OSHA Inspection: STUCCO BOYS LLC

Referral inspection · Safety discipline

On , OSHA opened a referral safety inspection of STUCCO BOYS LLC in 181 NORTH MAIN, BLACKFOOT, ID 83221 (NAICS 238140). OSHA activity number 330296518.

What this inspection record means

OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Stucco Boys LLC for free Get an email when a new federal OSHA severe-injury report for Stucco Boys LLC is published. One employer, no account, unsubscribe in one click.
Establishment
STUCCO BOYS LLC
Site address
181 NORTH MAIN
City
BLACKFOOT
State
ID
ZIP
83221
Mailing
991 EAST 700 NORTH, #E, SHELLEY, ID 83274
Inspection type
Referral (C)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238140
Employees
3
Ownership type
A

6 citations on file for this inspection.

1926.451 B01

Serious Gravity 1 1 instance 2 exposed
Issued
Jun 15, 2011
Abate by
Jun 16, 2011
Penalty
Initial $1,800 · Current $1,800
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii):    a) Jobsite: On May 23, 2011 and times prior thereto,  employees performed stucco activities on two seperate levels of scaffold that were not fully planked.    Note) Abatement certification is required for this item.
Recent events (1)
  • · Z (S) $1800

1926.451 C02

Serious Gravity 1 1 exposed
Issued
Jun 15, 2011
Abate by
Jun 16, 2011
Penalty
Initial $0 · Current $0
29 CFR 1926.451(c)(2): Supported scaffold poles, legs, posts, frames, and uprights did not bear on base plates and mud sills or other adequate firm foundation:    a) Jobsite: On May 23, 2011 and times prior thereto the scaffold used by employees to perform stucco work was missing either base plates or mudsill's or both.      Note) Abatement certification is required for this item.
Recent events (1)
  • · Z (S) $0

1926.451 E01

Serious Gravity 5 1 instance 1 exposed
Issued
Jun 15, 2011
Abate by
Jun 16, 2011
Penalty
Initial $2,400 · Current $2,400
29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, sturcure, personnel hoist, or similar surface was not used:    a) Jobsite: On May 23, 2011 and times prior thereto employees used self supporting A-framed ladders in the closed position for access to the lower level and for access between the upper levels of the scaffold.      Note) Abatement certification is required for this item.
Recent events (1)
  • · Z (S) $2400

1926.454 B02

Serious Gravity 5 1 exposed
Issued
Jun 15, 2011
Abate by
Jun 22, 2011
Penalty
Initial $0 · Current $0
29 CFR 1926.454(b)(2): The employer did not have each employee trained by a competent person for the correct procedures for erecting, disassembling, moving, operating, repairing, inspecting, and maintaining the type of scaffold in question:    a) Jobsite: On May23, 2011 and times prior thereto employees performing stucco activities on a tubular welded frame scaffold sysytem did not recognize the hazard(s) of not having a complete guardrail system in place, and take actions to minimize the hazard.     b)  Jobsite: On May23, 2011 and times prior thereto employees performing stucco activities on a tubular welded frame scaffold sysytem did not recognize the hazard of working on the upper levels that were not fully decked or planked, and take actions to minimize the hazard.     c) Jobsite: On May23, 2011 and times prior thereto employees performing stucco activities on a tubular welded frame scaffold sysytem did not recognize the hazard of not having safe access to all working levels of the scaffold system, and take actions to minimize the hazard.     d) Jobsite: On May23, 2011 and times prior thereto employees performing stucco activities on a tubular welded frame scaffold sysytem did not recognize that the scaffolld legs/frames were not all on base plates, mud sills or other adequate firm foundation, and take actions to minimize the hazard.    Note) Abatemen certification is required for this item.
Recent events (1)
  • · Z (S) $0

1926.451 G04 I

Serious Gravity 5 1 exposed
Issued
Jun 15, 2011
Abate by
Jun 16, 2011
Penalty
Initial $3,000 · Current $3,000
29 CFR 1926.451(g)(4)(i): Guardrail systems were not installed along all open sides and ends of platforms:    a) Jobsite: On May 23, 2011 and times prior thereto employees performing stucco activities from a scaffold system  that did not have guardrails in place at the platform ends of each working level, were exposed to a fall hazard to the sidewalk below.      Note) Abatement certification is required for this item.
Recent events (1)
  • · Z (S) $3000

1926.451 G04 IV

Serious Gravity 5 1 exposed
Issued
Jun 15, 2011
Abate by
Jun 16, 2011
Penalty
Initial $0 · Current $0
29 CFR 1926.451(g)(4)(iv): Midrails were not installed at a height approximately midway between the top edge of the guardrail system and the platform surface:    a) Jobsite: On May 23, 2011 and times prior thereto employees performed stucco activities on the upper levels of the scaffold without a complete guardrail system in place.      Note 1) 29 CFR 1926.451(g)(xv) states crossbracing is acceptable in place of a midrail when the crossing point of two braces is between 20 inches (0.5 m) and 30 inches (0.8 m) above the work platform or as a toprail when the crossing point of two braces is between 38 inches (0.97 m) and 48 inches (1.3 m) above the work platform. The end points at each upright shall be no more than 48 inches (1.3 m) apart.    Note 2) Abatement certification is required for this item.
Recent events (1)
  • · Z (S) $0

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 330296518.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.