OSHA Inspection: LATINO CONSTRUCTION

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of LATINO CONSTRUCTION in 1022-1024 FAIRMOUNT AVE, PHILADELPHIA, PA 19123 (NAICS 238140). OSHA activity number 335136180.

Watch Latino Construction — free Get an email when a new federal OSHA severe-injury report for Latino Construction is published. One employer, no account, unsubscribe in one click.
Establishment
LATINO CONSTRUCTION
Site address
1022-1024 FAIRMOUNT AVE
City
PHILADELPHIA
State
PA
ZIP
19123
Mailing
729 W. RITNER ST, PHILADELPHIA, PA 19184
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238140
Employees
4
Ownership type
A

4 citations on file for this inspection.

1926.451 G04 I

Serious Gravity 10 1 instance 2 exposed
Issued
Penalty
Initial $2800.00 · Current $1500.00 Reduced
29 CFR 1926.451(g)(4)(i):     Guardrail systems were not installed along all open sides and ends of platforms before being released for use by employees other than erection/dismantling crews:      a) Jobsite-1022-1024 Fairmount Ave, Philadelphia, PA- Employees were performing stucco work at approximately 18 ft. above ground level from a tubular welded scaffold which did not have the guardrails along all open sides.  Observed on or about 6/15/12.    NOTE: No abatement certification or documentation required.
Recent events (2)
  • — I (S) $1500
  • — Z (S) $2800

1926.451 B01 I

Serious Gravity 10 1 instance 2 exposed
Issued
Penalty
Initial $0.00 · Current $0.00
29 CFR 1926.451(b)(1)(i):     Each platform unit (e.g., scaffold plank, fabricated plank, fabricated deck, or fabricated platform) was not installed so that the space between adjacent units and the space between the platform and the uprights were no more than 1 inch (2.5 cm) wide, except where the employer can demonstrate that a wider space is necessary.    a) Jobsite-1022-1024 Fairmount Ave, Philadelphia, PA- Employees were performing stucco work at approximately 18 ft. above ground level from a tubular welded scaffold which was not fully planked.  Observed on or about 6/15/12.    NOTE: No abatement certification or documentation required.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.451 E01

Serious Gravity 5 1 instance 2 exposed
Issued
Penalty
Initial $0.00 · Current $0.00
29 CFR 1926.451(e)(1):     When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, sturcure, personnel hoist, or similar surface was not used.  Crossbraces were used as a means of access.      a) Jobsite-1022-1024 Fairmount Ave, Philadelphia, PA- Employees were performing stucco work at approximately 18 ft. above ground level from a tubular welded scaffold that did not have a means of access such as a ladder.  Observed on or about 6/15/12.    Note: No abatement certification or documentation required.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.454 A

Other-than-serious 1 instance 2 exposed
Issued
Abate by
Penalty
Initial $0.00 · Current $0.00
29 CFR 1926.454(a):     The employer shall have each employee who performs work while on a scaffold trained by a person qualified in the subject matter to recognize the hazards associated with the type of scaffold being used and to understand the procedures to control or minimize those hazards. The training shall include the following areas, as applicable:    a) Jobsite-1022-1024 Fairmount Ave, Philadelphia, PA- Employees were performing stucco work at approximately 18 ft. above ground level from a tubular welded scaffold without scaffold safety training. Observed on or about 6/15/12.    Note:Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement