HIALEAH, FL ·
OSHA Inspection: CINDERELLA HOLDINGS II, LLC
Programmed Related inspection · Safety discipline
At a glance
On , OSHA opened a programmed Related safety inspection of CINDERELLA HOLDINGS II, LLC in 1054 W 23 ST., HIALEAH, FL 33012 (NAICS 238140). OSHA activity number 334693785.
OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- CINDERELLA HOLDINGS II, LLC
- Site address
- 1054 W 23 ST.
- City
- HIALEAH
- State
- FL
- ZIP
- 33012
- Mailing
- 2335 WEST 12TH AVENUE, HIALEAH, FL 33010
What kind of inspection was it?
- Inspection type
- Programmed Related (J)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238140
- Employees
- 5
- Ownership type
- A
Citations
7 citations on file for this inspection.
1926.95 A
- Issued
- Oct 1, 2012
- Abate by
- Oct 2, 2012
- Penalty
- Initial $1,600 · Current $800 Reduced
General-duty citation text
29 CFR 1926.95(a): Protective equipment, including personal protective equipment for eyes, face, head, and extremities, protective clothing, respiratory devices, and protective shields and barriers, were not provided: On or about June 14, 2012, employees were observed working without hard hats.
Recent events (2)
- · I (S) $800
- · Z (S) $1600
1926.451 B01
- Issued
- Oct 1, 2012
- Abate by
- Oct 2, 2012
- Penalty
- Initial $2,000 · Current $1,000 Reduced
General-duty citation text
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii) On or about June14, 2012, an employee was observed applying stucco from a scaffold that was not fully planked at approximately 25 feet above the ground.
Recent events (2)
- · I (S) $1000
- · Z (S) $2000
1926.451 E01
- Issued
- Oct 1, 2012
- Abate by
- Oct 2, 2012
- Penalty
- Initial $2,000 · Current $1,000 Reduced
General-duty citation text
29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from another scaffold, structure, personnel hoist, or similar surface was not used: On or about June 14, 2012 employees were observed accessing the scaffold using the cross braces.
Recent events (2)
- · I (S) $1000
- · Z (S) $2000
1926.451 G04 I
- Issued
- Oct 1, 2012
- Abate by
- Oct 2, 2012
- Penalty
- Initial $2,000 · Current $1,000 Reduced
General-duty citation text
29 CFR 1926.451(g)(4)(i): Guardrail systems were not installed along all open sides and ends of platforms. On or about June 14,2012, an employee was observed applying stucco from a scaffold without guardrails at approximately 25 feet above the ground.
Recent events (2)
- · I (S) $1000
- · Z (S) $2000
1926.451 H02 II
- Issued
- Oct 1, 2012
- Abate by
- Oct 9, 2012
- Penalty
- Initial $1,600 · Current $800 Reduced
General-duty citation text
29 CFR 1926.451(h)(2)(ii): A toeboard was not erected along the edge of platforms more than 10 feet (3.1 m) above lower levels for a distance sufficient to protect employees below: On or about June 14, 2012, employees were observed working from multiple levels of a scaffold that was missing toe boards.
Recent events (2)
- · I (S) $800
- · Z (S) $1600
1926.452 C02
- Issued
- Oct 1, 2012
- Abate by
- Oct 2, 2012
- Penalty
- Initial $2,000 · Current $1,000 Reduced
General-duty citation text
29 CFR 1926.452(c)(2): Tubular welded frames and panels were not braced by cross, horizontal, or diagonal braces, or combination thereof, which would have secured vertical members together laterally: On or about June 14, 2012, employees were observed working from a scaffold that was missing cross braces.
Recent events (2)
- · I (S) $1000
- · Z (S) $2000
1926.451 C02
- Issued
- Oct 1, 2012
- Abate by
- Oct 9, 2012
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.451(c)(2): Supported scaffold poles, legs, posts, frames, or uprights did not bear on base plates, mud sills or other adequate firm foundation: On or about June 14, 2012, employees were observed working from a scaffold where the poles were supported by varying objects including but not limited to pieces of scrap wood.
Recent events (2)
- · I (O) $0
- · Z (O) $0
More inspections in this industry (NAICS 238140)
More inspections in FL
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 334693785.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.