SELMAN CITY, TX —
OSHA Inspection: HALO ENERGY LLC
Referral inspection · Safety discipline
At a glance
On , OSHA opened a referral safety inspection of HALO ENERGY LLC in RIG #112 CR 3108, SELMAN CITY, TX 75689 (NAICS 213112). OSHA activity number 314176249.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- HALO ENERGY LLC
- Site address
- RIG #112 CR 3108
- City
- SELMAN CITY
- State
- TX
- ZIP
- 75689
- Mailing
- 1709 INDUSTRIAL BLVD, KILGORE, TX 75662
What kind of inspection was it?
- Inspection type
- Referral (C)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- N
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 213112
- SIC code (legacy)
- 1389
- Employees
- 8
- Ownership type
- A
- Industry flags
- Manufacturing safety.
Citations
4 citations on file for this inspection.
5(a)(1)
- Issued
- Oct 21, 2010
- Abate by
- Oct 29, 2010
- Penalty
- Initial $2,100 · Current $1,470 Reduced
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees working from elevated heights of oil-well service rig derrick: On or about May 4, 2010 and times prior to, at HALO Energy Rig #112, an employee worked from the tubing board where an emergency escape device was not installed and available for use. The employee working from the tubing board was exposed to a potential fall or severe burns associated with, and in the event of a fire or explosion at the oil-well service rig platform. One feasible and acceptable abatement method to correct this hazard would be to ensure that an auxiliary means of escape is installed and ready for use prior to personnel working in the derrick in accordance with Recommended Practice for Occupational Safety for Oil and Gas Well Drilling and Servicing Operations- API 54, Third Edition, August 1999, Section 6.10.1, Auxiliary Escape: "On all land rigs, the derrick or mast shall have an auxiliary means of escape installed prior to personnel working in the derrick. The auxiliary escape route should use a specially rigged and securely anchored escape line attached to the derrick or mast so as to provide a ready and convenient means of escape from the derrickman's working platform."'s
Recent events (2)
- — I (S) $1470.00
- — Z (S) $2100.00
5(a)(1)
- Issued
- Oct 21, 2010
- Abate by
- Oct 29, 2010
- Penalty
- Initial $2,100 · Current $1,470 Reduced
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees exposed to struck by and crushing hazards: On or about May 4, 2010 and times prior to, at HALO Energy Rig #112, employees working at rig #112, were exposed to potential struck by and crushing hazards associated with the possible collapse of the derrick due to the continued use of a traveling block running wire-rope line rubbing against and compromising a critical spreader-arm of the derrick locking-pins. Among other methods, feasible and acceptable means to correct this hazard are: 1.Ensure the Rig Operator inspects the rigging involved each time the derrick is erected and does not initiate rig operations until questionable critical components are secured and not compromised. 2.Ensure the Rig Operator visually inspects and corrects the routing of the derricks running wire-rope line and does not continue rig operations when the integrity of the derrick locking area components are compromised in accordance with: API Recommended Practice 54, Third Edition, August 1999., Subsection 6.3.2,: Well operations involving the rig shall not be commenced until the rig is rigged up in a safe manner.
Recent events (2)
- — I (S) $1470.00
- — Z (S) $2100.00
1910.23 C01
- Issued
- Oct 21, 2010
- Abate by
- Oct 29, 2010
- Penalty
- Initial $2,100 · Current $1,470 Reduced
Recent events (2)
- — I (S) $1470.00
- — Z (S) $2100.00
1910.27 D05
- Issued
- Oct 21, 2010
- Abate by
- Oct 29, 2010
- Penalty
- Initial $2,100 · Current $1,470 Reduced
Recent events (2)
- — I (S) $1470.00
- — Z (S) $2100.00
More inspections in this industry (NAICS 213112)
More inspections in TX
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 314176249.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.