
Abate by
Jun 1, 2009
Penalty
Initial $750 · Current $500 Reduced
Recent events (2)
  • — I (S) $500.00
  • — Z (S) $750.00

1910.215 A04

Serious Gravity 01 1 instance 5 exposed
Issued
Apr 29, 2009
Abate by
Jun 1, 2009
Penalty
Initial $750 · Current $500 Reduced
Recent events (2)
  • — I (S) $500.00
  • — Z (S) $750.00

1910.243 C01

Serious Gravity 01 1 instance 1 exposed
Issued
Apr 29, 2009
Abate by
May 18, 2009
Penalty
Initial $750 · Current $500 Reduced
Recent events (2)
  • — I (S) $500.00
  • — Z (S) $750.00

1910.212 A03 II

Serious Gravity 10 1 instance 1 exposed
Issued
Apr 29, 2009
Abate by
May 7, 2009
Penalty
Initial $2,500 · Current $1,780 Reduced
Recent events (2)
  • — I (S) $1780.00
  • — Z (S) $2500.00

1910.212 A01

Serious Gravity 03 1 instance 1 exposed
Issued
Apr 29, 2009
Abate by
May 7, 2009
Recent events (2)
  • — I (S)
  • — Z (S)

1910.217 D06 I

Serious Gravity 03 1 instance 1 exposed
Issued
Apr 29, 2009
Abate by
Sep 1, 2009
Penalty
Initial $1,250 · Current $1,000 Reduced
Recent events (3)
  • — P (S) $1000.00
  • — I (S) $1000.00
  • — Z (S) $1250.00

1910.217 D09 I

Serious Gravity 02 1 instance 1 exposed
Issued
Apr 29, 2009
Abate by
Sep 1, 2009
Recent events (3)
  • — P (S)
  • — I (S)
  • — Z (S)

1910.217 E01 I

Serious Gravity 02 1 instance 1 exposed
Issued
Apr 29, 2009
Abate by
Jun 1, 2009
Recent events (2)
  • — I (S)
  • — Z (S)

5(a)(1)

Serious Gravity 03 1 instance 1 exposed
Issued
Apr 29, 2009
Abate by
Sep 1, 2009
Penalty
Initial $1,250 · Current $1,000 Reduced
Section 5(a)(1) of the Occupational Safety and Health Act of 1970:  The
employer did not furnish employment
and a place of employment which were free from recognized hazards that
were causing or likely to cause
death or serious physical harm to employees in that employees were exposed
to a possible crushing and/or
amputation hazard due to the unexpected operation of the hydraulic press:
(a) Facility, Bay 2, McLaughlin Run Road, Pittsburgh, PA:  On or about
April 21, 2009, there was no guard
over the foot pedal on the Greenerd hydraulic press.
Among other methods, one feasible and acceptable means of abatement is to
put a guard on the foot pedal
and/or stop the practice of using the foot pedal and use the two hand palm
buttons that are available on the
machine.
Recent events (3)
  • — P (S) $1000.00
  • — I (S) $1000.00
  • — Z (S) $1250.00

5(a)(1)

Serious Gravity 03 1 instance 39 exposed
Issued
Apr 29, 2009
Abate by
Sep 1, 2009
Penalty
Initial $1,250 · Current $1,000 Reduced
Section 5(a)(1) of the Occupational Safety and Health Act of 1970:  The
employer did not furnish employment
and a place of employment which were free from recognized hazards that
were causing or likely to cause
death or serious physical harm to employees in that employees were exposed
to falling loads:
(a) Facility, McLaughlin Run Road, Pittsburgh, PA:  On or about April 21,
2009, frequent (monthly) hoist
inspections are not being conducted. In addition, the periodic (yearly)
hoist inspections are not being
conducted in accordance with the hoist manufacturer's recommendations.
Among other methods, one feasible and acceptable means of abatement is to
conduct frequent and periodic
inspections of the hoists in accordance with the manufacturer's
recommendations and ASME B30.11 and
ASME B30.16.
Recent events (3)
  • — P (S) $1000.00
  • — I (S) $1000.00
  • — Z (S) $1250.00

1910.1200 E01

Other-than-serious Gravity 01 1 instance 70 exposed
Issued
Apr 29, 2009
Abate by
Sep 1, 2009
Recent events (3)
  • — P (O)
  • — I (O)
  • — Z (O)

1910.1200 E01 I

Other-than-serious Gravity 01 1 instance 70 exposed
Issued
Apr 29, 2009
Abate by
Sep 1, 2009
Recent events (3)
  • — P (O)
  • — I (O)
  • — Z (O)

1910.1200 H

Other-than-serious Gravity 01 1 instance 70 exposed
Issued
Apr 29, 2009
Abate by
Sep 1, 2009
Recent events (3)
  • — P (O)
  • — I (O)
  • — Z (O)

View Mosebach Manufacturing Company's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 312629702.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.