HIGH POINT, NC —
OSHA Inspection: CONCEPT PLASTICS, INC.
Planned inspection · Health discipline
At a glance
On , OSHA opened a planned health inspection of CONCEPT PLASTICS, INC. in 1218 HICKORY CHAPEL RD., HIGH POINT, NC 27261 (NAICS 325991). OSHA activity number 313600157.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- CONCEPT PLASTICS, INC.
- Site address
- 1218 HICKORY CHAPEL RD.
- City
- HIGH POINT
- State
- NC
- ZIP
- 27261
- Mailing
- P.O. BOX 847, HIGH POINT, NC 27261
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Complete (A)
- Discipline
- Health
- Advance notice
- No
- Union status
- N
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 325991
- SIC code (legacy)
- 3087
- Employees
- 65
- Ownership type
- A
- Industry flags
- Manufacturing health.
Citations
16 citations on file for this inspection.
95012901
- Issued
- Dec 16, 2009
- Abate by
- Feb 19, 2010
- Penalty
- Initial $2,100 · Current $1,400 Reduced
General-duty citation text
North Carolina General Statute 95-129(1) of the Occupational Safety and Health Act of North Carolina: The employer did not furnish each of his employees conditions of employment and a place of employment free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to fire and explosion hazards: a)Mixing Room, Clean-Up Area, Sanding Department - the work tasks, including, but not limited to, sanding and cutting of styrene resin based furniture components, and mixing of various dust components to create the styrene resin based materials for casting, produced dust that was not properly contained. Particularly in the Mixing Room, at least 95of the horizontal surfaces, including the floor, had accumulated dust greater than one inch thick. The Sanding/Sawing Department and Clean-Up Area contained varying degrees of the dust ranging from 1/32 of an inch to several inches on the majority of horizontal surfaces, including but not limited to, the following: building supports (joists), cross braces, work surfaces, sanding and sawing equipment, flourescent light bulbs and housings, compressed air lines, water lines, electrical equipment, and sprinkler system piping. The accumulated dust consisted of the various components, including cornstarch, wheat flour, ground pecan nut shell flour, marble, boron oxide, and styrene in resin. Cornstarch, pecan nut shell flour, and wheat flour were listed in NFPA 499, 1997 edition, as Group G combustible dusts. There were various deficiencies in attempted controls for the dust, including, but not limited to, the following: there had been no process hazard analysis completed for the process, the housekeeping program was not effective in eliminating accumulated dust on overhead surfaces in the work area, there were no management of change procedures for ventilation systems carrying wood dust and the styrene resin based dust, fugitive dust control measures were not in place, there was the lack of an inspection, testing, and maintenance program for the ventilation system, the methods for adding dust to mixtures included only manual dumping, and the dust collection equipment duct work was not grounded and bonded. REFERENCE: National Fire Protection Agency Standard no.654: Standard for the Prevention of Fire and Dust Explosions from the Manufacturing, Processing, and Handling of Combustible Particulate Solids, 2006 edition. NOTE: Among other methods of abatement, one feasible and acceptable method to correct these hazards would be to follow the guidelines established in the National Fire Protection Agency Standard no.654: Standard for the Prevention of Fire and Dust Explosions from the Manufacturing, Processing, and Handling of Combustible Particulate Solids, 2006 edition.
Recent events (3)
- — I (S) $1400.00
- — P (S) $2100.00
- — Z (S) $2100.00
1910.22 A01
- Issued
- Dec 16, 2009
- Abate by
- Feb 19, 2010
- Penalty
- Initial $2,100
Recent events (3)
- — I (S)
- — P (S) $2100.00
- — Z (S) $2100.00
1910.106 D02 I
- Issued
- Dec 16, 2009
- Abate by
- Feb 19, 2010
- Penalty
- Initial $1,500 · Current $1,000 Reduced
Recent events (3)
- — I (S) $1000.00
- — P (S) $1500.00
- — Z (S) $1500.00
1910.106 D02 III
- Issued
- Dec 16, 2009
- Abate by
- Feb 19, 2010
Recent events (2)
- — P (S)
- — Z (S)
1910.106 E06 II
- Issued
- Dec 16, 2009
- Abate by
- Feb 19, 2010
- Penalty
- Initial $1,500
Recent events (3)
- — I (S)
- — P (S) $1500.00
- — Z (S) $1500.00
1910.145 C03
- Issued
- Dec 16, 2009
- Abate by
- Feb 19, 2010
- Penalty
- Initial $2,100 · Current $1,400 Reduced
Recent events (3)
- — I (S) $1400.00
- — P (S) $2100.00
- — Z (S) $2100.00
1910.147 C06 I
- Issued
- Dec 16, 2009
- Abate by
- Feb 19, 2010
- Penalty
- Initial $900
Recent events (3)
- — I (O)
- — P (S) $900.00
- — Z (S) $900.00
1910.212 A01
- Issued
- Dec 16, 2009
- Abate by
- Feb 19, 2010
- Penalty
- Initial $900 · Current $600 Reduced
Recent events (3)
- — I (S) $600.00
- — P (S) $900.00
- — Z (S) $900.00
1910.212 B
- Issued
- Dec 16, 2009
- Abate by
- Feb 19, 2010
- Penalty
- Initial $900 · Current $600 Reduced
Recent events (3)
- — I (S) $600.00
- — P (S) $900.00
- — Z (S) $900.00
1910.242 B
- Issued
- Dec 16, 2009
- Abate by
- Feb 19, 2010
- Penalty
- Initial $2,100 · Current $1,400 Reduced
Recent events (3)
- — I (S) $1400.00
- — P (S) $2100.00
- — Z (S) $2100.00
1910.307 C02 I
- Issued
- Dec 16, 2009
- Abate by
- Feb 19, 2010
- Penalty
- Initial $2,100 · Current $2,100
Recent events (3)
- — I (S) $2100.00
- — P (S) $2100.00
- — Z (S) $2100.00
1910.23 D01 III
- Issued
- Dec 16, 2009
- Abate by
- Feb 19, 2010
Recent events (2)
- — P (O)
- — Z (O)
1910.107 B09
- Issued
- Dec 16, 2009
- Abate by
- Feb 19, 2010
Recent events (2)
- — P (O)
- — Z (O)
1910.176 B
- Issued
- Dec 16, 2009
- Abate by
- Feb 19, 2010
Recent events (2)
- — P (O)
- — Z (O)
1910.178 A06
- Issued
- Dec 16, 2009
- Abate by
- Feb 19, 2010
Recent events (2)
- — P (O)
- — Z (O)
1910.134 D01 III
- Issued
- Dec 16, 2009
- Abate by
- Dec 21, 2009
04302280
More inspections at Concept Plastics, INC.
View Concept Plastics, INC.'s full OSHA safety record →
More inspections in this industry (NAICS 325991)
More inspections in NC
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 313600157.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.