OSHA Inspection: CBH BUILDING AND DEVELOPMENT LLC

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of CBH BUILDING AND DEVELOPMENT LLC in 5005 WEST THEODORE ST., PLAINFIELD, IL 60586 (NAICS 236220). OSHA activity number 315154732.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch CBH Building and Development LLC — free Get an email when a new federal OSHA severe-injury report for CBH Building and Development LLC is published. One employer, no account, unsubscribe in one click.
Site address
5005 WEST THEODORE ST.
City
PLAINFIELD
State
IL
ZIP
60586
Mailing
152 84TH STREET SW, BYRON CENTER, MI 49315
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
N
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
236220
SIC code (legacy)
1542
Employees
12
Ownership type
A

2 citations on file for this inspection.

5(a)(1)

Serious Gravity 10 1 instance 4 exposed
Issued
Apr 29, 2011
Abate by
May 11, 2011
Penalty
Initial $4,200 · Current $2,940 Reduced
Section 5(a)(1) of the Occupational safety and Health Act of 1970:  the
employer did not furnish
employment and a place of employment which were free from recognized
hazards that were
causing or likely to cause death or serious physical harm to employees:
a. On or about January 26, 2011 - at the above addressed jobsite, the
employer allowed his
employees to operate and lift large wood trusses using lifting straps
placed around the structure
of a rough terrain forklift when this practice is not recommended and or
approved by the
manufacture. The employees were thereby exposed to struck by hazards due
to the possibility
of the load sliding out of the sling. One feasible and acceptable method
to correct this hazard,
among other means, would be for the contractor to purchase or rent the
appropriate attachments,
i.e. truss boom or crane hook to replace the existing forks. Either of
these two attachments are
better suited and approved for this type of work.
Recent events (2)
  • — I (S) $2940.00
  • — Z (S) $4200.00

1926.501 B13

Serious Gravity 10 1 instance 4 exposed
Issued
Apr 29, 2011
Abate by
May 11, 2011
Penalty
Initial $4,200 · Current $2,940 Reduced
Recent events (2)
  • — I (S) $2940.00
  • — Z (S) $4200.00

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 315154732.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.