MULKEYTOWN, IL —
OSHA Inspection: MICHAEL MCELROY & ALEX MCELROY JR., PARTNERS DBA T
Complaint inspection · Safety discipline
At a glance
On , OSHA opened a complaint safety inspection of MICHAEL MCELROY & ALEX MCELROY JR., PARTNERS DBA T in 4227 TANAGER ROAD, MULKEYTOWN, IL 62865 (NAICS 332999). OSHA activity number 313013054.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- MICHAEL MCELROY & ALEX MCELROY JR., PARTNERS DBA T
- Site address
- 4227 TANAGER ROAD
- City
- MULKEYTOWN
- State
- IL
- ZIP
- 62865
What kind of inspection was it?
- Inspection type
- Complaint (B)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- N
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 332999
- SIC code (legacy)
- 3499
- Employees
- 3
- Ownership type
- A
Citations
11 citations on file for this inspection.
5(a)(1)
- Issued
- Nov 13, 2009
- Abate by
- Jan 15, 2010
- Penalty
- Initial $450 · Current $315 Reduced
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to flying plastic projectiles hazards due to possible mechanical failure of plastic polyvinyl chloride (PVC) piping. In the weld shop building, the employer used a Schedule 40 PVC air system to transport compressed air throughout the building at an operating pressure of 130 pounds per inch (psi) from a Black Max air compressor. Employees were exposed to flying plastic projectiles hazards due to possible mechanical failure of the facility air supply system operating at a pressure in excess of 100 psi. Among other methods, the following are feasible and acceptable methods to correct this hazard. 1.Replace the current PVC compressed air piping system with materials suitable for the maximum air pressure as recommended by the Plastic Pipe Institute. 2.Follow the American National Standard Institute/American Society of Mechanical Engineers (ANSI/ASME) B31.1-2007 Power Piping as applicable. Abatement certification is required for this item in accordance with the requirements of 29 CFR 1903.19(c).s
Recent events (2)
- — I (S) $315.00
- — Z (S) $450.00
1910.107 C06
- Issued
- Nov 13, 2009
- Abate by
- Jan 15, 2010
- Penalty
- Initial $600 · Current $420 Reduced
Recent events (2)
- — I (S) $420.00
- — Z (S) $600.00
1910.107 E02
- Issued
- Nov 13, 2009
- Abate by
- Jan 15, 2010
Recent events (2)
- — I (S)
- — Z (S)
1910.212 A05
- Issued
- Nov 13, 2009
- Abate by
- Nov 25, 2009
- Penalty
- Initial $600 · Current $420 Reduced
Recent events (2)
- — I (S) $420.00
- — Z (S) $600.00
1910.215 A04
- Issued
- Nov 13, 2009
- Abate by
- Nov 25, 2009
- Penalty
- Initial $450 · Current $315 Reduced
Recent events (2)
- — I (S) $315.00
- — Z (S) $450.00
1910.215 B09
- Issued
- Nov 13, 2009
- Abate by
- Nov 25, 2009
1910.253 B04 III
- Issued
- Nov 13, 2009
- Abate by
- Nov 25, 2009
- Penalty
- Initial $600 · Current $420 Reduced
Recent events (2)
- — I (S) $420.00
- — Z (S) $600.00
1910.253 E05 IV
- Issued
- Nov 13, 2009
- Abate by
- Nov 25, 2009
- Penalty
- Initial $600 · Current $420 Reduced
Recent events (2)
- — I (S) $420.00
- — Z (S) $600.00
1910.304 F04
- Issued
- Nov 13, 2009
- Abate by
- Nov 25, 2009
- Penalty
- Initial $450 · Current $315 Reduced
Recent events (2)
- — I (S) $315.00
- — Z (S) $450.00
1910.305 G02 II
- Issued
- Nov 13, 2009
- Abate by
- Nov 25, 2009
- Penalty
- Initial $450 · Current $315 Reduced
Recent events (2)
- — I (S) $315.00
- — Z (S) $450.00
1910.157 E03
- Issued
- Nov 13, 2009
- Abate by
- Nov 25, 2009
More inspections at Michael Mcelroy & Alex Mcelroy JR., Partners DBA T
View Michael Mcelroy & Alex Mcelroy JR., Partners DBA T's full OSHA safety record →
More inspections in this industry (NAICS 332999)
More inspections in IL
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 313013054.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.