JUNCTION CITY, KS —
OSHA Inspection: VEOLIA WATER NORTH AMERICA CENTRAL LLC
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of VEOLIA WATER NORTH AMERICA CENTRAL LLC in 2101 N. JACKSON STREET, JUNCTION CITY, KS 66441 (NAICS 221310). OSHA activity number 315091298.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- VEOLIA WATER NORTH AMERICA CENTRAL LLC
- Site address
- 2101 N. JACKSON STREET
- City
- JUNCTION CITY
- State
- KS
- ZIP
- 66441
- Mailing
- 184 SHUMAN BLVD., SUITE 450, NAPERVILLE, IL 60540
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- N
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 221310
- SIC code (legacy)
- 4941
- Employees
- 8
- Ownership type
- A
Citations
11 citations on file for this inspection.
1910.119 D
- Issued
- Feb 28, 2012
- Abate by
- Jul 31, 2012
- Penalty
- Initial $4,000 · Current $2,800 Reduced
General-duty citation text
29 CFR 1910.119(d): The employer did not develop a written compilation of process safety information on hazardous chemicals in the process, the technology of the process, and the equipment in the process before conducting the process hazard analysis: Employee(s) working in the water treatment plant were exposed to asphyxiation hazards due to the process safety information for the following equipment not being available: (a)no written process safety information for the chlorine ton cylinders. (b)no written process safety information for the clear tubing being used for chlorine gas (c)no written process safety information for the chlorine metal piping. (d)no written process safety information for the chlorine pvc plastic piping (vent line). (e)no written process safety information for the chlorine globe valves. (f)no written process safety information for the black flexible tubing attached to the vacuum regulators. (g)no written process safety information for the clear tubing being used for the chlorine vent line. (h)no written process safety information for the flexible connector. (i)no written process safety information for the lead washers. Employee(s) were exposed to release of chlorine compounds to the atmosphere that can lead to death or injury to persons working in the facility. 29 CFR 1903.19(d)(1) requires certification and documentation that the abatement of the above violation is completed.
Recent events (2)
- — I (S) $2800.00
- — Z (S) $4000.00
1910.119 D03 IB
- Issued
- Feb 28, 2012
- Abate by
- Mar 2, 2012
- Penalty
- Initial $4,000 · Current $2,800 Reduced
General-duty citation text
29 CFR 1910.119(d)(3)(i)(B): Process safety information pertaining to the equipment in the process did not include the piping and instrument diagrams (P&ID'S): At the water treatment building, the employer had not verified that the P&ID's were up to date and accurate for use by Veolia water employee(s) and contractors for line breaks, equipment / piping replace or repairs, and etc. Piping circuits were evaluated and the following was noted: Chlorine Storage Room (a)Yoke valves between two gate valves for each cylinder were drawn on the p&id, but were not observed during the walk around. (b)A pressure gauge down stream from the ton cylinders were drawn on the p&id, but not observed during the walk around. (c)A globe valve was observed above the drip leg cap(#6), but was not drawn on the p&id. (d)A Jamesbury ball valve was observed downstream of drip leg (#6), but was not drawn on the p&id. (e)A flange coupling with a lead washer was observed between the pressure reducer and the Jamesbury ball valve, but not drawn on the p&id. (f)A metal to plastic coupling was observed on the chlorine vent line that was exiting the Fisher Porter pressure reducer during the walk around, but not drawn on the p&id. (g)The vent line exiting the Fisher Porter pressure reducer was observed during the walk around, but not drawn on the p&id. (h)A coupling flange downstream of the pressure reducer was observed during the walk around, but not drawn on the p&id. (i)a second Jamesbury ball valve was observed during the walk around, but not drawn on the p&id. (j)A second Jamesbury ball valve was observed downstream of the coupling flange, but not drawn on the p&id. (k)A second drip leg downstream of the Fisher Porter pressure reducer was observed during the walk around, but not drawn on the p&id. (l)A globe valve on the second drip leg downstream of the Fisher Porter pressure reducer was observed during the walk around, but not drawn on the p&id. Chlorine Feed Room (m)A flange was observed between the strainer and the drip leg upstream of chlorinator #1, but was not drawn on the p&id. (n)A pressure gage upstream of chlorinator #1 was observed during the walk around, but not drawn on the p&id. (o)A globe valve between the pressure gauge and drip leg (#11) for chlorinator 1 was observed during the walk around, but not drawn on the p&id. (p)A heater attached to drip leg (#11) for chlorinator 1 was observed during the walk around, but not drawn on the p&id. (q)A globe valve between drip leg (#11) and the vacuum regulator for chlorinator 1 was observed during the walk around, but not drawn on the p&id. (r)A flange was observed between the strainer and the drip leg upstream of chlorinator #2, but was not drawn on the p&id. (s)A pressure gauge upstream of chlorinator #2 was observed during the walk around, but not drawn on the p&id. (t)A globe valve between the pressure gauge and drip leg (#11) for chlorinator 2 was observed during the walk around, but not drawn on the p&id. (u)A heater attached to drip leg (#11) for chlorinator 2 was observed during the walk around, but not drawn on the p&id. (v)A globe valve between drip leg (#11) and the vacuum regulator for chlorinator 2 was observed during the walk around, but not drawn on the p&id. (w)A vent line from vacuum regulator for chlorinator 1 was observed during the walk around, but not drawn on the p&id. (x)A vent line from vacuum regulator for chlorinator 2 was observed during the walk around, but not drawn on the p&id. (y)A rotameter for chlorinator #1 was observed during the walk around, but not drawn on the p&id. Employee(s) were exposed to release of chlorine compounds to the atmosphere that can lead to death or injury to persons working in the facility. 29 CFR 1903.19(c)(2) abatement of the above violation was verified at the time of inspection. No certification is required.tion
Recent events (2)
- — I (S) $2800.00
- — Z (S) $4000.00
1910.119 D03 IF
- Issued
- Feb 28, 2012
- Abate by
- Jul 31, 2012
- Penalty
- Initial $3,000 · Current $2,100 Reduced
General-duty citation text
29 CFR 1910.119(d)(3)(i)(F): Process safety information pertaining to the equipment did not include the design codes and standards employed: At the facility, the employer did not include design codes and standards employed in the process safety information pertaining to equipment, including, but not limited to the following: (a) steel piping (b) pvc piping (c) black flexible tubing (d) valves (e) fittings Employee(s) were exposed to release of chlorine compounds to the atmosphere that can lead to death or injury to persons working in the facility. 29 CFR 1903.19(d)(1) requires certification and documentation that the abatement of the above violation is completed.
Recent events (2)
- — I (O) $2100.00
- — Z (S) $3000.00
1910.119 D03 IC
- Issued
- Feb 28, 2012
- Abate by
- Jul 31, 2012
General-duty citation text
29 CFR 1910.119(d)(3)(i)(C): Process safety information pertaining to the equipment in the process did not include the electrical classification: An electrical classification of the chlorine process was not provided for the water treatment plant where electrical equipment was being used. The operators working inside the chlorine storage / feed rooms were to fire / electrical hazards due to no evaluation being performed to determine if the electrical equipment operating in the chlorine process that could possibly react with the inadvertent release of chlorine gas. Employee(s) were exposed to release of chlorine compounds to the atmosphere that can lead to death or injury to persons working in the facility. 29 CFR 1903.19(d)(1) requires certification and documentation that the abatement of the above violation is completed.
Recent events (2)
- — I (O)
- — Z (S)
1910.119 D03 II
- Issued
- Feb 28, 2012
- Abate by
- Jul 31, 2012
- Penalty
- Initial $4,000 · Current $2,800 Reduced
General-duty citation text
29 CFR 1910.119(d)(3)(ii): The employer did not document that the equipment in the process complied with recognized and generally accepted good engineering practices: At the facility, the employer did not document that the equipment in the process complied with recognized and generally acceptable good engineering practices for the following: (a)Employee(s) working in the chlorine process were potentially exposed to health hazards of chlorine gas. The chlorine gas monitors in the chlorine storage and feed rooms had their alarm set point at 2 parts per million, this setting is above the OSHA ceiling level of 1 part per million. (b)Employee(s) working in the chlorine process were potentially exposed to chlorine gas health hazards due to the chlorine gas monitors in the storage and feed room being approximately 28 inches from the ground floor. Industry practice is to locate chlorine gas monitors approximately 12 inches from the ground floor due to chlorine being heavier than air and if there was a leak, the chlorine will accumulate on the floor. 29 CFR 1903.19(d)(1) requires certification and documentation that the abatement of the above violation is completed.
Recent events (2)
- — I (O) $2800.00
- — Z (S) $4000.00
1910.119 F01 I
- Issued
- Feb 28, 2012
- Abate by
- May 31, 2013
- Penalty
- Initial $5,000 · Current $3,500 Reduced
General-duty citation text
29 CFR 1910.119(f)(1): The employer did not develop and implement written operating procedures that provided clear instructions for safety conducting activities in each covered process consistent with the process safety information and which addressed the elements listed in 29 CFR 1910.119(f)(1)(i) through (f)(1)(iv): (a)Employee(s) disconnecting and replacing flexible connector or black flexible tubing for the chlorine process were exposed to chlorine gas health hazards due to no standard operating procedures being developed or implemented to address cleaning the inside of new process piping, prior to installation in the chlorine process. (b)At the water treatment plant a written standard operating procedure for shutting down the chlorine process in the event of a long term power outage were exposing employee(s) to potential chlorine gas health hazards due to no backup power source being provided. For employee(s) required enter the chlorine storage and feed rooms to shut down the chlorine process, there would be no power to turn on the ventilation system prior to entry nor would the operators have access to the chlorine gas detection monitors. (c)At the water treatment plant a written standard operating procedure for changing one ton chlorine cylinders was inadequate due to the facility manager or the site/project safety coordinator not being present during a ton cylinder change out at all times according to the ton cylinder change out procedure. Employee(s) were exposed to release of chlorine compounds to the atmosphere that can lead to death or injury to persons working in the facility. 29 CFR 1903.19(d)(1) requires certification and documentation that the abatement of the above violation is completed.
Recent events (3)
- — P (O) $3500.00
- — I (O) $3500.00
- — Z (S) $5000.00
1910.119 J02
- Issued
- Feb 28, 2012
- Abate by
- May 31, 2013
- Penalty
- Initial $5,000 · Current $3,500 Reduced
General-duty citation text
29 CFR 1910.119(j)(2): The employer did not establish and implement written procedures to maintain the on-going mechanical integrity of process equipment: (a)The employer did not develop and implement a procedure for evaluating flexible connectors that were to be changed out annually to determine if the annual replacement policy was adequate. (b)The employer did not develop and implement a procedure for evaluating valves in the chlorine process. (c)The employer did not develop and implement a procedure for conducting non- destructive testing on pressurized metal piping. (d)The employer did not develop and implement a procedure for evaluating metal pipe supported by ceiling hangars for metal to metal corrosion. (e)The employer did not develop and implement a procedure for evaluating the black flexible tubings that processes chlorine from the rotameter to the ejectors. Employee(s) were exposed to release of chlorine compounds to the atmosphere that can lead to death or injury to persons working in the facility. 29 CFR 1903.19(d)(1) requires certification and documentation that the abatement of the above violation is completed.
Recent events (3)
- — P (S) $3500.00
- — I (S) $3500.00
- — Z (S) $5000.00
1910.119 J04 I
- Issued
- Feb 28, 2012
- Abate by
- May 31, 2013
- Penalty
- Initial $7,000 · Current $4,900 Reduced
General-duty citation text
29 CFR 1910.119(j)(4)(i): Inspections and tests were not performed on process equipment to maintain its mechanical integrity: Employee(s) working in the water treatment plant were exposed to health hazards due to the following equipment not receiving mechanical integrity inspections: (a)there were no mechanical integrity inspection records for the metal piping in the chlorine storage room. (b)there were no mechanical integrity inspection records for the metal piping in the chlorine feed room. (c)there were no mechanical integrity inspection records for the chlorine manifold system in the storage room. (d)there were no mechanical integrity inspection records for the pvc vent piping in the chlorine storage and chemical feed rooms. (e)there were no mechanical integrity inspection records for the black flexible tubings that are attached to the vacuum regulators, rotameters, and the ejectors. Employee(s) were exposed to release of chlorine compounds to the atmosphere that can lead to death or injury to persons working in the facility. 29 CFR 1903.19(d)(1) requires certification and documentation that the abatement of the above violation is completed.
Recent events (3)
- — P (S) $4900.00
- — I (S) $4900.00
- — Z (S) $7000.00
1910.119 L01
- Issued
- Feb 28, 2012
- Abate by
- Jul 31, 2012
- Penalty
- Initial $4,000 · Current $2,800 Reduced
General-duty citation text
29 CFR 1910.119(l)(1): The employer did not establish and implement written procedures to manage changes to process chemicals, technology, equipment, and procedures; and, changes to facilities that affect a covered process: (a)At the water treatment plant, a written management of change program had not been developed and implemented to inform all employee(s) working in the chlorine process when changes to the process chemicals, technology, equipment, or procedures have occurred. (b)the employer had not developed nor implemented a written management of change program to address changes to the chlorine process; there has been several changes to the program where no management of change was conducted such as the following: (1)No management of change for the removal of the pressure regulator #7. (2)No management of change for the removal of the yoke valves. (3)No management of change for the removal of the pressure gauge #8 (4)No management of change for attaching a clear plastic tubing to the second pvc plastic vent line entering the chlorine feed room. Employee(s) were exposed to release of chlorine compounds to the atmosphere that can lead to death or injury to persons working in the facility. 29 CFR 1903.19(d)(1) requires certification and documentation that the abatement of the above violation is completed.
Recent events (2)
- — I (S) $2800.00
- — Z (S) $4000.00
1910.119 O01
- Issued
- Feb 28, 2012
- Abate by
- Jul 31, 2012
- Penalty
- Initial $3,000 · Current $2,100 Reduced
General-duty citation text
29 CFR 1910.119(o)(1): The employer did not certify that they had evaluated compliance with the provisions of 29 CFR 1910.119 at least every three years to verify that the procedures and practices developed under this standard were adequate and are being followed: (a) In the 2010 compliance audit the employer did not address the following: (1)Process Hazard Analysis item number 11 (2)Contractors item number 22 (3)Contractors item number 23 (4)Contractors item number 24 (b) The employer did not complete a compliance audit every 3 years to determine if the procedures and practices established for the processes covered by the process safety management standard were being followed. There was no compliance audit conducted prior to 2010. Employee(s) were exposed to release of chlorine compounds to the atmosphere that can lead to death or injury to persons working in the facility. 29 CFR 1903.19(d)(1) requires certification and documentation that the abatement of the above violation is completed.
Recent events (2)
- — I (S) $2100.00
- — Z (S) $3000.00
1910.119 O04
- Issued
- Feb 28, 2012
- Abate by
- May 31, 2013
General-duty citation text
29 CFR 1910.119(o)(4): The employer did not determine and document an appropriate response to each of the findings of the compliance audit required by 29 CFR 1910.119(o)(1), and document that the deficiencies had been corrected: Employee(s) working in the water treatment building were exposed to health hazards associated with chlorine vapors in that the employer had not documented corrective actions pending or taken in relation to each of the deficiencies documented in the 2010 compliance audit such as but not limited to the following: (a)an evaluation of the consequences of deviations for the technology of the process (b)the PHA did not address previous incidents with likely potential for catastrophic consequences (c)written procedures to maintain the on-going integrity of process equipment and documentation that indicate the procedures have been implemented. (d)documented each inspection and test has been performed on process equipment. (e)developing a report of the findings for each compliance audit (f)has the employer promptly determined and documented an appropriate response to each of the compliant audit findings (g)documented that deficiencies noted in 2010 compliance audit has been corrected Employee(s) were exposed to release of chlorine compounds to the atmosphere that can lead to death or injury to persons working in the facility. 29 CFR 1903.19(d)(1) requires certification and documentation that the abatement of the above violation is completed.
Recent events (3)
- — P (S)
- — I (S)
- — Z (S)
More inspections at Veolia Water North America Central LLC
View Veolia Water North America Central LLC's full OSHA safety record →
More inspections in this industry (NAICS 221310)
More inspections in KS
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 315091298.