Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,197,549Inspections Most recent open 2026-08-27 Last loaded 2026-08-31

OSHA Inspection: RAMBLER ENERGY SERVICES, INC.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of RAMBLER ENERGY SERVICES, INC. in HARRIGAN #1 WELL, SEC 1-11N-3W OKLAHOMA CTY, OKLAHOMA CITY, OK 73129 (NAICS 213112). OSHA activity number 313694333.

What this inspection record means

OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Rambler Energy Services, INC. for free Get an email when a new federal OSHA severe-injury report for Rambler Energy Services, INC. is published. One employer, no account, unsubscribe in one click.
Site address
HARRIGAN #1 WELL, SEC 1-11N-3W OKLAHOMA CTY
City
OKLAHOMA CITY
State
OK
ZIP
73129
Mailing
114 E BROADWAY, STE 207, ENID, OK 73702
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
Non-union (N)
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
213112
SIC code (legacy)
1389
Employees
4
Ownership type
Private (A)

5 citations on file for this inspection.

5(a)(1)

Serious Gravity 10 1 instance 1 exposed
Issued
Jan 12, 2011
Abate by
Jan 17, 2011
Penalty
Initial $2,500 · Current $1,000 Reduced
Section 5(a)(1) of the Occupational Safety and Health Act of 1970:  The
employer did not
furnish employment and a place of employment which were free from
recognized hazards that
were causing or likely to cause death or serious physical harm:
Well site; on or about August 18, 2010, employees were operating a service
rig during the re-
installation of an oil/gas well down hole electric pump, the derrick hand
was working in the rig
mast where the emergency escape system (Geronimo) had not been installed.
This prevented
the derrick hand from making timely emergency egress from the mast during
rig emergencies
with hazards as:  fire, explosion, flying objects and rig collapse.  The
American Petroleum
Institute (API) Recommended Practice (RP) for Occupational Safety for Oil
and Gas Well
Drilling and Servicing Operations, RP 54, 6.10.1 requires that an
auxiliary means of escape be
installed on the  mast/derrick and that it provides a ready and convenient
means of escape from
the derrick man's working platform.  Among other methods, one feasible and
acceptable
abatement method to correct this hazard is to assure that the available
escape system is installed
according to the manufacturers instructions prior to the rig being
operated.ons
Recent events (2)
  • · I (S) $1000.00
  • · Z (S) $2500.00

1910.23 C01

Serious Gravity 01 2 instances 4 exposed
Issued
Jan 12, 2011
Abate by
Jan 17, 2011
Penalty
Initial $750 · Current $300 Reduced
Recent events (2)
  • · I (S) $300.00
  • · Z (S) $750.00

1910.132 A

Serious Gravity 05 4 instances 4 exposed
Issued
Jan 12, 2011
Abate by
Feb 25, 2011
Penalty
Initial $1,750 · Current $700 Reduced
Recent events (2)
  • · I (S) $700.00
  • · Z (S) $1750.00

1910.133 A01

Serious Gravity 02 4 instances 4 exposed
Issued
Jan 12, 2011
Abate by
Jan 24, 2011
Penalty
Initial $1,000 · Current $500 Reduced
Recent events (2)
  • · I (S) $500.00
  • · Z (S) $1000.00

1910.157 C04

Other-than-serious Gravity 01 1 instance 4 exposed
Issued
Jan 11, 2011
Abate by
Jan 21, 2011

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). OSHA publishes its own view of this case as inspection number 313694333.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.