PHILADELPHIA, PA ·
OSHA Inspection: DORRIAN MASONRY
Unprogrammed Other inspection · Safety discipline
At a glance
On , OSHA opened an unprogrammed Other safety inspection of DORRIAN MASONRY in 409-11-13 MANTON STREET, PHILADELPHIA, PA 19147 (NAICS 238140). OSHA activity number 334827383.
OSHA opens inspections for many reasons: routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- DORRIAN MASONRY
- Site address
- 409-11-13 MANTON STREET
- City
- PHILADELPHIA
- State
- PA
- ZIP
- 19147
- Mailing
- 6124 GIRARD AVENUE, PHILADELPHIA, PA 19151
What kind of inspection was it?
- Inspection type
- Unprogrammed Other (I)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238140
- Employees
- 3
- Ownership type
- A
Citations
6 citations on file for this inspection.
1926.451 F06
- Issued
- Dec 20, 2012
- Abate by
- Dec 27, 2012
- Penalty
- Initial $2,000 · Current $2,000
General-duty citation text
29 CFR 1926.451(f)(6): Scaffolds were erected, used, dismantled, altered, or moved such that they, or any conductive material handled on them, could have come closer than the minimum distances established for specific voltages as set forth in the table in subparagraph (f)(6). Note: Specify distances as indicated in table in paragraph (f)(6) of this section. a) Jobsite - 409-11-13 Manton Street -The clearance between the tubular welded frame scaffold and the insulated Tri-plex type overhead power lines was less than three (3) feet potentially exposing employees to electrical hazards. Observed on or about 6/22/12. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement
Recent events (1)
- · Z (S) $2000
1926.451 B01
- Issued
- Dec 20, 2012
- Abate by
- Dec 27, 2012
- Penalty
- Initial $4,000 · Current $4,000
General-duty citation text
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds shall be fully planked or decked between the front uprights and the guardrail supports as follows: a) Jobsite: 409-11-13 Manton Street, Philadelphia, PA- the working platforms on the tubular welded frame scaffold were missing planks. Employees were performing masonry operations up to 19.5 feet above ground level. Observed on or about 06/22/12. DORIAN MASONRY WAS PREVIOUSLY CITED FOR THIS OCCUPATIONAL SAFETY AND HEALTH STANDARD WHICH WAS CONTAINED IN OSHA INSPECTION #315819383, CITATION 1 ITEM 1 AND WAS AFFIRMED AS A FINAL ORDER ON JUNE 15, 2011 WITH RESPECT TO THE WORKSITE LOCATED AT 8TH & CHRISTIAN STS., PHILADELPHIA, PA. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (1)
- · Z (R) $4000
1926.451 E01
- Issued
- Dec 20, 2012
- Abate by
- Dec 27, 2012
- Penalty
- Initial $4,000 · Current $4,000
General-duty citation text
29 CFR 1926.451(e)(1): When scaffold platforms are more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from another scaffold, structure, personnel hoist, or similar surface shall be used. Crossbraces shall not be used as a means of access. a) Jobsite: 409-11-13 Manton Street, Philadelphia, PA- the tubular welded scaffold did not have any portable ladders or other means of access to the working levels of the scaffold. Observed on or about 06/22/12. DORIAN MASONRY WAS PREVIOUSLY CITED FOR THIS OCCUPATIONAL SAFETY AND HEALTH STANDARD WHICH WAS CONTAINED IN OSHA INSPECTION #315819383, CITATION 1 ITEM 3 AND WAS AFFIRMED AS A FINAL ORDER ON JUNE 15, 2011 WITH RESPECT TO THE WORKSITE LOCATED AT 8TH & CHRISTIAN STS., PHILADELPHIA, PA. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (1)
- · Z (R) $4000
1926.451 C01
- Issued
- Dec 20, 2012
- Abate by
- Dec 27, 2012
- Penalty
- Initial $3,200 · Current $3,200
General-duty citation text
29 CFR 1926.451(c)(1): Supported scaffolds with a height to base width (including outrigger supports, if used) ratio of more than four to one (4:1) were not restrained from tipping by guying, tying, bracing, or equivalent means: a) Jobsite: 409-11-13 Manton Street, Philadelphia, PA- the working platforms on the tubular welded frame scaffold were up to 26 feet high and the working levels were up to 19.5 feet, performing masonry operations. There were no restraints to prevent the scaffold from tipping. Observed on or about 06/22/12. DORIAN MASONRY WAS PREVIOUSLY CITED FOR THIS OCCUPATIONAL SAFETY AND HEALTH STANDARD WHICH WAS CONTAINED IN OSHA INSPECTION #315819383, CITATION 1 ITEM 2 AND WAS AFFIRMED AS A FINAL ORDER ON JUNE 15, 2011 WITH RESPECT TO THE WORKSITE LOCATED AT 8TH & CHRISTIAN STS., PHILADELPHIA, PA. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (1)
- · Z (R) $3200
1926.451 G01 VII
- Issued
- Dec 20, 2012
- Abate by
- Dec 27, 2012
- Penalty
- Initial $4,000 · Current $4,000
General-duty citation text
29 CFR 1926.451(g)(1)(vii): For all scaffolds not otherwise specified in paragraphs (g)(1)(i) through (g)(1)(vi) of this section, each employee was not protected by the use of personal fall arrest systems or guardrail systems meeting the requirements of paragraph (g)(4) of this section. a) Jobsite - 409-11-13 Manton Street- Employees, performing bricklaying and stucco operations from a tubular welded frame scaffold, were exposed to a fall hazard of approximately 13 feet where adequate means of fall protection was not utilized. On or about 06/22/12. DORIAN MASONRY WAS PREVIOUSLY CITED FOR THIS OCCUPATIONAL SAFETY AND HEALTH STANDARD WHICH WAS CONTAINED IN OSHA INSPECTION #315819383, CITATION 1 ITEM 5a AND WAS AFFIRMED AS A FINAL ORDER ON JUNE 15, 2011 WITH RESPECT TO THE WORKSITE LOCATED AT 8TH & CHRISTIAN STS., PHILADELPHIA, PA. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (1)
- · Z (R) $4000
1926.454 A
- Issued
- Dec 20, 2012
- Abate by
- Dec 27, 2012
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.454(a): The employer did not have each employee who performed work while on a scaffold trained by a person qualified in the subject matter to recognize the hazards associated with the type of scaffold being used and to understand the procedures to control or minimize those hazards: a) Jobsite: 403-11-13 Manton St, Philadelphia, PA. - On or about 06/22/12, employees were not trained to recognize the hazards associated with their work while working from a supported tubular welded frame scaffold. DORIAN MASONRY WAS PREVIOUSLY CITED FOR THIS OCCUPATIONAL SAFETY AND HEALTH STANDARD WHICH WAS CONTAINED IN OSHA INSPECTION #315819383, CITATION 1 ITEM 5b AND WAS AFFIRMED AS A FINAL ORDER ON JUNE 15, 2011 WITH RESPECT TO THE WORKSITE LOCATED AT 8TH & CHRISTIAN STS., PHILADELPHIA, PA. Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (1)
- · Z (R) $0
More inspections at Dorrian Masonry
View Dorrian Masonry's full OSHA safety record →
More inspections in this industry (NAICS 238140)
More inspections in PA
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 334827383.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.