OSHA Inspection: AWR DEVELOPERS, INC.
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of AWR DEVELOPERS, INC. in 3549 N. RETA, CHICAGO, IL 60657 (NAICS 238140). OSHA activity number 331906446.
OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- AWR DEVELOPERS, INC.
- Site address
- 3549 N. RETA
- City
- CHICAGO
- State
- IL
- ZIP
- 60657
- Mailing
- 12621 ROSEMARY LN, PALOS PARK, IL 60464
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- Non-union (B)
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238140
- Employees
- 8
- Ownership type
- Private (A)
Citations
8 citations on file for this inspection.
1903.19 C01
- Issued
- Jul 18, 2012
- Abate by
- Jul 19, 2012
- Penalty
- Initial $600 · Current $600
General-duty citation text
29 CFR 1903.19(c)(1): The employer did not certify to OSHA, within 10 calendar days after the abatement date, that the cited violation had been abated: AWR Developers, Inc. failed to certify to OSHA within 10 calendar days after the abatement date that each of the following cited violations had been corrected: Citation Number Item Number Abatement Date 01 01 05/18/2012 01 02a 05/18/2012 01 02b 05/18/2012 01 03 05/18/2012 01 04 05/18/2012 01 05 05/18/2012 01 06 05/18/2012 In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (1)
- · Z (O) $600
1910.178 L01 I
- Issued
- Mar 12, 2012
- Abate by
- May 18, 2012
- Penalty
- Initial $3,000 · Current $1,500 Reduced
General-duty citation text
29 CFR 1926.602(d): Note: The requirements applicable to construction work under paragraph (d) of this section are identical to those set forth at paragraph (l) of 29 CFR 1910.178: 29 CFR 1910.178(l)(1)(i): The employer did not ensure that each powered industrial truck operator was competent to operate a powered industrial truck safely, as demonstrated by the successful completion of the training and evaluation specified in this paragraph (l): a) The employer did not train and evaluate employees operating the Lull 1044C-54 all terrain forklift. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (2)
- · I (S) $1500
- · Z (S) $3000
1926.451 C02
- Issued
- Mar 12, 2012
- Abate by
- May 18, 2012
- Penalty
- Initial $3,000 · Current $1,500 Reduced
General-duty citation text
29 CFR 1926.451(c)(2): Supported scaffold poles, legs, posts, frames, and uprights did not bear on base plates and mud sills or other adequate firm foundation: a) The scaffold that the employees were working from did not bear on base plates. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (2)
- · I (S) $1500
- · Z (S) $3000
1926.451 C02 II
- Issued
- Mar 12, 2012
- Abate by
- May 18, 2012
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.451(c)(2)(ii): Unstable objects were used to support scaffolds or platform units: a) Employees were performing masonry work from tubular welded frame scaffolding that was supported by unstable objects. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (2)
- · I (S) $0
- · Z (S) $0
1926.451 G01
- Issued
- Mar 12, 2012
- Abate by
- May 18, 2012
- Penalty
- Initial $4,200 · Current $2,100 Reduced
General-duty citation text
29 CFR 1926.451(g)(1): Each employee on a scaffold more than 10 feet above a lower level was not protected from falling to that lower level. a) Employees were exposed to the hazard of falling approximately 40 feet to the ground, while performing masonry work from tubular welded frame scaffold platform. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
- · I (S) $2100
- · Z (S) $4200
1926.501 B01
- Issued
- Mar 12, 2012
- Abate by
- May 18, 2012
- Penalty
- Initial $4,200 · Current $2,100 Reduced
General-duty citation text
29 CFR 1926.501(b)(1): Each employee on a walking/working surface with an unprotected side or edge which was 6 feet (1.8 m) or more above a lower level was not protected from falling by the use of guardrail systems, safety net systems, or personal fall arrest systems: a) Employees engaged in masonry work were not protected from fall hazards of up to approximately 35 feet to the ground, while working along unprotected edge of the deck. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
- · I (S) $2100
- · Z (S) $4200
1926.501 B04 I
- Issued
- Mar 12, 2012
- Abate by
- May 18, 2012
- Penalty
- Initial $3,000 · Current $1,500 Reduced
General-duty citation text
29 CFR 1926.501(b)(4)(i): Each employee on walking/working surfaces was not protected from falling through holes (including skylights) more than 6 feet (1.8 m) above lower levels by personal fall arrest systems, covers or guardrail systems erected around such holes: a) Employees were not protected from the hazard of falling approximately 11 feet to the lower level while performing masonry work around unguarded floor holes. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (2)
- · I (S) $1500
- · Z (S) $3000
1926.503 A01
- Issued
- Mar 12, 2012
- Abate by
- May 18, 2012
- Penalty
- Initial $3,000 · Current $1,500 Reduced
General-duty citation text
29 CFR 1926.503(a)(1): The employer did not provide a training program for each employee who might be exposed to fall hazards: a) Employer did not provide training to each employee in order to recognize hazards associated with working at an elevation and to understand procedures to control or minimize those hazards. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (2)
- · I (S) $1500
- · Z (S) $3000
More inspections at AWR Developers, INC.
View AWR Developers, INC.'s full OSHA safety record →
More inspections in this industry (NAICS 238140)
More inspections in IL
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). OSHA publishes its own view of this case as inspection number 331906446.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.